Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract No. |
Site Activities (January
2025) |
ND/2019/01 |
(a)
Drainage
works, watermain works,
sheet piling and slope works
in Portion 1a (b)
Site
formation, watermain works and
construction of noise barrier, ELS construction, sewage
works, backfill and road works in
Portion 1c (c)
Site
formation, construction of subway, drainage
works, road
works, slope works and soil nail in
Portion 2 (d)
HAC soil treatment, watermain works,
drainage works and
sheet piles in Portion 3 (e)
Site
formation, watermain works, drainage works and sewage
works in Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road works,
district cooling system,
and road light works in
Portion 6a (g)
Operation
of HAC soil
treatment facility in Portion 6b (h)
Excavation, watermain works, sewage works, road works and
drainage works
in Portion 7 (i)
Road pavement
construction, RC construction of fresh
water service reservoir,
drainage works, watermain works and backfilling works in Portion 8a (j)
Trenchless
work, watermain
construction and ELS construction in
Portion 8b (k)
Sheet
piling, excavation, drainage works, watermain works and district cooling system in
Portion 9b (l)
No activity in Portion 11b
this month (m)
Stockpile of soil
in Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
(a)
Portion 2
to Portion 20C - Defect Rectification of Lodging Facility |
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding Erection (f)
Rebar Fixing (g)
ELS |
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V Roof slab was casted on 9 Jan 2025. -
Lift LT01
¡V Installation of louvre and glasses completed. Installation of E&M items
in progress. -
Lift LT02
¡V Concreting works completed on 08 Jan 2025 -
FW54 ¡V
Plate Load Test was carried out and completed on 7 Jan 2025. -
Sign
Gantry FT1 ¡V Excavation completed. Footing in progress. -
E4
Retaining Wall ¡V Construction of wall in progress. -
E4 Ramp Utrough ¡V Bay 17-18 blinding layer casted on 6 Jan 2025.
Bay 17 footing is targeted to complete in mid Jan 2025. -
D2-03
Drainage Reinstatement ¡V Manholes and drain pipes laying are in progress. -
Noise
barrier NB109 A.
Bay 14 ¡V
Wall completed on 11 December 2024. B.
Bay 15,
16 ¡V Plate load test at Bay 15 completed. Bay 15 Footing target completion in
end of Jan 2025. C.
Bay 19,
20 ¡V Excavation completed. Footing target completion on 13 Jan 2025. -
Noise
barrier NB70 A.
Bay 2 to
6 ¡V Footing and stem wall are completed. B.
Bay 1 ¡V
Footing completed. Construction of stem wall is in progress. -
Noise
barrier NB69 A.
Bay 1, 2
¡V Bay 2b wall construction is resumed after Bridge E4 segment erection. B.
Bay 8a ¡V
Backfilling to formation in progress. -
Noise
barrier NB110 A.
Bay 10 ¡V
Pile caps PC1 and PC2 were completed. Construction of wall in progress. -
Noise
barrier NB 29 Through Bay 6-15 A.
Footing
is 100% completed B.
Wall (exclude
parapet) is 90% completed. Parapet section will cast after backfilling to
formation. -
Noise barrier NB 30 A.
NB30
Predrilling works (28/28 nos) completed on 03 Jan
2025 B.
Pre-bored
Socket H pile construction (70/219 nos) completed. -
Noise barrier NB 77 A.
Pre-bored
Socket H pile construction (16/16 nos) completed 27
Dec 2024. -
Fabrication
of Sign Gantry ¡V DS19 and DS20 under fabrication. -
Fabrication
of Noise Barrier ¡V NB32 and NB109 under fabrication. (b)
North
Team -
Dismantling
of truss at B2-01 cross head completed. -
B1
abutment wall completed. -
Reinstatement
works & footpath in progress in C4-02 (HD) -
C3-03b
& C3-04b for viaduct drainage & water works completed. -
viaduct
drainage & water works at C4-01B in progress. -
Backfilling
of C3-04a, C2-01, C1-02a, C1-01b & E2-01 in progress. C1-02a completed. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 90%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 90 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting
works for traffic signal & road light was in progress ( 95 % completed). -
JCR near
F63 ¡V Breaking of temporary pavement was in progress. (c)
Bridges
and Structures -
All 116 Type C segments
casted in DongGuan Casting yard. -
All Type A segment
fabrication completed. Total 780 segments were delivered to site, and total
774 segments erected. -
C1-01 to B2-03 end span
segment erection by LG completed, and LG will be launched to B1-02. -
Total 1347 pcs of
parapet-skin fabricated; 1089 pcs of parapet skin erected. -
Installation of deck void
drainage at Bridge C1,C2 in progress. -
Segment erection at Bridge
E4 completed. -
Reinstate of lifting tower
NF83A in progress. -
D2-04 end span segment
erection in progress. -
Total 18 nos. of movement
joint installation in progress. -
Bridge deck water proofing
material of bridge D1&E1 arrived. (d)
Form Traveler -
Form traveller at 9th
pair segment at E3-04 in progress. -
Form traveller at 11th
pair segment at D2-01 in progress -
Mid
stitching between E2-01 & E2-02 completed -
Mid
stitching between E3-02 & E3-01 completed. -
Dismantling
of form traveller at E3-02 completed. -
Completed
concreting E3-E3-04-E3-03-S06 & E3-E3-04-E3-05-S06, E3-E3-04-E3-03-S07
& E3-E3-04-E3-05-S07. E3-E3-04-E3-03-S08 & E3-E3-04-E3-05-S08.
D2-D2-01-D2-02-S08 & D2-D2-01-D1-04-S08. D2-D2-01-D2-02-S09 &
D2-D2-01-D1-04-S09. D2-D2-01-D2-02-S10 & D2-D2-01-D1-04-S10. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2 and 4 (c)
Drainage works, Sewerage works at Portion 1, 2, 3 and 4 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at Portion 4 (f)
Waterworks at Portion 1, 2 and 4 (g)
Construction
of noise barrier at Portion 4 |