Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (February 2025)

ND/2019/01

(a)          Drainage works, watermain works, sheet piling and slope works in Portion 1a

(b)         Site formation, watermain works, ELS construction, sewage works, backfill and road works in Portion 1c

(c)          Site formation, construction of subway, drainage works, road works, slope works and soil nail in Portion 2

(d)         HAC soil treatment, watermain works, drainage works and sheet piles in Portion 3

(e)          Site formation, watermain works, drainage works and DCS pipe work in Portion 5

(f)          Backfilling, drainage works, watermain works, slope works, road works and district cooling system in Portion 6a

(g)         Operation of HAC soil treatment facility in Portion 6b

(h)         Excavation, watermain works, sewage works, road works and drainage works in Portion 7

(i)           Road pavement construction, RC construction of fresh water service reservoir, drainage works, watermain works, backfilling, planting and metal works in Portion 8a

(j)           Trenchless work, watermain construction and ELS construction in Portion 8b

(k)         Sheet piling, excavation, drainage works, watermain works and district cooling system in Portion 9b

(l)           No activity in Portion 11b this month

(m)       Stockpile of soil in Portion 13

ND/2019/02

(a)           Backfilling

(b)           Excavation

(c)            Concreting

(d)           Cut and Fill of Slope

(e)            Sheet Piling

(f)            Pipe Jacking

(g)           Pipe laying and bedding

(h)           Grouting

ND/2019/03

(a)          Portion 2 to Portion 20C

-      Defect Rectification of Lodging Facility

ND/2019/04

(a)           Back Filling

(b)           Excavation

(c)           Grouting

(d)           Road works

(e)           Formwork and Scaffolding Erection

(f)            Rebar Fixing

(g)           ELS

(h)           Backfilling

ND/2019/05

(a)          South Team

-          BBI Toilet ¡V Roof parapet wall was casted on 24 Jan 2025.

-          Lift LT01 ¡V Installation of E&M items was completed on 10 Feb 2025. Lift installation will commence on 13 Feb 2025.

-          Lift LT02 ¡V Concreting works completed on 08 Jan 2025

-          FW54 ¡V Footing from CH0 to CH10 was casted on 06 Feb 2025.

-          Sign Gantry FT1 ¡V Footing on casted 18 Jan 2025. Backfilling work was also completed.

-          E4 Retaining Wall ¡V Construction of wall in progress.

-          E4 Ramp Utrough ¡V Bay 17 and Bay 18 footing were casted on 17 Jan 2025 and 23 Jan 2025 respectively.

-          D2-03 Drainage Reinstatement ¡V Manholes and drain pipes laying were completed.

-          Noise barrier NB109

A.     Bay 19 Footing was casted on 13 Jan 2025.

B.      Bay 15, 16 ¡V Footings were casted on 18 Jan 2025 and 24 Jan 2025.

-          Noise barrier NB70

A.       Bay 1 ¡V Stem wall was casted on 16 Jan 2025.

B.        Bay 1 to 6 ¡V Backfilling in progress.

-          Noise barrier NB69

A.         Bay 2b ¡V Stem wall was casted on 08 Feb 2025.

B.          Bay 1, 2a ¡V Removal of temporary blinding and existing pavement in progress.

-          Noise barrier NB110

A.         Bay 10 ¡V PC1 and PC2 stem wall completed and backfilling in progress. PC3 pile cap excavation completed and construction in progress.

-          Noise barrier NB 29 Through Bay 6-15

A.         Footing is 56% completed

B.          Wall (exclude parapet) is 45% completed. Parapet section will cast after backfilling to formation.

-          Noise barrier NB 30

A.         Pre-bored Socket H pile construction (94/211 nos) completed.

-          Noise barrier NB 77

A.         ELS works for NB77 footing in progress.

-              Fabrication of Sign Gantry ¡V DS19 fabrication completed and delivered to site. DS20 fabrication is 50% completed.

-              Fabrication of Noise Barrier ¡V NB32 and NB109 under fabrication.

(b)         North Team

-          Reinstatement works & footpath in progress in C4-02 (HD)

-          C4-01B for viaduct drainage & water works completed.

-          Backfilling of C2-01, C1-02a, C1-01b, D2-01 & E2-01 in progress. C3-04A & C1-02b completed.

-          JCR: Construction of new central median & ducting works for traffic signal & road light were completed of 90%.

-          JCR & Tong Hang Village J/O improvement works (FS 25): slope works 90 % completed.

-          JCR & Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal & road light was in progress ( 95 % completed).

-          JCR near F63 ¡Vslope feature construction works in progress.

(c)          Bridges and Structures

-          All of 116 type C segments were casted in DongGuan casting yard and delivered to site. Total 75 segment were erected.

-          All of 791 type A segments were casted in HuiZhou casting yard and delivered to site. Total 781 segment were erected.

-          LG launching to B1-02 completed, and the segment erection at pier B1-02 in progress.

-          Total 1421 pcs of parapet-skin fabricated; 1029 pcs of parapet skin erected.

-          Installation of deck void drainage at Bridge C1,C2 in progress.

-          Reinstate of lifting tower NF83A in progress.

-          D2-04 end span segment erection completed.

-          Movement joint installation for Bridge C4 in progress.

-          Water proofing for Bridge E1 in progress.

-          Erection of sign gantry ADS19 completed.

-          Installation of railing in progress.

(d)         Form Traveler

-              Mid stitching between E3-04 & E3-03 completed.

-              Mid stitching between D2-01 & D2-02 in progress.

-              Mid stitching between E3-04 & E3-05 in progress.

-              Dismantling of form traveller at E3-04 D2-01 & E2-02 in progress.

-              Completed concreting E3-E3-04-E3-03-S09 & E3-E3-04-E3-05-S09. D2-D2-01-D2-02-S11 & D2-D2-01-D1-04-S11. D2-D2-01-D1-04-S12.

ND/2019/06

The construction phase was completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)            Road works at Portion 1, 4 and 5

(b)           C&D waste disposal at Portion 1, 2 and 4

(c)            Drainage works, Sewerage works at Portion 1, 2, 3 and 4

(d)           Filling works at Portion 2 and 4

(e)            Construction of site haul road at Portion 4

(f)            Waterworks at Portion 1, 2 and 4

(g)           Construction of noise barrier at Portion 4