Table 10.2       Observations and Recommendations during Site Audits

Parameters

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

 

Air Quality

29/10/2024

Mitigation measures i.e.  Water Tank Truck patrol should be enhanced at the exposed site

of Portion 8A.

Improvement/Rectification was observed during follow-up audit session on 5 November 2024.

19/11/2024

Haul road at Portion 6A should be kept clean.

Improvement/Rectification was observed during follow-up audit session on 26 November 2024.

Water Quality

26/11/2024

The construction materials at the drainage channel at Portion 7/13 should be cleared.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/02

Water Quality

30/10/2024

Contractors were reminded to immediately establish proper drainage system for pumped groundwater at Portion 7.

Item remarked as 241106-O01. Follow-up action is needed to be review.

06/11/2024

Item remarked as 241113-O01. Follow-up action is needed to be review.

13/11/2024

Item remarked as 241120-O01. Follow-up action is needed to be review.

20/11/2024

Item remarked as 241127-O01. Follow-up action is needed to be review.

27/11/2024

Follow-up action is needed to be reported in the following month.

30/10/2024

Provide complete drainage system to treat wastewater. (Shek Wu Hui Treatment Plant works area)

Item remarked as 241106-R02. Follow-up action is needed to be review.

06/11/2024

Item remarked as 241113-R02. Follow-up action is needed to be review.

13/11/2024

Item remarked as 241120-R02. Follow-up action is needed to be review.

20/11/2024

Item remarked as 241127-R02. Follow-up action is needed to be review.

27/11/2024

Follow-up action is needed to be reported in the following month.

30/10/2024

Enhance water mitigation measures to avoid surface runoff out of site boundary. (Portion 6)

Item remarked as 241106-R03. Follow-up action is needed to be review.

06/11/2024

Item remarked as 241113-R03. Follow-up action is needed to be review.

13/11/2024

Item remarked as 241120-R03. Follow-up action is needed to be review.

20/11/2024

Item remarked as 241127-R03. Follow-up action is needed to be review.

27/11/2024

Follow-up action is needed to be reported in the following month.

Air Quality

27/11/2024

Wheel washing facilities at Portion 11 near Ho Sheung Heung Pai Fung Road should be maintained properly to avoid dust and debris exceeds the site area.

Follow-up action is needed to be reported in the following month.

Ecology

30/10/2024

Dull green hoarding should be erected along the site boundary as according to the submitted location plan.

Item remarked as 241106-R01. Follow-up action is needed to be review.

06/11/2024

Item remarked as 241113-R01. Follow-up action is needed to be review.

13/11/2024

Item remarked as 241120-R01. Follow-up action is needed to be review.

20/11/2024

Item remarked as 241127-R01. Follow-up action is needed to be review.

27/11/2024

Follow-up action is needed to be reported in the following month.

Waste/Chemical Management

30/10/2024

Oil leakage was observed with no drip tray provided at Shek Wu Hui Treatment Plant works area. Potential risk of leakage exceeds site boundary. 

Item remarked as 241106-O02. Follow-up action is needed to be review.

06/11/2024

Item remarked as 241113-O02. Follow-up action is needed to be review.

13/11/2024

Item remarked as 241120-O02. Follow-up action is needed to be review.

20/11/2024

Improvement/Rectification was observed during follow-up audit session on 27 November 2024.

Contract No.: ND/2019/03

--

--

--

--

Contract No.: ND/2019/04

Air Quality

12/11/2024

Site exit at Sha Tau Kok Road should be kept clean and free from tyre marks etc.

Improvement/Rectification was observed during follow-up audit session on 21 November 2024.

Water Quality

12/11/2024

Old drainage hole leads to Ng Tung River should be sealed to prevent seepage.

Improvement/Rectification was observed during follow-up audit session on 21 November 2024.

Waste / Chemical Management

07/11/2024

Drip tray should be provided for Fuel/Chemical containers at A2.

Improvement/Rectification was observed during follow-up audit session on 12 November 2024.

Contract No.: ND/2019/05

Waste / Chemical Management

21/11/2024

Drip tray should be provided for fuel/chemical containers.

Improvement/Rectification was observed during follow-up audit session on 25 November 2024.

Air Quality

28/10/2024

Dusty stockpile near Bridge C1 should be covered by tarpaulin sheets entirely to prevent dust generation.

Improvement/Rectification was observed during follow-up audit session on 4 November 2024.

Contract No.: ND/2019/06

--

--

--

--

Contract No.: ND/2019/07

 

--

--

--

--