Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract
No. |
Site
Activities (November 2024) |
ND/2019/01 |
(a)
Drainage
works, watermain works, sheet piling and slope works in Portion
1a (b)
Site
formation, watermain and construction of noise barrier in
Portion 1c (c)
Site
formation, construction of subway, drainage works, road works,
slope work and soil nail in Portion
2 (d)
Watermain
works, drainage work and
sheet piles in Portion
3 (e)
Site
formation, watermain works and drainage works in Portion 5 (f)
Backfilling,
drainage works, watermain works, slope works, road work and district cooling system in
Portion 6a (g)
Operation
of HAC soil treatment facility in Portion 6b (h)
Excavation, watermain works, sewage works, road works and drainage works in Portion
7 (i)
Road pavement construction, RC construction of fresh water service reservoir,
drainage works, watermain works and backfilling works in Portion 8a (j)
Trenchless
work, watermain construction, ELS construction and
ground treatment works in Portion
8b (k)
Sheet
piling, excavation, drainage, watermain works and district cooling system in
Portion 9b (l)
No activity in Portion 11b this month (m)
Stockpile of soil in Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Excavation (d)
Concreting (e)
Bedding and pipe laying (f)
Sheet Piling (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry agricultural land creation -
Construction of Water Treatment Wetland |
ND/2019/04 |
(a)
Pile Cap (b)
Back Filling (c)
Excavation (d)
Grouting (e)
Road works (f)
Formwork and Scaffolding Erection (g)
Rebar Fixing (h)
ELS |
ND/2019/05 |
(a)
South Team -
BBI Toilet ¡V Wall construction completed. Roof construction is in
progress. -
Lift LT01 ¡V Installation of louvre and glasses in progress. -
Lift LT02 ¡V Lift shaft in progress. -
Sign Gantry DS20 ¡V Pile cap construction in progress. -
E4 Retaining Wall ¡V Base slab construction in progress. -
Noise barrier NB109 A. Bay 14 ¡V
Footing completed. Wall construction in progress. B. Bay 17,
18 ¡V Walls are completed. Backfilling to formation level in progress. C. Bay 1 to
4 ¡V Partially completed up to 1m below road level. Backfilling to suit
TTA-423 in progress. -
Noise barrier NB70 A. Bay 5, 6
¡V Footing and wall construction completed. B.
Bay 2, 3, 4 - Excavation completed. Footing construction in progress. -
Noise barrier NB69 A.
Bay 1, 2 ¡V Bay 2b wall construction to be resumed after Bridge E4
segment erection. -
Noise barrier NB110 A.
Bay 10 ¡V Pile loading tests completed on 26 October 2024. Excavation
for pile caps PC1 and PC2 is completed. Pile cap construction is in progress -
Noise barrier NB 29 Through Bay 6-15 A.
Footing is 90% completed B.
Wall (exclude parapet) is 75% completed. Parapet section will cast
after backfilling to formation. -
Noise barrier NB 30 A.
NB30 Predrilling works (13/28 nos)
completed. B.
Pre-bored Socket H pile construction (7/220 nos)
completed. -
Noise barrier NB 77 A.
Pre-bored Socket H pile construction (1/16 nos)
completed. (b)
North Team -
B2-01 cross
head construction concreting completed. -
Rebar
fixing for B1abutment wall in progress. -
Reinstatement
works & footpath in progress in C4-02 (HD) -
C3-03b
& C3-04b for viaduct drainage & water works in progress -
Backfilling
of C3-04a, C2-01, C1-02a & C1-02b in progress. -
On Kui
Street (near newly constructed DN 900 manhole) ¡V reinstatement completed. -
On Kui
Street ¡V Construction of FW 53 completed. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were completed of 85%. -
JCR &
Tong Hang Village J/O improvement works (FS 25): slope works 90 % completed. -
JCR &
Tong Hang Village J/O (near bus-stop) : Ducting
works for traffic signal & road light was in progress ( 75 % completed). -
JCR near
Wong Kong Shan Village¡V Trial pits to verify of proposed alignment of
watermain diversion was completed. -
JCR near
F63 ¡V Breaking of temporary pavement was in progress. Laying of DN 150 FWM
was completed. (c)
Bridges and Structures -
All 116 Type C segments casted in DongGuan Casting yard. -
All Type A segment fabrication completed. Total
758 segments were delivered to site, and total 734 segments erected. -
B2-02 T-span segment erection by LG completed,
B2-03 T-span segment erection in progress. -
Total 1106 pcs of parapet-skin fabricated; 920
pcs of parapet skin erected. -
Installation of deck void drainage at Bridge C2
in progress. -
Segment erection at E4-01 & E4-02 T-span in
progress. -
Bridge rotation at D2-01 in progress. -
Reinstate of lifting tower NF83A in progress. (d)
Form Traveler -
Form traveler at 04th pair segment at E3-04 in progress. -
Form traveler at 11th pair segment at E3-02 completed -
Form traveler at 7th pair segment at D2-01 completed. -
Mid stitching between E2-01 & E2-02 in progress. -
Mid stitching between E3-02 & E3-03 completed. -
Dismantling of form traveler at E3-02 in progress -
Completed concreting E3-E3-02-E3-03-S10 & E3-E3-02-E3-01-S10,
E3-E3-02-E3-01-S011. -
Completed concreting E3-E3-04-E3-03-S02 & E3-E3-04-E3-05-S02,
E3-E3-04-E3-03-S03 & E3-E3-04-E3-05-S03. |
ND/2019/06 |
The
construction phase was completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road
works at Portion 1, 4 and 5 (b)
C&D
waste disposal at Portion 1, 2 and 4 (c)
Drainage works, Sewerage works at Portion 1, 2, 3 and 4 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at Portion 4 (f)
Waterworks at Portion 1, 2 and 4 (g)
Construction of noise barrier at
Portion 4 |