Table 10.4 Photographic Records and Implementation Status of
Measures
EP No. |
Condition |
Photographic
Record |
Implementation
Status |
EP-466/2013/A |
2.9 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m
high solid dull green site barrier fences shall be erected around all active
works areas. |
^[1] |
EP-467/2013/A |
2.9 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m
high solid dull green site barrier fences shall be erected around all active
works areas. |
^[1] |
EP-468/2013/A |
2.11 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas. |
^[1] |
EP-469/2013 |
2.7 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas. |
^[1] |
EP-473/2013/A |
2.13 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas. |
^[1] |
EP-475/2013/A |
2.7 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas. |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance
of mitigation measure · Non-compliance
but rectified by the contractor N/A Not Applicable at this stage as no such
site activities were conducted in the reporting period |
Remark:
[1]: Barrier fences might be
subjected to change according to the phasing plan designed at detailed design
stage