2.1
The Kwu Tung North
(KTN) and Fanling North (FLN) New Development Areas
(NDAs) are one of the important sources of land and housing supply in the
medium and long term. The development of the KTN and FLN NDAs will be
implemented in phase for full completion by 2031. The Phase 1 of the NDAs development,
comprising the Advance Works and First Stage Works, is targeted to be
implemented from the second half of 2019 progressively. The Advance and First
Stage Works would include site formation, engineering infrastructure works
(including roads, drainage, sewerage, waterworks, landscaping works, pumping
stations, and fresh water and flushing water service reservoirs), soil
remediation, reprovisioning of North District Temporary Wholesale Market,
development of a nature park at Long Valley and implementation of environmental
mitigation measures.
2.2
The scope of works under the Advance and First
Stage Works comprises the following:
a)
The Advance Works (PWP item No. 7747CL-2)
consist of:
i)
site formation of land (including soil
remediation) in KTN and FLN NDAs for housing, community facilities and
engineering infrastructure;
ii)
construction of roads including the eastern
section of Fanling Bypass (FLBP(E)) connecting the
FLN NDA to Fanling Highway and other roads with
footpaths and cycle tracks, and associated junction/ road improvements;
iii)
engineering infrastructure works including
drainage. Sewerage (including two sewage pumping
stations), waterworks (including a fresh water service reservoir and a flushing
water service reservoir in the KTN NDA), landscape works and slopeworks;
iv)
part expansion and upgrading of Shek Wu Hui
Sewage Treatment Works (SWHSTW);
v)
reprovisioning works; and
vi)
implementation of environmental mitigation
measures and environmental monitoring and audit (EM&A) programme
for the works mentioned in (i) to (v) above.
b)
The First Stage Works (PWP item No. 7759CL)
consist of:
i)
development of a nature park at Long Valley
including provision of a visitor centre and a
footbridge spanning across Sheung Yue River for connection between these two
facilities;
ii)
reprovisioning of two egretry
sites in the FLN NDA and enhancement works to an existing egretry
site in the KTN NDA;
iii)
site formation of land for a village resite area and a district police
station in the KTN NDA;
iv)
engineering infrastructure works including
roads, drainage, sewerage, waterbirds, and landscape works; and
v)
implementation of environmental mitigation
measures and environmental monitoring and audit (EM&A) programme
for the works mentioned in (i) to (iv) above.
2.3
The Project which covers KTN and FLN NDAs is a
designated project (DP) under Schedule 3 of the Environmental Impact Assessment
(EIA) Ordinance (Cap. 499). In October 2013, the EIA Report (AEIAR-175/2013)
for the Project was approved by the Director of Environmental Protection
pursuant to the EIA Ordinance. The relevant EPs under the Project and the
respective Work Contracts are summarised in Tables 2.1a and 2.1.b.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP
No. |
Designated
Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
¡@ |
|||||||
Kwu
Tung North New Development Area Road P1 and P2 and Associated New Kwu Tung Interchange and Pak Shek Au Interchange
Improvement |
ü |
¡@ |
|||||||
Kwu
Tung North New Development Area Road D1 to D5 |
ü |
ü |
¡@ |
||||||
Sewage Pumping Stations in Kwu
Tung North New Development Area |
ü |
¡@ |
|||||||
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
|||||||
Fanling
Bypass Eastern Section |
ü |
ü |
ü |
¡@ |
|||||
Reprovision of temporary Wholesale Market in Fanling North New Development Area |
ü |
¡@ |
|||||||
EP-546/2017 |
Fanling
North Temporary Sewage Pumping Station |
ü |
¡@ |
Notes:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope of Works under concerned EP
Environmental Permit (EP)
No. |
Work Contract(s) |
Scope of Works under
concerned EP(s) |
Site Layout Plan under
concerned EP(s) |
EP-466/2013/A(Part) |
C1 |
Realign Castle Peak Road and join with the
Pak Shek Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction of new primary distributor road
(P1) within Kwu Tung North New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction of new primary distributor
roads (D1, D3, D4 and part of D5) within Kwu Tung
North New Development Area |
Figure 14 |
C3 |
Development of a nature park at Long Valley
and ecological mitigation and enhancement works for the nature park (Condition
2.9) |
Figure 15 |
|
EP-469/2013(Part) |
C2 |
Construction of one sewage pumping station
in Kwu Tung North with installed capacity of more
than 2,000 m3 per day |
Figure 16 |
EP-470/2013/A(Part) |
C1 |
Construction of service reservoir and
watermain for the reuse of treated sewage effluent for reuse in Kwu Tung North Development Areas |
Figure 17 |
EP-473/2013/A(Part) |
C3 |
Establishment
of alternative egretry sites and enhance the existing egretry
site at Ho Sheung Heung and/or its vicinity (Condition 2.7) |
Figure 18 |
EP-473/2013/A(Part) |
C5A |
Construction of new district distributor
inside FLN NDA, which provides a linkage between the Man Kam To Road and the proposed Fanling
Bypass Eastern Section |
Figure 19 |
EP-473/2013/A(Part) |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The re-provisioned wholesale market will
have approximately 1,000 market stalls within a site area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a temporary sewage
pumping station in Fanling North with installed
capacity (average dry weather flow) of about 3,600m3/day |
Figure 22 |
Remark:
The EP(s) not related to the Project of the First Phase of the Kwu
Tung North (KTN) and Fanling North (FLN) New
Development Area (NDA) Development Areas are not included in the Table.
2.4
The site boundary of the Project and all Works
Contracts are shown in Drawing No. 1.
2.5
The required submissions and submission status
under Environmental Permits are shown in Appendix
U.
2.6
The site layout plans under concerned Environmental Permits are shown in Figures 12 - 22.
2.7
Different parties with different levels of
involvement in the Project organisation include:
Project Proponent ¡V Civil Engineering and
Development Department (CEDD)
Supervisor / Supervisor's Representative ¡V AECOM Asia Co. Ltd.
Environmental Team (ET) ¡V Wellab
Limited
Independent Environmental Checker (IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The names and contact numbers of key personnel are summarised
in Table 2.2.
Table 2.2 Key Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
Civil Engineering and
Development Department, HKSAR (CEDD) |
Project Proponent |
Mr. Ryan Chau |
3797 5387 |
3547 1658 |
Supervisor
/ Supervisor's Representative (AECOM Asia Co. Ltd.) |
Chief
Resident Engineer |
Mr. Alan Lee |
6398 5982 |
2680 9515 |
Senior Resident Engineer |
Mr. King-man
Chan |
9651 2635 |
2680 9515 |
|
Environmental Team (Wellab Limited) |
Environmental Team Leader |
Dr. Priscilla Choy |
2898 7388 |
2898 7076 |
Independent Environmental
Checker (MottMac) |
Independent
Environmental Checker |
Mr. Thomas Chan |
2828 5967 |
2827 1823 |
Contract
No. ND/2019/01 Contractor (Build King ¡V Richwell Engineering Joint Venture) |
Site
Agent |
Mr. Ivan Leung |
9640
8340 |
-- |
Environmental
Officer |
Mr. Edward Tam |
9287
8270 |
||
Contract
No. ND/2019/02 Contractor (Chun Wo ¡V Kwan
Lee Joint Venture.) |
Site
Agent |
Mr. Andy Chan |
3485
9780 |
-- |
Environmental
Officer |
Mr. Sofi So |
9637
1667 |
||
Contract
No. ND/2019/03 Contractor (Sang Hing Kuly Joint Venture) |
Site
Agent |
Mr. Tang Wing Kai |
9300
7037 |
-- |
Environmental
Officer |
Mr. `Ken Cheung |
9803 5297 |
||
Contract
No. ND/2019/04 Contractor (Daewoo ¡V Chun
Wo ¡V Kwan Lee Joint Venture) |
Site
Agent |
Mr. Eric Wu |
9786 8630 |
-- |
Environmental
Officer |
Mr. Sam Lam |
6178 3179 |
||
Contract
No. ND/2019/05 Contractor (CRCC ¡V Paul Y.
Joint Venture) |
Site
Agent |
Mr. Darvin Lo |
9467 5891 |
-- |
Environmental
Manager |
Mr. Pan Fong |
9436 9435 |
||
Environmental
Officer |
Mr. Kevin Cheung |
6117 1344 |
||
Contract
No. ND/2019/06 Contractor (New Concepts
Engineering Development Ltd.) |
Project Manager |
Mr. Joe
Cheng |
9861
0060 |
-- |
Environmental
Officer |
Mr. Alex Choy |
6360 3236 |
||
Contract
No. ND/2019/07 Contractor (China Road and
Bridge Corporation) |
Site Agent |
Mr. Mac Chow |
9169 9567 |
-- |
Environmental
Manager |
Mr. K. M. Lui |
5113 8223 |
||
Environmental
Officer |
Ms. Sedo Sze |
5111 8018 |
Summary of
Construction Works Undertaken During Reporting Month
2.9
The major site activities undertaken in the
reporting month are shown in Table 2.3.
Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract No. |
Site Activities (February
2025) |
ND/2019/01 |
(a)
Drainage
works, watermain works, sheet piling and slope works in Portion 1a (b)
Site
formation, watermain works, ELS
construction, sewage works, backfill and road works in Portion 1c (c)
Site
formation, construction of subway, drainage works, road
works, slope works and soil
nail in Portion
2 (d)
HAC soil treatment, watermain works, drainage works and
sheet piles in
Portion 3 (e)
Site
formation, watermain works, drainage
works and DCS pipe work in
Portion 5 (f)
Backfilling,
drainage works, watermain works,
slope works, road works and district
cooling system in Portion 6a (g)
Operation
of HAC soil treatment facility in Portion 6b (h)
Excavation, watermain works, sewage works, road works and
drainage works in Portion 7 (i)
Road pavement
construction, RC
construction of fresh water service
reservoir,
drainage works, watermain works, backfilling, planting and metal works in
Portion 8a (j)
Trenchless
work, watermain construction and ELS construction in Portion 8b (k)
Sheet
piling, excavation, drainage
works,
watermain works and district cooling system in Portion 9b (l)
No activity in Portion 11b
this month (m)
Stockpile of soil in Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
(a)
Portion 2
to Portion 20C - Defect Rectification of Lodging Facility |
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding Erection (f)
Rebar Fixing (g)
ELS (h)
Backfilling |
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V Roof parapet wall was casted on 24 Jan 2025. -
Lift LT01
¡V Installation of E&M items was completed on 10
Feb 2025. Lift installation will commence on 13 Feb 2025. -
Lift LT02
¡V Concreting works completed on 08 Jan 2025 -
FW54 ¡V
Footing from CH0 to CH10 was casted on 06 Feb 2025. -
Sign
Gantry FT1 ¡V Footing on casted 18 Jan 2025. Backfilling work was also
completed. -
E4
Retaining Wall ¡V Construction of wall in progress. -
E4 Ramp Utrough ¡V Bay 17 and Bay 18 footing were casted on 17 Jan
2025 and 23 Jan 2025 respectively. -
D2-03
Drainage Reinstatement ¡V Manholes and drain pipes laying were completed. -
Noise
barrier NB109 A.
Bay 19
Footing was casted on 13 Jan 2025. B.
Bay 15,
16 ¡V Footings were casted on 18 Jan 2025 and 24 Jan 2025. -
Noise
barrier NB70 A.
Bay 1 ¡V
Stem wall was casted on 16 Jan 2025. B.
Bay 1 to
6 ¡V Backfilling in progress. -
Noise
barrier NB69 A.
Bay 2b ¡V
Stem wall was casted on 08 Feb 2025. B.
Bay 1, 2a
¡V Removal of temporary blinding and existing pavement in progress. -
Noise
barrier NB110 A.
Bay 10 ¡V
PC1 and PC2 stem wall completed and backfilling in progress. PC3 pile cap
excavation completed and construction in progress. -
Noise
barrier NB 29 Through Bay 6-15 A.
Footing
is 56% completed B.
Wall
(exclude parapet) is 45% completed. Parapet section will cast after
backfilling to formation. -
Noise barrier NB 30 A.
Pre-bored
Socket H pile construction (94/211 nos) completed. -
Noise barrier NB 77 A.
ELS works
for NB77 footing in progress. -
Fabrication
of Sign Gantry ¡V DS19 fabrication completed and delivered to site. DS20 fabrication
is 50% completed. -
Fabrication
of Noise Barrier ¡V NB32 and NB109 under fabrication. (b)
North
Team -
Reinstatement
works & footpath in progress in C4-02 (HD) -
C4-01B
for viaduct drainage & water works completed. -
Backfilling
of C2-01, C1-02a, C1-01b, D2-01 & E2-01 in progress. C3-04A & C1-02b
completed. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 90%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 90 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting
works for traffic signal & road light was in progress ( 95 % completed). -
JCR near
F63 ¡Vslope feature construction works in progress. (c)
Bridges
and Structures -
All of 116 type C segments
were casted in DongGuan casting yard and delivered
to site. Total 75 segment were erected. -
All of 791 type A segments
were casted in HuiZhou casting yard and delivered
to site. Total 781 segment were erected. -
LG launching to B1-02
completed, and the segment erection at pier B1-02 in progress. -
Total 1421 pcs of
parapet-skin fabricated; 1029 pcs of parapet skin erected. -
Installation of deck void
drainage at Bridge C1,C2 in progress. -
Reinstate of lifting tower
NF83A in progress. -
D2-04 end span segment
erection completed. -
Movement joint
installation for Bridge C4 in progress. -
Water proofing for Bridge
E1 in progress. -
Erection of sign gantry
ADS19 completed. -
Installation of railing in
progress. (d)
Form Traveler -
Mid
stitching between E3-04 & E3-03 completed. -
Mid
stitching between D2-01 & D2-02 in progress. -
Mid
stitching between E3-04 & E3-05 in progress. -
Dismantling
of form traveller at E3-04 D2-01 & E2-02 in
progress. -
Completed
concreting E3-E3-04-E3-03-S09 & E3-E3-04-E3-05-S09. D2-D2-01-D2-02-S11
& D2-D2-01-D1-04-S11. D2-D2-01-D1-04-S12. |
ND/2019/06 |
The construction phase was completed and handed
over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2 and 4 (c)
Drainage works, Sewerage works at Portion 1, 2, 3 and 4 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at Portion 4 (f)
Waterworks at Portion 1, 2 and 4 (g)
Construction
of noise barrier at Portion 4 |
Construction Programme
2.10 Copies of Contractors¡¦ construction programmes are provided in Appendix A.
Status of Environmental Licences,
Notifications and Permits
2.11
A summary of the relevant permits, licences, and/or notifications on environmental protection
for this Project is presented in Table
2.4.
Table 2.4 Status of Environmental
Licences, Notifications and Permits