1.1
Wellab Limited
was commissioned by Civil Engineering and Development Department (CEDD) as the
Environmental Team to undertake the Environmental Monitoring and Audit
(EM&A) services for the Works Contracts involved in the implementation of the First Phase Development of Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs) Project to ensure that the
environmental performance of the Works Contracts complies with the requirements specified in the Environmental Permits (EPs),
Updated EM&A Manual, Environmental Impact Assessment (EIA) Report of the
KTN FLN NDAs project and other relevant statutory requirements.
1.2
This is
the 59th EM&A
Report which summarises the key findings of the
EM&A programme in September 2024.
1.3
The structure
of the report is as follows:
Section 1: |
Introduction
- purpose and structure of the
report. |
Section 2: |
Project
Information - summarises background and scope of
the Project, site description, project organisation
and contact details, construction programme, the
construction works undertaken and the status of Environmental Permits/Licences during the reporting month. |
Section 3: |
Air Quality Monitoring - summarises the monitoring parameters,
monitoring programmes, monitoring methodologies,
monitoring frequencies, monitoring locations, Action and Limit Levels,
monitoring results and Event / Action Plans. |
Section 4: |
Noise
Monitoring - summarises the monitoring parameters,
monitoring programmes, monitoring methodologies,
monitoring frequencies, monitoring locations, Action and Limit Levels,
monitoring results and Event / Action Plans. |
Section 5: |
Water Quality Monitoring - summarises the monitoring parameters,
monitoring programmes, monitoring methodologies,
monitoring frequencies, monitoring locations, Action and Limit Levels and
Event / Action Plans. |
Section 6: |
Land Contamination (Ambient Arsenic Monitoring) - summarises the monitoring parameters,
monitoring programmes, monitoring methodologies,
monitoring frequencies, monitoring locations, Action and Limit Levels,
monitoring results and Event / Action Plans. |
Section 7: |
Landfill
Gas Monitoring - summarises the monitoring
requirement, monitoring parameters and frequency, monitoring locations,
Action and Limit Levels, monitoring results and observation, and Event /
Action Plans. |
Section 8: |
Built
Heritage Monitoring ¡V summarises the monitoring requirement,
monitoring parameters and frequency, monitoring locations, Action and Limit
Levels, monitoring results and observation. |
Section 9: |
Ecological Monitoring ¡V summarises the details
of monitoring of measures to minimise disturbance
to waterbirds in Ng Tung River, Sheung Yue River, Shek Sheung River and Long
Valley, monitoring of measures to minimise impacts
on ecological sensitive habitats from disturbance and pollution during the reporting
month. |
Section 10: |
Environmental
Site Inspection - summarises the audit findings of the
weekly site inspections undertaken within the reporting month. |
Section 11: |
Environmental
Non-conformance - summarises any monitoring exceedance,
environmental complaints, environmental summons and successful prosecutions
within the reporting month. |
Section 12: |
Future Key
Issues - summarises the impact forecast,
proposed mitigation measures and monitoring schedule for the upcoming months. |
Section 13: |
Conclusions
and Recommendations |