Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract No. |
Site Activities (February
2025) |
ND/2019/01 |
(a)
Drainage
works, watermain works,
sheet piling and slope works
in Portion 1a (b)
Site
formation, watermain works, ELS construction, sewage
works, backfill and road works in
Portion 1c (c)
Site
formation, construction of subway, drainage
works, road
works, slope works and soil nail in
Portion 2 (d)
HAC soil treatment, watermain works,
drainage works and
sheet piles in Portion 3 (e)
Site
formation, watermain works, drainage works and DCS pipe
work in Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road works
and district cooling system in Portion 6a (g)
Operation
of HAC soil
treatment facility in Portion 6b (h)
Excavation, watermain works, sewage works, road works and
drainage works
in Portion 7 (i)
Road pavement
construction, RC construction of fresh
water service reservoir,
drainage works, watermain works, backfilling,
planting and metal works in
Portion 8a (j)
Trenchless
work, watermain
construction and ELS construction in
Portion 8b (k)
Sheet
piling, excavation, drainage works, watermain works and district cooling system in
Portion 9b (l)
No activity in Portion 11b
this month (m)
Stockpile of soil
in Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
(a)
Portion 2
to Portion 20C - Defect Rectification of Lodging Facility |
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding Erection (f)
Rebar Fixing (g)
ELS (h)
Backfilling |
ND/2019/05 |
(a)
South
Team -
BBI
Toilet ¡V Roof parapet wall was casted on 24 Jan 2025. -
Lift LT01
¡V Installation of E&M items was completed on 10
Feb 2025. Lift installation will commence on 13 Feb 2025. -
Lift LT02
¡V Concreting works completed on 08 Jan 2025 -
FW54 ¡V
Footing from CH0 to CH10 was casted on 06 Feb 2025. -
Sign
Gantry FT1 ¡V Footing on casted 18 Jan 2025. Backfilling work was also
completed. -
E4
Retaining Wall ¡V Construction of wall in progress. -
E4 Ramp Utrough ¡V Bay 17 and Bay 18 footing were casted on 17 Jan
2025 and 23 Jan 2025 respectively. -
D2-03
Drainage Reinstatement ¡V Manholes and drain pipes laying were completed. -
Noise
barrier NB109 A.
Bay 19
Footing was casted on 13 Jan 2025. B.
Bay 15,
16 ¡V Footings were casted on 18 Jan 2025 and 24 Jan 2025. -
Noise
barrier NB70 A.
Bay 1 ¡V
Stem wall was casted on 16 Jan 2025. B.
Bay 1 to
6 ¡V Backfilling in progress. -
Noise
barrier NB69 A.
Bay 2b ¡V
Stem wall was casted on 08 Feb 2025. B.
Bay 1, 2a
¡V Removal of temporary blinding and existing pavement in progress. -
Noise
barrier NB110 A.
Bay 10 ¡V
PC1 and PC2 stem wall completed and backfilling in progress. PC3 pile cap
excavation completed and construction in progress. -
Noise
barrier NB 29 Through Bay 6-15 A.
Footing
is 56% completed B.
Wall
(exclude parapet) is 45% completed. Parapet section will cast after
backfilling to formation. -
Noise barrier NB 30 A.
Pre-bored
Socket H pile construction (94/211 nos) completed. -
Noise barrier NB 77 A.
ELS works
for NB77 footing in progress. -
Fabrication
of Sign Gantry ¡V DS19 fabrication completed and delivered to site. DS20 fabrication
is 50% completed. -
Fabrication
of Noise Barrier ¡V NB32 and NB109 under fabrication. (b)
North
Team -
Reinstatement
works & footpath in progress in C4-02 (HD) -
C4-01B
for viaduct drainage & water works completed. -
Backfilling
of C2-01, C1-02a, C1-01b, D2-01 & E2-01 in progress. C3-04A & C1-02b
completed. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 90%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 90 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting
works for traffic signal & road light was in progress ( 95 % completed). -
JCR near
F63 ¡Vslope feature construction works in progress. (c)
Bridges
and Structures -
All of 116 type C segments
were casted in DongGuan casting yard and delivered
to site. Total 75 segment were erected. -
All of 791 type A segments
were casted in HuiZhou casting yard and delivered
to site. Total 781 segment were erected. -
LG launching to B1-02
completed, and the segment erection at pier B1-02 in progress. -
Total 1421 pcs of
parapet-skin fabricated; 1029 pcs of parapet skin erected. -
Installation of deck void
drainage at Bridge C1,C2 in progress. -
Reinstate of lifting tower
NF83A in progress. -
D2-04 end span segment
erection completed. -
Movement joint
installation for Bridge C4 in progress. -
Water proofing for Bridge
E1 in progress. -
Erection of sign gantry
ADS19 completed. -
Installation of railing in
progress. (d)
Form Traveler -
Mid
stitching between E3-04 & E3-03 completed. -
Mid
stitching between D2-01 & D2-02 in progress. -
Mid
stitching between E3-04 & E3-05 in progress. -
Dismantling
of form traveller at E3-04 D2-01 & E2-02 in
progress. -
Completed
concreting E3-E3-04-E3-03-S09 & E3-E3-04-E3-05-S09. D2-D2-01-D2-02-S11
& D2-D2-01-D1-04-S11. D2-D2-01-D1-04-S12. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2 and 4 (c)
Drainage works, Sewerage works at Portion 1, 2, 3 and 4 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at Portion 4 (f)
Waterworks at Portion 1, 2 and 4 (g)
Construction
of noise barrier at Portion 4 |