Table 2.3     Summary Table for Major Site Activities in the Reporting Month

Contract No.

Site Activities (October 2024)

ND/2019/01

(a)          Drainage works, watermain works, sheet piling and slope works in Portion 1a

(b)         Site formation, watermain and construction of noise barrier in Portion 1c

(c)          Site formation, construction of subway, drainage works, road works, slope work and soil nail in Portion 2

(d)         Road works, watermain works, drainage work and sheet piles in Portion 3

(e)          Site formation, watermain works, drainage works and road works in Portion 5

(f)          Backfilling, drainage works, watermain works, slope works, road work and district cooling system in Portion 6a

(g)         Operation of HAC soil treatment facility in Portion 6b

(h)         Excavation and watermain works in Portion 7

(i)           Road pavement construction, RC construction of fresh water service reservoir, drainage works, watermain works, backfilling works and construction of receiving pit in Portion 8a

(j)           Trenchless work, watermain construction, excavation and ground treatment works in Portion 8b

(k)         Sheet piling, excavation, drainage, watermain works and district cooling system in Portion 9b

(l)           Excavation and drainage works in Portion 11b

(m)       Stockpile of soil in Portion 13

ND/2019/02

(a)       Pipe Jacking

(b)       Backfilling

(c)       Concreting

(d)       Bedding and pipe laying

(e)       ELS

(f)        Sheet Pile Installation

(g)       Cut and Fill of Slope

ND/2019/03

(a)          Portion 2 to Portion 20C

-      Wetland creation & restoration, Dry agricultural land creation

-      Construction of Water Treatment Wetland

ND/2019/04

(a)           Pile Cap

(b)           Back Filling

(c)           Excavation

(d)           Grouting

(e)           Road works

(f)            Formwork and Scaffolding Erection

(g)           Rebar Fixing

(h)           ELS

ND/2019/05

(a)          South Team

-          E4-02 ¡V Reinstatement of DN900 stormwater manhole and backfilling are completed.

-          E4-03M ¡V Backfilling is completed.

-          D2-04M ¡V Abutment construction in progress.

-          Works in TWSRE

A.     BBI Toilet ¡V Structure wall and roof construction are in progress.

B.      Lift LT01 ¡V Installation of louvre and glasses in progress.

C.      Sign Gantry DS20 ¡V Pile cap construction in progress.

D.     E4 Retaining Wall ¡V Excavation in progress.

-          Works in TWSRW

A.     FS04 ¡V Construction of footpath & temporary carriageway in progress.

B.      Demolition of HKY Ramp ¡V Existing ramp demolition completed.

C.      HKY Access Road ¡V Road and Drain in progress for footpath diversion completed.

D.     Sewerage work ¡V Laying 600Dia pipes to Manhole TW3.01 is completed. final connection to existing sewerage manhole completed.

E.      LT2 lift shaft in progress.

-          Noise barrier NB109

A.     Bay 14 ¡V Footing construction in progress

B.      Bay 17, 18 ¡V Wall construction in progress

C.      Bay 1 to 4 ¡V ELS completed. Bay 1-2 footing construction in progress.

-          Noise barrier NB70

A.       Bay 1-6 ¡V Bay 5 wall construction in progress. Bay 4 excavation in progress.

-          Noise barrier NB69

A.         Bay 3-10 ¡V Bay 8a backfilling in progress. Bay 2b wall construction resumed after E304 form traveller erected.

-          Noise barrier NB110

A.         Bay 10 ¡V 31 piles including 2 nos. of proof drilling are completed. Pile loading tests will take place on 17 October 2024. Excavation for pile caps construction is in progress.  

-          Noise barrier NB 29 Through Bay 6-15

A.         Footing is 70% completed

B.          Wall (exclude parapet) is 60% completed. Parapet section will cast after backfilling to formation.

-          Noise barrier NB 29

A.         NB30 Predrilling works (13/28 nos) completed.

(b)         North Team

-          Rebar fixing for B2-01 cross head construction in progress.

-          Formwork erection for B1abutment wall in progress.

-          Reinstatement works & footpath in progress in C4-02 (HD)

-          C3-03b & C3-04b for viaduct drainage & water works in progress

-          Backfilling of C1-02b in progress.

-          On Kui Street (near newly constructed DN 900 manhole) ¡V reinstatement completed.

-          On Kui Street ¡V Construction of FW 53 completed.

-          JCR: Construction of new central median & ducting works for traffic signal & road light were completed of 85%.

-          JCR & Tong Hang Village J/O improvement works (FS 25): slope works 90 % completed.

-          JCR & Tong Hang Village J/O (near bus-stop) : Ducting works for traffic signal & road light was in progress ( 75 % completed).

-          JCR near Wong Kong Shan Village¡V Trial pits to verify of proposed alignment of watermain diversion was completed.

-          JCR near F63 ¡V Breaking of temporary pavement was in progress. Laying of DN 150 FWM was completed.

-          Predrilling works in Tong Hang Village for Pai Lau completed

(c)          Bridges and Structures

-          Total 104 Type C segments casted in DongGuan Casting yard.

-          All Type A segment fabrication completed. Total 725 segments were delivered to site, and total 723 segments erected.

-          B2-02 & B2-03 T-span segment erection in progress.

-          Total 990 pcs of parapet-skin fabricated; 793 pcs of parapet skin arrived to site; 718 pcs of parapet skin erected.

-          Installation of deck void drainage at Bridge C2 in progress.

-          Erection of precast cell at pier E4-02 completed.

-          Site formation for bridge E4 segment erection in progress.

-          E2-01 bridge rotation completed.

-          Preparation of bridge rotation at D2-01 in progress.  

(d)         Form Traveler

-              Assembly of form traveler at E3-04 completed.

-              Form traveler at 10th pair segment at E3-02 in progress.

-              Form traveler at 7th pair segment at D2-01 completed.

-              Mid stitching between E2-01 & E2-02 in progress.

-              Dismantling of temporary platform & Parapet construction at D2-01 completed.

-              Dismantling of form traveler at E2-03 completed.

-              Grouting works for tendon duct at D2-02, D2-03 & D2-01 completed & at E2-03 in progress.

-              Completed concreting E3-E3-02-E3-03-S08 & E3-E3-02-E3-01-S08, E3-E3-02-E3-03-S09 & E3-E3-02-E3-01-S09.

-              Completed concreting E3-E3-04-E3-03-S01 & E3-E3-04-E3-05-S01.  

ND/2019/06

The construction phase was completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)            Road works at Portion 1, 4 and 5

(b)           C&D waste disposal at Portion 1, 2 and 4

(c)            Drainage works, Sewerage works at Portion 1, 2, 3 and 4

(d)           Filling works at Portion 2 and 4

(e)            Construction of site haul road at Portion 4

(f)            Waterworks at Portion 1, 2 and 4

(g)           Construction of noise barrier at Portion 4