Table 12.1 Summary Table for Site Activities, Potential
Environmental Impacts and Recommended Mitigation Measures in the Coming Months
Contract
No. |
Major Site Activities |
Location/ Working Period |
Potential Environmental Impact |
Recommended Mitigation Measures |
ND/2019/01 |
(a) Excavation / Backfilling |
Portion 6a, 7, 8a, 9b |
- Construction Dust impact - Noise Impact (Construction Phase) - Water Quality Impact (Construction
Phase) - Waste Management
(Construction Waste) |
Air -
Watering on
exposed earth and haul road. -
Cover the
stockpiles or dusty materials. -
Deploy water
bowsers to water the haul road. -
Deploy
mist-cannon on site -
Provide
shelter with top and 3-sides for cement production activities. -
Cover the
Arsenic-containing soil. -
Store the
bulk cement in enclosed silo tank for soil treatment. -
Close the mechanical
cover of the vehicles used for transporting dusty materials. -
Establish
vehicle wheel washing facilities at vehicle exit points. -
Speed
control of site vehicles. Noise -
Regular
inspect of construction plants in good condition. -
Provide
temporary noise screens if necessary. -
Use of
Quiet plants (QPME) and working methods if possible. -
Sequencing
operation of construction plants where practicable. -
Shut down
the machines and plant if not in use. -
Only
well-maintained plant to be operated on-site -
Mobile
plant to be sited as far away from NSRs as possible practicable. -
Conduct
noise monitoring regularly. -
Erect
silent-up noise barrier at portion 6b. Water -
Set up
wastewater treatment system (AquaSed) on site -
Erect soil
bund / temporary drain to divert /collect surface runoff. -
Maintain
the drainage and wastewater treatment facilities. Waste / Chemical Management -
Sort out
demolition debris and excavated materials from demolition works to recover
reusable / recyclable portions -
Provide
recycling bins on site,
encourage reuse and recycle as much as possible. -
Provide
drip trays for
chemical containers. -
Chemical spill kit available on site. -
Chemical waste cabinet available on site. -
Chemical wastes to be stored in appropriate containers and collected
by a licensed chemical waste collector. -
Delivery of yard waste to tree shredding facility for upcycling. |
(b) Site formation |
Portion 1c, 2, 5 |
|||
(c) Construction of noise barrier |
Portion 1c |
|||
(d) Construction
of subway |
Portion 2 |
|||
(e)
Sewage Works |
Portion 7 |
|||
(f) RC Construction of fresh water service reservoir |
Portion 8a |
|||
(g)
Construction of receiving pit |
NIL |
|||
(h) Operation of HAC treatment facility |
Portion 6b |
|||
(i)
Drainage
works / watermains works |
Portion 1a, 1c, 2, 3, 5, 6a, 7, 8a, 8b, 9b |
|||
(j)
Road works/ Road pavement construction |
Portion 2,
6a,7, 8a |
|||
(k)
Soil nail / Slope works |
Portion 1a, 2, 6a |
|||
(l)
Trenchless
works |
Portion 8b |
|||
(m)
Ground treatment |
Portion 8b |
|||
(n)
Sheet piling/ ELS & pipe pile |
Portion 1a, 3, 9b |
|||
(o)
Stockpile of soil |
Portion 13 |
|||
ND/2019/02 |
(a)
Pipe
Jacking |
Portions 2, 4 |
Air, Noise,
Waste |
-
Dusty works should be
spray water. Idle stockpile or slop should be covered by Tarpaulin sheet
properly. -
Wheel washing should
be carried out at every exit. -
Plants should be well
maintained to prevent dark smoke and oil leakage. Idle plant should be turned
off. -
Drip tray should be
provided for all chemical and stationary plants. -
No construction works
shall be carried out in restricted hours (7:00 pm to 7:00 am) unless CNP is
obtained. -
Erect noise screen
along site boundary. -
Waste should be
sorted and dispose according to the Waste Management Plan -
No direct discharge
of wastewater into storm drains is allowed. Wastewater must be de-silted
before discharged in accordance with the water discharge license. -
Dull green barrier and ecological measures should be implemented
according to the Ecological protection plan. |
(b)
Backfilling |
Portion 10, 4, 8 |
Air, Noise,
Waste |
||
(c)
Concreting |
Portions 4, 8, 10 |
Air, Noise,
Water, Waste, Ecology |
||
(d)
Bedding
& Pipe Laying |
Portion 5, 6 |
Air, Noise,
Water, Waste, Ecology |
||
(e)
ELS |
Portions 4, 10 |
Air, Noise,
Water, Waste, Ecology |
||
(f)
Sheet Pile
Removal |
NIL |
NIL |
||
(g)
Cut and
Fill of Slope |
Portion 4, 5 |
Air, Noise,
Water, Waste |
||
(h) Sheet pile installation |
Portion 4, 5 |
Air, Noise,
Water, Waste |
||
ND/2019/03 |
(a)
Excavation
& ELS |
Portion 1, 1A, 2, 3, 4, 4A, 4B, 5, 5A |
-
Waste -
Air
pollution -
Noise
pollution |
-
Dusty works should be sprayed with water or stockpile should be
covered by Tarpaulin properly. -
Plants should have maintenance to prevent dark smoke and oil leakage.
Idle plant should be turned off. -
Drip tray should be provided for all chemical and stationary plants. -
No construction works shall be carried out in restricted hours (7:00
pm to 7:00 am) unless CNP is granted. -
Waste should be sorted and disposed according to Waste Management
Plan. -
No direct discharge of wastewater into storm water drains is allowed. Wastewater
must be desilted before discharging according to water discharge license. |
(b) Site Clearance |
Sections 7, 8 and 9 |
-
Waste -
Air
pollution -
Noise
pollution |
||
(c)
Tree
Felling |
Sections 6, 7, 8 and 9 |
-
Waste -
Air
pollution -
Noise
pollution |
||
ND/2019/04 |
(a)
Rebar Fixing, formwork erection and scaffolding
erection |
Bridge
F, A1, A2, A3, Portion J, K, H |
-
Air, Noise, Waste |
-
Dusty works should be sprayed with water or stockpile should be
covered by tarpaulin properly. -
Plants should have maintenance to prevent dark smoke and oil leakage.
Idle plant should be turned off. -
Drip tray should be provided for all chemical and stationary plants. -
No construction works shall be carried out in restricted hours (7:00
pm to 7:00 am) unless CNP is granted. -
Waste should be sorted and disposed according to Waste Management
Plan. -
No direct discharge of wastewater into storm water drains is allowed.
Wastewater must be desilted before discharging according to water discharge
license. |
(b)
Pile cap |
Bridge G, Portion J and K |
-
Air, Noise,
Water, Waste |
||
(c)
Grouting |
Bridge F, A1, A2, A3 and Portion J, K, H |
-
Air, Noise,
Water, Waste |
||
(d)
Sheet piling removal |
NIL |
-
NIL |
||
(e)
Excavation
& ELS |
Portion J,
H, K |
-
Air, Noise,
Waste |
||
(f)
Road works |
Portion B, J, H |
-
Air, Noise,
Waste |
||
(g)
Pre-drilling |
NIL |
-
NIL |
||
(h)
Sheet piling |
Bridge
A1, A2 |
-
Air, Noise,
Waste |
||
(i)
UU diversion |
Portion J and
K |
-
Air, Noise,
Waste |
||
ND/2019/05 |
(a)
ELS & Pile Cap Construction |
NB69 Bay 2~8 NB110 Bay 6~7 |
-
Construction
Dust Impact -
Noise
Impact -
Water
Quality Impact (Construction Phase) -
Waste
Management (Construction Waste) -
Landscape
and Visual -
Cultural
Heritage |
Regular watering
on exposed worksites and haul road. -
Stockpiling area should be provided with covers and water spraying
system. -
Only well maintained plant to be operated on site. -
plant known to emit noise strongly in one direction, where possible,
be orientated so that the noise is directed away from nearby NSRs. -
mobile plant to be sited as far away from NSRs as possible
practicable. -
All open stockpiles of construction materials of more than 50m3 to be
cove red with tarpaulin. -
Manholes to be adequately covered and temporarily sealed so as to
prevent silt, construction materials or debris being washed into the drainage
system. -
All vehicles and plant to be cleaned before leaving a construction
site to ensure no earth, mud, debris and the like is deposited by them on
roads. -
Segregate and store different types of waste in different containers,
skip or stockpiles to enhance reuse or recycling of materials and their
proper disposal. -
Sort out demolition debris and ex cavated materials from demolition
works to recover reusable/recyclable portions. -
Provide training to workers on appropriate waste management
procedures, including waste reduction, reuse and recycling. -
To adopt other good site practice, such as arrangements for collection
and effective disposal to an appropriate facility, of all wastes generated at
the site and regular cleaning and maintenance programme for drainage. -
Chemical wastes to be stored in appropriate containers and collected
by a licensed chemical waste Contractor. Chemical wastes (e.g. spent
lubricant oil) should be recycled at an appropriate facility as far as
possible, while the chemical waste that ca nnot be recycled should be
disposed of at either the Chemical Waste Treatment Centre, or another
licensed facility, in accordance with the Waste Disposal (Chemical Waste)
(General) Regulation. -
Conducting Construction Vibration Monitoring -
Tree Protection & Preservation Exiting trees to be retained within
the Project Site should be carefully protected during construction. In
particular OVTs will be preserved according to ETWB Technical Circular
(Works) No. 29/2004. -
Tree Transplantation Trees unavoidably affected by the Project works
should be transplanted where practical. Trees should be transplanted straight
to their final receptor site and not held in a temporary nursery as far as
possible. -
Erect 2m high dull green site boundary fence. |
(b)
Cap Construction |
E3-04a,
E3-04b, E4-01 and E4-02 |
|||
(c)
Cross head
construction |
B2-01, B2-02 and B2-03 |
|||
(d) Pier / Pier head Construction |
D2-01 and E305M |
|||
(e)
Fabrication for segment |
C2, C1, D1, D2, E1, E4 |
|||
(f)
Form Traveler |
E3-01 construction 3rd to 6th
pair E2-02 construction 14th pair
& dismantling of FT1 D2-02 construction 6th to 8th
pair D2-03 construction 2nd pair to
4th pair E2-01 erection of 5th set of
form traveler. |
|||
(g)
Segment Erection by Launching Girder &
Crane |
Bridges
C3, C2 |
|||
(h) SOP construction
(precast & in-situ cast in type) |
D2-01 |
|||
(i)
Road construction |
TWSRW, TWSRE |
|||
(j)
Road works |
Jockey Club Rd, TWSRW |
|||
(k)
Base slab construction |
NB109 ¡V bay 11~12 |
|||
(l)
Tree Works |
All
works areas |
|||
(m)
Drainage works |
On Kui Street |
|||
ND/2019/06 |
N/A |
N/A |
N/A |
N/A |
ND/2019/07 |
(a)
Road works |
Portion 1, 4,
5 |
-
Construction
Dust Impact -
Noise
Impact -
Water
Quality Impact (Construction Phase) -
Waste
Management (Construction Waste) -
Landscape
and Visual |
-
Regular watering on exposed worksites and haul road. -
Stockpiling area should be provided with covers and water spraying
system. -
Only well-maintained plant to be operated on-site. -
plant known to emit noise strongly in one direction, where possible,
be orientated so that the noise is directed away from nearby NSRs. -
mobile plant to be sited as far away from NSRs as possible
practicable. -
All open stockpiles of construction materials of more than 50m3 to be
covered with tarpaulin. -
Manholes to be adequately covered and temporarily sealed so as to
prevent silt, construction materials or debris being washed into the drainage
system. -
All vehicles and plant to be cleaned before leaving a construction
site to ensure no earth, mud, debris and the like is deposited by them on
roads. -
Segregate and store different types of waste in different containers,
skip or stockpiles to enhance reuse or recycling of materials and their
proper disposal. -
Sort out demolition debris and excavated materials from demolition
works to recover reusable/recyclable portions. -
Provide training to workers on appropriate waste management
procedures, including waste reduction, reuse and recycling. -
To adopt other good site practice, such as arrangements for collection
and effective disposal to an appropriate facility, of all wastes generated at
the site and regular cleaning and maintenance programme for drainage. -
Chemical wastes to be stored in appropriate containers and collected
by a licensed chemical waste Contractor. Chemical wastes (e.g. spent
lubricant oil) should be recycled at an appropriate facility as far as
possible, while the chemical waste that cannot be recycled should be disposed
of at either the Chemical Waste Treatment Centre, or another licensed
facility, in accordance with the Waste Disposal (Chemical Waste) (General)
Regulation. -
Tree Protection & Preservation ¡V Exiting trees to be retained
within the Project Site should be carefully protected during construction. In
particular OVTs will be preserved according to ETWB Technical Circular
(Works) No. 29/2004. -
Tree Transplantation ¡V Trees unavoidably affected by the Project works
should be transplanted where practical. Trees should be transplanted straight
to their final receptor site and not held in a temporary nursery as far as
possible. -
Erect 2m high dull green site boundary fence. -
Light Control ¡V Construction day and night time lighting should be
controlled to minimize glare impact to adjacent VSRs during the Construction
phase. |
(b) C&D
waste disposal |
Portion 1, 2,
4 |
|||
(c)
Filling works |
Portions 2, 4 |
|||
(d) Construction
of site haul road |
Portions 4 |
|||
(e)
Drainage Works |
Portion 1, 2, 3, 4 |
|||
(f)
Sewerage works |
Portion 3, 4 |
|||
(g) Construction
of Noise Barrier |
Portion 4 |
|||
(h) Waterworks |
Portion 1, 2, 4 |
|||
|
|