Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract
No. |
Site
Activities (October 2024) |
ND/2019/01 |
(a)
Drainage
works, watermain works, sheet piling and slope works in Portion
1a (b)
Site
formation, watermain and construction of noise barrier in
Portion 1c (c)
Site
formation, construction of subway, drainage works, road works,
slope work and soil nail in Portion
2 (d)
Road works, watermain works,
drainage work and sheet piles in Portion
3 (e)
Site
formation, watermain works, drainage works and road works in Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road work and district cooling system in
Portion 6a (g)
Operation
of HAC soil treatment facility in Portion 6b (h)
Excavation and watermain works in Portion
7 (i)
Road pavement construction, RC construction of fresh water service reservoir,
drainage works, watermain works, backfilling works and construction of
receiving pit in Portion 8a (j)
Trenchless
work, watermain construction, excavation and ground treatment
works in Portion
8b (k)
Sheet
piling, excavation, drainage, watermain works and district cooling system in
Portion 9b (l)
Excavation and drainage works
in Portion 11b (m)
Stockpile of soil in Portion 13 |
ND/2019/02 |
(a) Pipe Jacking (b) Backfilling (c) Concreting (d) Bedding and pipe laying (e) ELS (f)
Sheet Pile Installation (g) Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry agricultural land creation -
Construction of Water Treatment Wetland |
ND/2019/04 |
(a)
Pile Cap (b)
Back Filling (c)
Excavation (d)
Grouting (e)
Road works (f)
Formwork and Scaffolding Erection (g)
Rebar Fixing (h)
ELS |
ND/2019/05 |
(a)
South Team -
E4-02 ¡V Reinstatement of DN900 stormwater manhole and backfilling are
completed. -
E4-03M ¡V Backfilling is completed. -
D2-04M ¡V Abutment construction in progress. -
Works in TWSRE A. BBI
Toilet ¡V Structure wall and roof construction are in progress. B. Lift
LT01 ¡V Installation of louvre and glasses in progress. C. Sign
Gantry DS20 ¡V Pile cap construction in progress. D. E4
Retaining Wall ¡V Excavation in progress. -
Works in TWSRW A. FS04 ¡V
Construction of footpath & temporary carriageway in progress. B. Demolition
of HKY Ramp ¡V Existing ramp demolition completed. C. HKY
Access Road ¡V Road and Drain in progress for footpath diversion completed. D. Sewerage
work ¡V Laying 600Dia pipes to Manhole TW3.01 is completed. final connection
to existing sewerage manhole completed. E. LT2 lift
shaft in progress. -
Noise barrier NB109 A. Bay 14 ¡V
Footing construction in progress B. Bay 17,
18 ¡V Wall construction in progress C. Bay 1 to
4 ¡V ELS completed. Bay 1-2 footing construction in progress. -
Noise barrier NB70 A. Bay 1-6
¡V Bay 5 wall construction in progress. Bay 4 excavation in progress. -
Noise barrier NB69 A.
Bay 3-10 ¡V Bay 8a backfilling in progress. Bay 2b wall construction
resumed after E304 form traveller erected. -
Noise barrier NB110 A.
Bay 10 ¡V 31 piles including 2 nos. of proof drilling are completed.
Pile loading tests will take place on 17 October 2024. Excavation for pile
caps construction is in progress. -
Noise barrier NB 29 Through Bay 6-15 A.
Footing is 70% completed B.
Wall (exclude parapet) is 60% completed. Parapet section will cast
after backfilling to formation. -
Noise barrier NB 29 A.
NB30 Predrilling works (13/28 nos)
completed. (b)
North Team -
Rebar
fixing for B2-01 cross head construction in progress. -
Formwork
erection for B1abutment wall in progress. -
Reinstatement
works & footpath in progress in C4-02 (HD) -
C3-03b
& C3-04b for viaduct drainage & water works in progress -
Backfilling
of C1-02b in progress. -
On Kui
Street (near newly constructed DN 900 manhole) ¡V reinstatement completed. -
On Kui
Street ¡V Construction of FW 53 completed. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 85%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 90 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting
works for traffic signal & road light was in progress ( 75 % completed). -
JCR near
Wong Kong Shan Village¡V Trial pits to verify of proposed alignment of
watermain diversion was completed. -
JCR near
F63 ¡V Breaking of temporary pavement was in progress. Laying of DN 150 FWM
was completed. -
Predrilling
works in Tong Hang Village for Pai Lau completed (c)
Bridges and Structures -
Total 104 Type C segments casted in DongGuan Casting yard. -
All Type A segment fabrication completed. Total
725 segments were delivered to site, and total 723 segments erected. -
B2-02 & B2-03 T-span segment erection in
progress. -
Total 990 pcs of parapet-skin fabricated; 793
pcs of parapet skin arrived to site; 718 pcs of parapet skin erected. -
Installation of deck void drainage at Bridge C2
in progress. -
Erection of precast cell at pier E4-02
completed. -
Site formation for bridge E4 segment erection
in progress. -
E2-01 bridge rotation completed. -
Preparation of bridge rotation at D2-01 in
progress. (d)
Form Traveler -
Assembly of form traveler at E3-04 completed. -
Form traveler at 10th pair segment at E3-02 in progress. -
Form traveler at 7th pair segment at D2-01 completed. -
Mid stitching between E2-01 & E2-02 in progress. -
Dismantling of temporary platform & Parapet construction at D2-01
completed. -
Dismantling of form traveler at E2-03 completed. -
Grouting works for tendon duct at D2-02, D2-03 & D2-01 completed
& at E2-03 in progress. -
Completed concreting E3-E3-02-E3-03-S08 & E3-E3-02-E3-01-S08,
E3-E3-02-E3-03-S09 & E3-E3-02-E3-01-S09. -
Completed concreting E3-E3-04-E3-03-S01 & E3-E3-04-E3-05-S01. |
ND/2019/06 |
The
construction phase was completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road
works at Portion 1, 4 and 5 (b)
C&D
waste disposal at Portion 1, 2 and 4 (c)
Drainage works, Sewerage works at Portion 1, 2, 3 and 4 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at Portion 4 (f)
Waterworks at Portion 1, 2 and 4 (g)
Construction of noise barrier at
Portion 4 |