Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (January 2025)

ND/2019/01

(a)          Drainage works, watermain works, sheet piling and slope works in Portion 1a

(b)         Site formation, watermain works and construction of noise barrier, ELS construction, sewage works, backfill and road works in Portion 1c

(c)          Site formation, construction of subway, drainage works, road works, slope works and soil nail in Portion 2

(d)         HAC soil treatment, watermain works, drainage works and sheet piles in Portion 3

(e)          Site formation, watermain works, drainage works and sewage works in Portion 5

(f)          Backfilling, drainage works, watermain works, slope works, road works, district cooling system, and road light works in Portion 6a

(g)         Operation of HAC soil treatment facility in Portion 6b

(h)         Excavation, watermain works, sewage works, road works and drainage works in Portion 7

(i)           Road pavement construction, RC construction of fresh water service reservoir, drainage works, watermain works and backfilling works in Portion 8a

(j)           Trenchless work, watermain construction and ELS construction in Portion 8b

(k)         Sheet piling, excavation, drainage works, watermain works and district cooling system in Portion 9b

(l)           No activity in Portion 11b this month

(m)       Stockpile of soil in Portion 13

ND/2019/02

(a)           Backfilling

(b)           Excavation

(c)            Concreting

(d)           Cut and Fill of Slope

(e)            Sheet Piling

(f)            Pipe Jacking

(g)           Pipe laying and bedding

(h)           Grouting

ND/2019/03

(a)          Portion 2 to Portion 20C

-      Defect Rectification of Lodging Facility

ND/2019/04

(a)           Back Filling

(b)           Excavation

(c)           Grouting

(d)           Road works

(e)           Formwork and Scaffolding Erection

(f)            Rebar Fixing

(g)           ELS

ND/2019/05

(a)          South Team

-          BBI Toilet ¡V Roof slab was casted on 9 Jan 2025.

-          Lift LT01 ¡V Installation of louvre and glasses completed. Installation of E&M items in progress.

-          Lift LT02 ¡V Concreting works completed on 08 Jan 2025

-          FW54 ¡V Plate Load Test was carried out and completed on 7 Jan 2025.

-          Sign Gantry FT1 ¡V Excavation completed. Footing in progress.

-          E4 Retaining Wall ¡V Construction of wall in progress.

-          E4 Ramp Utrough ¡V Bay 17-18 blinding layer casted on 6 Jan 2025. Bay 17 footing is targeted to complete in mid Jan 2025.

-          D2-03 Drainage Reinstatement ¡V Manholes and drain pipes laying are in progress.

-          Noise barrier NB109

A.     Bay 14 ¡V Wall completed on 11 December 2024.

B.      Bay 15, 16 ¡V Plate load test at Bay 15 completed. Bay 15 Footing target completion in end of Jan 2025.

C.      Bay 19, 20 ¡V Excavation completed. Footing target completion on 13 Jan 2025.

-          Noise barrier NB70

A.         Bay 2 to 6 ¡V Footing and stem wall are completed.

B.          Bay 1 ¡V Footing completed. Construction of stem wall is in progress.

-          Noise barrier NB69

A.         Bay 1, 2 ¡V Bay 2b wall construction is resumed after Bridge E4 segment erection.

B.          Bay 8a ¡V Backfilling to formation in progress.

-          Noise barrier NB110

A.         Bay 10 ¡V Pile caps PC1 and PC2 were completed. Construction of wall in progress.

-          Noise barrier NB 29 Through Bay 6-15

A.         Footing is 100% completed

B.          Wall (exclude parapet) is 90% completed. Parapet section will cast after backfilling to formation.

-          Noise barrier NB 30

A.         NB30 Predrilling works (28/28 nos) completed on 03 Jan 2025

B.          Pre-bored Socket H pile construction (70/219 nos) completed.

-          Noise barrier NB 77

A.         Pre-bored Socket H pile construction (16/16 nos) completed 27 Dec 2024.

-              Fabrication of Sign Gantry ¡V DS19 and DS20 under fabrication.

-              Fabrication of Noise Barrier ¡V NB32 and NB109 under fabrication.

(b)         North Team

-          Dismantling of truss at B2-01 cross head completed.

-          B1 abutment wall completed.

-          Reinstatement works & footpath in progress in C4-02 (HD)

-          C3-03b & C3-04b for viaduct drainage & water works completed.

-          viaduct drainage & water works at C4-01B in progress.

-          Backfilling of C3-04a, C2-01, C1-02a, C1-01b & E2-01 in progress. C1-02a completed.

-          JCR: Construction of new central median & ducting works for traffic signal & road light were completed of 90%.

-          JCR & Tong Hang Village J/O improvement works (FS 25): slope works 90 % completed.

-          JCR & Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal & road light was in progress ( 95 % completed).

-          JCR near F63 ¡V Breaking of temporary pavement was in progress.

(c)          Bridges and Structures

-          All 116 Type C segments casted in DongGuan Casting yard.

-          All Type A segment fabrication completed. Total 780 segments were delivered to site, and total 774 segments erected.

-          C1-01 to B2-03 end span segment erection by LG completed, and LG will be launched to B1-02.

-          Total 1347 pcs of parapet-skin fabricated; 1089 pcs of parapet skin erected.

-          Installation of deck void drainage at Bridge C1,C2 in progress.

-          Segment erection at Bridge E4 completed.

-          Reinstate of lifting tower NF83A in progress.

-          D2-04 end span segment erection in progress.

-          Total 18 nos. of movement joint installation in progress.

-          Bridge deck water proofing material of bridge D1&E1 arrived.

(d)         Form Traveler

-              Form traveller at 9th pair segment at E3-04 in progress.

-              Form traveller at 11th pair segment at D2-01 in progress

-              Mid stitching between E2-01 & E2-02 completed

-              Mid stitching between E3-02 & E3-01 completed.

-              Dismantling of form traveller at E3-02 completed.

-              Completed concreting E3-E3-04-E3-03-S06 & E3-E3-04-E3-05-S06, E3-E3-04-E3-03-S07 & E3-E3-04-E3-05-S07. E3-E3-04-E3-03-S08 & E3-E3-04-E3-05-S08. D2-D2-01-D2-02-S08 & D2-D2-01-D1-04-S08. D2-D2-01-D2-02-S09 & D2-D2-01-D1-04-S09. D2-D2-01-D2-02-S10 & D2-D2-01-D1-04-S10.

ND/2019/06

The construction phase was completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)            Road works at Portion 1, 4 and 5

(b)           C&D waste disposal at Portion 1, 2 and 4

(c)            Drainage works, Sewerage works at Portion 1, 2, 3 and 4

(d)           Filling works at Portion 2 and 4

(e)            Construction of site haul road at Portion 4

(f)            Waterworks at Portion 1, 2 and 4

(g)           Construction of noise barrier at Portion 4