2.1
The
Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs) are one of the important sources of
land and housing supply in the medium and long term. The development of the KTN
and FLN NDAs will be implemented in phase for full completion by 2031. The
Phase 1 of the NDAs development, comprising the Advance Works and First Stage
Works, is targeted to be implemented from the second half of 2019
progressively. The Advance and First Stage Works would include site formation,
engineering infrastructure works (including roads, drainage, sewerage,
waterworks, landscaping works, pumping stations, and fresh water and flushing
water service reservoirs), soil remediation, reprovisioning of North District
Temporary Wholesale Market, development of a nature park at Long Valley and
implementation of environmental mitigation measures.
2.2
The
scope of works under the Advance and First Stage Works comprises the following:
a)
The
Advance Works (PWP item No. 7747CL-2) consist of:
i)
site
formation of land (including soil remediation) in KTN and FLN NDAs for housing,
community facilities and engineering infrastructure;
ii)
construction
of roads including the eastern section of Fanling
Bypass (FLBP(E)) connecting the FLN NDA to Fanling
Highway and other roads with footpaths and cycle tracks, and associated
junction/ road improvements;
iii)
engineering
infrastructure works including drainage. Sewerage (including two sewage pumping stations), waterworks (including a fresh
water service reservoir and a flushing water service reservoir in the KTN NDA),
landscape works and slopeworks;
iv)
part
expansion and upgrading of Shek Wu Hui Sewage Treatment Works (SWHSTW);
v)
reprovisioning
works; and
vi)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (v) above.
b)
The
First Stage Works (PWP item No. 7759CL) consist of:
i)
development
of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung Yue River
for connection between these two facilities;
ii)
reprovisioning
of two egretry sites in the FLN NDA and enhancement
works to an existing egretry site in the KTN NDA;
iii)
site
formation of land for a village resite
area and a district police station in the KTN NDA;
iv)
engineering
infrastructure works including roads, drainage, sewerage, waterbirds, and
landscape works; and
v)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (iv) above.
2.3
The
Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule
3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October
2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director
of Environmental Protection pursuant to the EIA Ordinance. The relevant EPs
under the Project and the respective Work Contracts are summarised in Tables
2.1a and 2.1.b.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP No. |
Designated
Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
¡@ |
|||||||
Kwu Tung North New Development Area Road P1 and P2 and
Associated New Kwu Tung Interchange and Pak Shek Au
Interchange Improvement |
ü |
¡@ |
|||||||
Kwu Tung North New Development Area Road D1 to D5 |
ü |
ü |
¡@ |
||||||
Sewage Pumping Stations in Kwu Tung North New Development Area |
ü |
¡@ |
|||||||
Utilization of Treated Sewage
Effluent (TSE) from Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
|||||||
Fanling Bypass Eastern Section |
ü |
ü |
ü |
¡@ |
|||||
Reprovision of temporary Wholesale
Market in Fanling North New Development Area |
ü |
¡@ |
|||||||
EP-546/2017 |
Fanling North Temporary Sewage Pumping Station |
ü |
¡@ |
Notes:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope of Works under concerned EP
Environmental
Permit (EP) No. |
Work
Contract(s) |
Scope
of Works under concerned EP(s) |
Site
Layout Plan under concerned EP(s) |
EP-466/2013/A(Part) |
C1 |
Realign Castle Peak Road and join with the Pak
Shek Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction of new primary distributor road (P1)
within Kwu Tung North New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction of new primary distributor roads (D1,
D3, D4 and part of D5) within Kwu Tung North New
Development Area |
Figure 14 |
C3 |
Development of a nature park at Long Valley and
ecological mitigation and enhancement works for the nature park (Condition
2.9) |
Figure 15 |
|
EP-469/2013(Part) |
C2 |
Construction of one sewage pumping station in Kwu Tung North with installed capacity of more than 2,000
m3 per day |
Figure 16 |
EP-470/2013/A(Part) |
C1 |
Construction of service reservoir and watermain
for the reuse of treated sewage effluent for reuse in Kwu
Tung North Development Areas |
Figure 17 |
EP-473/2013/A(Part) |
C3 |
Establishment of
alternative egretry sites and enhance the existing egretry
site at Ho Sheung Heung and/or its vicinity (Condition 2.7) |
Figure 18 |
EP-473/2013/A(Part) |
C5A |
Construction of new district distributor inside
FLN NDA, which provides a linkage between the Man Kam To
Road and the proposed Fanling Bypass Eastern
Section |
Figure 19 |
EP-473/2013/A(Part) |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The re-provisioned wholesale market will have
approximately 1,000 market stalls within a site area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a temporary sewage pumping
station in Fanling North with installed capacity
(average dry weather flow) of about 3,600m3/day |
Figure 22 |
Remark:
The EP(s) not related to the Project of the First Phase of the Kwu Tung North (KTN) and Fanling
North (FLN) New Development Area (NDA) Development Areas are not included in
the Table.
2.4
The
site boundary of the Project and all Works Contracts are shown in Drawing No. 1.
2.5
The
required submissions and submission status under Environmental Permits are
shown in Appendix U.
2.6
The
site
layout
plans
under concerned Environmental Permits are shown in Figures
12 - 22.
2.7
Different
parties with different levels of involvement in the Project organisation include:
Project Proponent ¡V Civil
Engineering and Development Department (CEDD)
Supervisor
/ Supervisor's Representative ¡V AECOM Asia Co. Ltd.
Environmental Team (ET) ¡V Wellab Limited
Independent Environmental Checker
(IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The
names and contact numbers of key personnel are summarised in Table
2.2.
Table 2.2 Key Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax
No. |
Civil Engineering and
Development Department, HKSAR (CEDD) |
Project Proponent |
Mr. Ryan Chau |
3797 5387 |
3547
1658 |
Supervisor / Supervisor's Representative (AECOM Asia Co. Ltd.) |
Chief Resident Engineer |
Mr. Alan Lee |
6398
5982 |
2680
9515 |
Senior Resident
Engineer |
Mr. King-man
Chan |
9651
2635 |
2680
9515 |
|
Environmental Team (Wellab
Limited) |
Environmental Team Leader |
Dr. Priscilla Choy |
2898
7388 |
2898 7076 |
Independent
Environmental Checker (MottMac) |
Independent Environmental Checker |
Mr. Thomas Chan |
2828 5967 |
2827 1823 |
Contract No. ND/2019/01 Contractor
(Build King ¡V Richwell Engineering Joint Venture) |
Site Agent |
Mr. Ivan Leung |
9640 8340 |
-- |
Environmental Officer |
Mr. Edward Tam |
9287 8270 |
||
Contract No. ND/2019/02 Contractor
(Chun Wo ¡V Kwan Lee Joint Venture.) |
Site Agent |
Mr. Andy Chan |
3485 9780 |
-- |
Environmental Officer |
Mr.
Sofi So |
9637 1667 |
||
Contract No. ND/2019/03 Contractor
(Sang Hing Kuly Joint Venture) |
Site Agent |
Mr. Tang Wing Kai |
9300 7037 |
-- |
Environmental Officer |
Mr. Ken Cheung |
9803 5297 |
||
Contract No. ND/2019/04 Contractor
(Daewoo ¡V Chun Wo ¡V Kwan Lee Joint Venture) |
Site Agent |
Mr. Eric Wu |
9786 8630 |
-- |
Environmental Officer |
Mr. Sam Lam |
6178 3179 |
||
Contract No. ND/2019/05 Contractor
(CRCC ¡V Paul Y. Joint Venture) |
Site Agent |
Mr. Darvin Lo |
9467 5891 |
-- |
Environmental Manager |
Mr. Pan Fong |
9436 9435 |
||
Environmental Officer |
Mr. Kevin Cheung |
6117 1344 |
||
Contract No. ND/2019/06 Contractor
(New Concepts Engineering Development Ltd.) |
Project Manager |
Mr. Joe
Cheng |
9861 0060 |
-- |
Environmental Officer |
Mr. Alex Choy |
6360 3236 |
||
Contract No. ND/2019/07 Contractor
(China Road and Bridge Corporation) |
Site Agent |
Mr. Mac Chow |
9169 9567 |
-- |
Environmental Manager |
Mr. K. M. Lui |
5113 8223 |
||
Environmental Officer |
Ms. Sedo Sze |
5111 8018 |
2.9
The
major site activities undertaken in the reporting month are shown in Table 2.3.
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (September 2024) |
ND/2019/01 |
(a)
Drainage
works, watermain works, sheet piling and slope works in Portion
1a (b)
Site
formation, watermain and construction of noise barrier in
Portion 1c (c)
Site
formation, construction of subway, drainage works, road works,
slope work and soil nail in Portion
2 (d)
Watermain
works, drainage work and
sheet piles in Portion
3 (e)
Site
formation and pipe jacking in Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road work and district cooling system in
Portion 6a (g)
Operation
of HAC soil treatment facility in Portion 6b (h)
Excavation and watermain works in Portion
7 (i)
RC
construction of fresh water service reservoir, drainage works, watermain
works, backfilling
works and construction of receiving pit in Portion 8a (j)
Trenchless
work, watermain construction, excavation and ground treatment
works in Portion
8b (k)
Sheet
piling, excavation, drainage, watermain works and district cooling system in
Portion 9b (l)
Excavation and drainage works
in Portion 11b (m)
Stockpile of soil in Portion 13 |
ND/2019/02 |
(a) Pipe Jacking (b) Backfilling (c) Concreting (d) Bedding and pipe laying (e) ELS (f)
Sheet Pile Installation (g) Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry agricultural land creation -
Construction of Water Treatment Wetland |
ND/2019/04 |
(a)
Pile Cap (b)
Back Filling (c)
Excavation (d)
Grouting (e)
Road works (f)
Formwork and Scaffolding Erection (g)
Rebar Fixing (h)
ELS |
ND/2019/05 |
(a)
South Team -
E3-04 ¡V Dismantling works for portal beam completed. -
E4-02 ¡V Reinstatement of DN900 stormwater manhole and backfilling are
completed. -
E4-03M ¡V Backfilling is completed. -
D2-04M ¡V Abutment construction in progress. -
Works in TWSRE A. Extension
to HKY Footbridge ¡V Installation of railing, floor tiles, and fall arrest system
is completed. B. BBI
Toilet ¡V Structure wall and roof construction are in progress. C. TTA-421
¡V TTA for E4 segment erection implemented on 20 August 2024. D. Sign
Gantry DS11 steel frame was removed on 11 July 2024 and its footing
obstructed NB110 was also removed on 31 July 2024. E. E4
Retaining Wall ¡V Setting up plate load test. Site clearance in progress. -
Works in TWSRW A. FS04 ¡V
Construction of footpath in progress B. Demolition
of HKY Ramp ¡V Existing ramp demolition is in progress. C. HKY
Access Road ¡V Road and Drain in progress for footpath diversion. D. Sewerage
work ¡V Laying 600Dia pipes to Manhole TW3.01 is completed. Waiting to final
connection to existing sewerage manhole. -
Noise barrier NB109 A. Bay 14,
15, 16 ¡V ELS is in progress B. Bay 17,
18 ¡V Footings are completed. Wall construction in progress C. Bay 1 to
4 ¡V Bay 3-4 Excavation completed. Footing construction in progress. Bay 1-2
ELS in progress. -
Noise barrier NB70 A. Bay 1-6
¡V Bay 5 excavation completed. Footing construction in progress. -
Noise barrier NB69 A.
Bay 3-10 ¡V Footings and walls are completed. Backfilling in progress. -
Noise barrier NB110 A.
Bay 10 ¡V 24 out of 31 piles completed. -
Noise barrier NB 29 A.
Footing is 60% completed B.
Wall (exclude parapet) is 55% completed.
Parapet section will cast after backfilling to formation. (b)
North Team -
Dismantling
of falsework at B2-03 cross head completed. -
Side
formwork erection for B2-01 cross head construction in progress. -
Reinstatement
works was in progress in C4-01b. -
Breaking of
temporary concrete pavement in C3-03b & C3-04b for viaduct drainage &
water works. -
On Kui
Street (near newly constructed DN 900 manhole) ¡V reinstatement was in
progress. -
On Kui
Street ¡V Construction of FW 53 was in progress (60 % completed) -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 80%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 80 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting
works for traffic signal & road light was in progress ( 50 % completed). -
JCR near
Wong Kong Shan Village¡V Trial pits to verify of proposed alignment of
watermain diversion was completed. -
JCR near
F63 ¡V Breaking of temporary pavement was in progress. Laying of DN 150 FWM
was completed. -
Trial pit
in Tong Hang Village for Pai Lau completed. (c)
Bridges and Structures -
Total 86 Type C segments casted in DongGuan Casting yard. -
All Type A segment fabrication completed. Total
725 segments were delivered to site, and total 701 segments erected. -
Segment erection at C1-01~ C1-02 end span
completed. -
Total 909 pcs of parapet-skin fabricated; 769
pcs of parapet skin arrived to site; 624 pcs of parapet skin erected. -
Installation of deck void drainage at Bridge
C3&C2 in progress. -
Erection of precast cell at pier E4-01
completed. -
Site formation for bridge E4 segment erection
in progress. -
Erection of end span segment
E2-E1-04M-E2-01-S01, E2-E1-04M-E2-01-S02, E2-E1-04M-E2-01-S03 completed. -
Preparation of bridge rotation at E2-01 in
progress. (d)
Form Traveler -
Dismantling of form traveler at E2-01 completed. -
Assembly of form traveler at E3-04 in progress. -
Form traveler at 8th pair segment at E3-02 in progress. -
Form traveler at 7th pair segment at D2-01 completed. -
Mid stitching between E2-03 & E3-01 completed. -
Dismantling of form traveler at E2-03 in progress. -
Grouting works for tendon duct at D2-02, D2-03 & D2-01 in
progress. -
Completed concreting E3-E3-02-E3-03-S06 & E3-E3-02-E3-01-S06,
E3-E3-02-E3-03-S07 & E3-E3-02-E3-01-S07. -
Completed concreting D2-D2-01-D2-02-S06 & D2-D2-01-D1-04-S06,
D2-D2-01-D2-02-S07 & D2-D2-01-D1-04-S07. |
ND/2019/06 |
The construction
phase was completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road
works at Portion 1, 4 and 5 (b)
C&D
waste disposal at Portion 1, 2 and 4 (c)
Drainage works, Sewerage works at Portion 1, 2, 3 and 4 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at Portion 4 (f)
Waterworks at Portion 1, 2 and 4 (g)
Construction of noise barrier at
Portion 4 and 5 |
2.10
Copies of Contractors¡¦ construction programmes are
provided in Appendix A.
2.11
A
summary of the relevant permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.4.
Table 2.4 Status
of Environmental Licences, Notifications and Permits