10           ENVIRONMENTAL SITE INSPECTION

Site Audits

10.1     Site audits were carried out by ET on a weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures on the Contract site.  Summary of the site audits are presented in Table 10.1 and Appendix P.

Table 10.1   Summary of Site Audits

Environmental Site Inspection

Works Contracts

ND/2019/01

ND/2019/02

ND/2019/03

ND/2019/04

ND/2019/05

ND/2019/06

ND/2019/07

Weekly site audit with representative of the Supervisor¡¦s Representative and the Contractor

10, 14, 21 and 28 May 24

2, 8, 14, 22 and 29 May 24

3, 10, 17, 24 and 31 May 24

2, 9, 13, 23 and 30 May 24

6, 16, 20 and 27 May 24

N/A

3, 10, 17, 24 and 31 May 24

Joint Site Audit with representative of the Supervisor¡¦s Representative, the Contractor and IEC

10 May 24

22 May 24

31 May 24

13 May 24

16 May 24

N/A

17 May 24

Remarks: The weekly site inspection for ND/2019/06 has been terminated starting from 19/10/2023 since the termination proposal was approved by EPD on the same day.

10.2     During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarised in Table 10.2. Any outstanding and recurrence deficiencies are presented in Table 10.3.

10.3     All construction activities with significant environmental impact undertaken by Contract No. ND/2019/06 was substantially completed in March 2022 and the majority of outstanding works were also completed in April 2022 with defect rectification works remained. The outstanding installation works were the short-duration works which would be completed within 2 months during the 1-year defect correction period, originally estimated.

10.4     Due to problems in material deliveries from Mainland China in 2022, the completion date of the outstanding works would be extended to June 2023 tentatively. However, in June 2023, more defects were found during the handover inspection so the rectification works were undertaken until July 2023 when all works were completed.

10.5     The weekly site inspection and EM&A Reporting for ND/2019/06 were maintained until the termination proposal for ND/2019/06 has been endorsed by the IEC (17 Aug 23), the Engineer (26 Aug 23) and the Project Proponent (19 Sep 23) followed by approval from EPD (19 Oct 23) in accordance. The procedure for termination proposal for ND/2019/06 is in accordance with section 15.4.2 of updated EM&A Manual.


 


Table 10.2       Observations and Recommendations during Site Audits

Parameters

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

 

Water Quality

21/05/2024

Muddy debris was observed at the haul road of Portion 6A. Contractor was reminded to clean the road and enhanced the wheel washing system.

Improvement/Rectification was observed during follow-up audit session on 28 May 2024.

Contract No.: ND/2019/02

Water Quality

24/04/2024

Water mitigation measures should be enhanced to avoid muddy runoff discharge into manholes. (Dill¡¦s Corner)

Improvement/Rectification was observed during follow-up audit session on 2 May 2024.

02/05/2024

Muddy water runoff was observed flowing into nearby outlet at Portion 11. Contractor was reminded to enhance water mitigation measures to prevent runoff entering water bodies, and redirect any groundwater pumped out to water treatment facilities.

Item remarked as 240508-O01. Follow-up action is needed to be review.

08/05/2024

Item remarked as 240514-O01. Follow-up action is needed to be review.

14/05/2024

Contractors were reminded to immediately establish proper drainage system for muddy runoff at Portion 11.

Item remarked as 240522-O01. Follow-up action is needed to be review.

22/05/2024

Item remarked as 240529-O01. Follow-up action is needed to be review.

29/05/2024

Follow-up action is needed to be reported in the following month.

02/05/2024

Wetsep at Portion 5 were observed not properly in function. Contractor was reminded to ensure its proper functioning in treatment of wastewater before discharge.

Item remarked as 240508-O02. Follow-up action is needed to be review.

08/05/2024

Item remarked as 240514-R02. Follow-up action is needed to be review.

14/05/2024

Maintenance should be provided to the Wetsep ay Portion 5.

Improvement/Rectification was observed during follow-up audit session on 22 May 2024.

24/04/2024

Review the drainage system to ensure the existing water pipe was connected to wetsep and

discharged into a valid location.

Item remarked as 240502-R02. Follow-up action is needed to be review.

02/05/2024

Item remarked as 240508-R02. Follow-up action is needed to be review.

08/05/2024

Item remarked as 240514-O02. Follow-up action is needed to be review.

14/05/2024

Contractors were reminded to immediately establish proper drainage system for pumped groundwater at Portion 7.

Item remarked as 240522-O02. Follow-up action is needed to be review.

22/05/2024

Item remarked as 240529-O02. Follow-up action is needed to be review.

29/05/2024

Follow-up action is needed to be reported in the following month.

24/04/2024

Vehicles exits should be paved to ensure vehicles remain clean when leaving the site.

(Portion 5)

Item remarked as 240502-R03. Follow-up action is needed to be review.

02/05/2024

Item remarked as 240508-R03. Follow-up action is needed to be review.

08/05/2024

Vehicles exits should be paved to ensure vehicles remain clean when leaving the site.

(Portion 4 and 5)

Item remarked as 240514-R03. Follow-up action is needed to be review.

14/05/2024

Item remarked as 240522-R03. Follow-up action is needed to be review.

22/05/2024

Improvement/Rectification was observed during follow-up audit session on 29 May 2024.

24/04/2024

Sandbag bund should be enhanced to avoid muddy runoff discharge. (Portion 3)

Item remarked as 240502-R04. Follow-up action is needed to be review.

02/05/2024

Sandbag bund should be enhanced to avoid muddy runoff discharge. (Portion 3, 4 and 7)

Item remarked as 240508-R04. Follow-up action is needed to be review.

08/05/2024

Sandbag bund should be enhanced to avoid muddy runoff discharge. (Portion 4 and 7)

Item remarked as 240514-R04. Follow-up action is needed to be review.

14/05/2024

Item remarked as 240522-R04. Follow-up action is needed to be review.

22/05/2024

Item remarked as 240529-R04. Follow-up action is needed to be review.

29/05/2024

Sandbag bund should be enhanced to avoid muddy runoff discharge. (Portion 4)

Follow-up action is needed to be reported in the following month.

02/05/2024

Exposed slope at Portion 4 should be properly covered with tarpaulin sheets.

Item remarked as 240508-R05. Follow-up action is needed to be review.

08/05/2024

Item remarked as 240514-R05. Follow-up action is needed to be review.

14/05/2024

Item remarked as 240522-R05. Follow-up action is needed to be review.

22/05/2024

Improvement/Rectification was observed during follow-up audit session on 29 May 2024.

22/05/2024

Earth bund at Portion 6 should be maintained.

Item remarked as 240529-R02. Follow-up action is needed to be review.

29/05/2024

Follow-up action is needed to be reported in the following month.

Air Quality

02/05/2024

Large mud trails were observed outside of vehicle exit at Portion 4. Contractor was reminded to ensure vehicles were properly cleaned before leaving the site.

Improvement/Rectification was observed during follow-up audit session on 8 May 2024.

Waste / Chemical Management

24/04/2024

Oily content in the drip tray should be cleared. (Portion 7)

Improvement/Rectification was observed during follow-up audit session on 2 May 2024.

14/05/2024

Construction waste near the nullah at Portion 11 should be cleared.

Item remarked as 240522-R06. Follow-up action is needed to be review.

22/05/2024

Improvement/Rectification was observed during follow-up audit session on 29 May 2024.

Ecology

24/04/2024

The removed green hoarding along Sheung Yue River due to the construction works should be replaced and maintained properly as soon as possible.

Item remarked as 240502-R01. Follow-up action is needed to be review.

02/05/2024

Item remarked as 240508-R01. Follow-up action is needed to be review.

08/05/2024

Item remarked as 240514-R01. Follow-up action is needed to be review.

14/05/2024

Item remarked as 240522-R01. Follow-up action is needed to be review.

22/05/2024

Dull green hoarding should be erected along the site boundary as according to the submitted location plan.

Item remarked as 240529-R01. Follow-up action is needed to be review.

29/05/2024

Follow-up action is needed to be reported in the following month.

29/05/2024

Silt curtain at Portion 5 should be maintained properly.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/03

Air Quality

26/04/2024

Dusty haul road should be watered regularly.

Improvement/Rectification was observed during follow-up audit session on 3 May 2024.

Water Quality

31/05/2024

Provide mitigation measure to avoid surface runoff to existing drainage.

Follow-up action is needed to be reported in the following month.

Waste/Chemical Management

26/04/2024

Drip tray should be provided for chemical/fuel containers.

Improvement/Rectification was observed during follow-up audit session on 3 May 2024.

26/04/2024

Accumulation of general refuse should be avoided.

Improvement/Rectification was observed during follow-up audit session on 3 May 2024.

10/05/2024

Provide drip tray for chemical/fuel containers.

Item remarked as 240517-F01. Follow-up action is needed to be review.

17/05/2024

Improvement/Rectification was observed during follow-up audit session on 24 May 2024.

31/05/2024

Provide drip tray for chemical/fuel containers

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/04

Air Quality

09/05/2024

Dusty stockpile should be covered by impervious sheeting. (Location: A301)

Improvement/Rectification was observed during follow-up audit session on 13 May 2024.

Ecology

25/04/2024

The 2m high green barrier of the 10m vegetated buffer zone between A2-03 and A2-04 should be maintained properly and regularly.

Improvement/Rectification was observed during follow-up audit session on 2 May 2024.

25/04/2024

The silt curtain at Bridge A should be maintained properly and regularly.

Improvement/Rectification was observed during follow-up audit session on 2 May 2024.

09/05/2024

The 2m high green barrier of the 10m vegetated buffer zone should be maintained properly and regularly.

Improvement/Rectification was observed during follow-up audit session on 13 May 2024.

30/05/2024

Silt curtain at Bridge F should be maintained properly.

Follow-up action is needed to be reported in the following month.

Water Quality

13/05/2024

Water mitigation measures at A3-01 should be enhanced to prevent muddy water discharge into Ng Tung River.

Item remarked as 240523-R01. Follow-up action is needed to be review.

23/05/2024

Item remarked as 240530-R01. Follow-up action is needed to be review.

30/05/2024

Follow-up action is needed to be reported in the following month.

30/05/2024

Sandbag bunds or concrete bunds or any other mitigation measures should be implemented to avoid surface runoff exceeds the site boundary.

Follow-up action is needed to be reported in the following month.

Waste / Chemical Management

02/05/2024

Drip tray for the chemical/fuel containers should be provided.

Improvement/Rectification was observed during follow-up audit session on 9 May 2024.

09/05/2024

The silt curtain should be maintained to avoid waste accumulation.

Improvement/Rectification was observed during follow-up audit session on 13 May 2024.

09/05/2024

Drip tray should be cleaned regularly to avoid overflow. (Location: A1)

Improvement/Rectification was observed during follow-up audit session on 13 May 2024.

Contract No.: ND/2019/05

Water Quality

29/04/2024

Cutoff drainage or earth bunding should be implemented at the pedestrian exit of Bridge C

to prevent muddy water leakage.

Improvement/Rectification was observed during follow-up audit session on 6 May 2024.

Waste/Chemical Management

29/04/2024

Drip tray for the chemical/fuel containers should be provided.

Improvement/Rectification was observed during follow-up audit session on 6 May 2024.

Contract No.: ND/2019/06

--

--

--

--

Contract No.: ND/2019/07

 

Water Quality

26/04/2024

Review any potential spillage of waste water passing through the hoarding. If any spillage is identified, please enhance the water mitigation measures and prevent it.

Improvement/Rectification was observed during follow-up audit session on 3 May 2024.

24/05/2024

The site should be generally kept clean and tidy.

Improvement/Rectification was observed during follow-up audit session on 31 May 2024.



Table 10.3       Summary Table for the Outstanding item(s) in the reporting month

Contract No.

Outstanding deficiencies since last reporting month

(Apr 2024)

Deficiencies recorded

in the reporting month

(May 2024)

Total deficiencies (including repeated deficiencies) in the reporting month

Deficiencies rectified in the reporting month

Outstanding deficiencies

need to be Follow-up in the next month

(June 2024)

Total

outstanding deficiencies

A

N

W

W/C

CH

L&V

E

P/L

A

N

W

W/C

CH

L&V

E

P/L

ND/2019/01

/

/

/

1

/

/

/

/

/

1

1

/

/

/

/

/

/

/

/

/

ND/2019/02

6

1

/

28

2

/

/

6

/

37

7

/

/

4

/

/

/

2

/

6

ND/2019/03

3

/

/

1

3

/

/

/

/

4

4

/

/

1

1

/

/

/

/

2

ND/2019/04

2

1

/

4

3

/

/

2

/

10

7

/

/

2

/

/

/

1

/

3

ND/2019/05

2

/

/

/

/

/

/

/

/

/

2

/

/

/

/

/

/

/

/

/

ND/2019/06*

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

/

ND/2019/07

1

/

/

1

/

/

/

/

/

1

2

/

/

/

/

/

/

/

/

/

Legends:

A = Air Quality

N = Construction Noise Impact

W = Water Quality

W/C = Waste / Chemical Management

CH = Cultural Heritage

L&V = Landscape & Visual

E = Ecology

P/L = Permit / Licences

* The weekly site inspection for ND/2019/06 has been terminated starting from 19/10/2023 since the termination proposal was approved by EPD on the same day.

 

Implementation Status of Environmental Mitigation Measures

10.6     According to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the Environmental Mitigation Implementation Schedule is provided in Appendix Q. The photographic records of measures as stipulated in EPs to mitigate environmental impacts in the reporting month are presented in Table 10.4.


Table 10.4   Photographic Records and Implementation Status of Measures

EP No.

Condition

Photographic Record

Implementation Status

EP-466/2013/A

2.9

 

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^[1]

EP-467/2013/A

2.9

 

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^[1]

EP-468/2013/A

2.11

     

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^[1]

EP-469/2013

2.7

 

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^[1]

EP-473/2013/A

2.13

  

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^[1]

EP-475/2013/A

2.7

 

To minimise adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high solid dull green site barrier fences shall be erected around all active works areas.

^[1]

Implementation status:

^         Mitigation measure was fully implemented

*         Observation/reminder was made during site audit but improved/rectified by the contractor

#         Observation/reminder was made during site audit but not yet improved/ rectified by the            contractor

X        Non-compliance of mitigation measure

¡P         Non-compliance but rectified by the contractor

N/A   Not Applicable at this stage as no such site activities were conducted in the reporting period

Remark:

 [1]:     Barrier fences might be subjected to change according to the phasing plan designed at detailed design stage

 

Implementation Status of Water Quality Mitigation Measures

10.7     The water quality mitigation measures detailed in the EIA Report and the Updated EM&A Manual are recommended to be implemented during the construction phase. Water quality mitigation measures implemented by the contractors were closely monitored to prevent water pollution, especially during rainy season. An updated summary of the Environmental Mitigation Implementation Schedule is provided in Appendix Q. Specific water quality mitigation measures for major construction works in the reporting month are presented in Table 10.5.


 

Table 10.5       Specific Water Quality Mitigation Measures for Major Construction Works in the Reporting Month

Works Contracts

Photographic Records

ND/2019/01

Hard paved exposed slope surface

Provision of maintenance for the drainage and sump pit around the construction site

ND/2019/02

Hard paved exposed haul road

Hard paved exposed slope surface

ND/2019/03

Hard paved exposed haul road

Watering the main haul road regularly.

ND/2019/04

Hard paved exposed slope surface

Deployment of silt curtain around works area in Ng Tung River

ND/2019/05

Covering dusty stockpile at different works area

Provision of sand bags around works area and sump pit to prevent the untreated muddy water

ND/2019/07

Covering exposed slope surface with tarpaulin

De-silting waste water before discharge

Water quality mitigation measures for site(s) in operation phase, remaining defect works

ND/2019/06

Hard paved exposed haul road

Hard paved exposed haul road

 


 

Solid and Liquid Waste Management Status

10.8     Waste generated from Contract Nos. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05 and ND/2019/07 included inert construction and demolition (C&D) materials and non-inert C&D wastes in the reporting month. The site of ND/2019/06 was handed over to AFCD for operation since 4 April 2022.

10.9     The amount of wastes generated by the construction works of the Contract Nos. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05 and ND/2019/07 during the reporting month are shown in Appendix R. The site of ND/2019/06 was handed over to AFCD for operation since 4 April 2022.

10.10 The Contractors are advised to minimise the wastes generated through recycling or reusing. All mitigation measures stipulated in the Updated EM&A Manual and waste management plans shall be fully implemented. The status of implementation of waste management and reduction measures are summited in Appendix Q.

Ecological Mitigation Measures ¡V Creation of Long Valley Nature Park (LVNP)

10.11 Based on the findings of the EIA Report, the area of Long Valley has been assessed as of high to very high ecological value and is the largest contiguous area of freshwater wetland habitats in Hong Kong. To safeguard the ecological value of Long Valley, about 37 hectares of land in Long Valley has been proposed to develop into Long Valley Nature Park (LVNP) for conserving and enhancing the ecologically important environment as well as for compensation of the wetland loss due to the NDA development.

10.12  LVNP is developed according to the approved Habitat Creation and Management Plan (HCMP) submitted under EP-468/2013/A. HCMP provides a framework and specifications for development and management of LVNP and guides the development to maintain and enhance the 37 hectares of low-lying wetland habitats.

10.13 Regarding the design, the zoning of land use in LVNP is intended to maintain the existing mosaic pattern of wet and dry agriculture, while controlling the activities that could potentially disturb target habitats and species. LVNP will be divided into three broad zones of land use as below:

       Biodiversity Zone of about 21 hectares largely designated for biodiversity conservation through cultivation of specified crops and habitat management.

       Agricultural Zone of about 11 hectares designated for commercially focuses crop production and eco-friendly agricultural practice for farming.

       Visitor Zone of about 5 hectares designed to accommodate visitors as well as storage and other facilities and for educational purposes.

10.14 The construction of LVNP started in late 2019 and was expected to be completed in 2023. During the construction period, the progress of construction and wetland enhancement works has been under observation by different stakeholders including AFCD and green groups. Close communication between AFCD and CEDD were conducted to exchange views on conservation, restoration and management of habitats as well as on the planning and design of the park. In addition, advices from green groups, Hong Kong Bird Watching Society (HKBWS) and The Conservancy Association (CA), have been taken on habitat management of Long Valley and potential effects on habitat and wildlife of each individual work conducted in Long Valley. The last meeting was held on 18 November 2022 to share the progress of LVNP with different stakeholders, including CEDD, AFCD, CA, HKBWS, Contractor, ET, IEC and farmers.

10.15 Proposals on wetland creation and restoration, dry agricultural land creation, pond creation, water treatment wetland and design of irrigation channel were submitted by the Contractor to achieve the objectives stated in HCMP and accepted by the Engineer with consent from AFCD before implementation. The Contractor would consult the stakeholders for recommendations and suggestions on mitigation measures to minimise the environmental impacts arising from construction works. The progress of works would be arranged to minimise impacts to avifauna and maintain the habitat for avifauna. The photographic records of site activities in LVNP are presented in Table 10.6.


 

Table 10.6       Photographic Records of Site Activities in LVNP

Continuing agricultural practice in existing farmland to maintain habitats in Long Valley

Open water Habitat

Open water Habitat

Creation of wetland with designated habitat for biodiversity conservation

 

Planting of paddy rice to provide foraging ground for Yellow-breasted Bunting

 

Enhancement of irrigation channel to provide reliable water source for farmland in Long Valley

Provision of bird island (hidden area)

Restoring of water flea pond to provide food source to water birds

Construction of storage sheds for farmers

An Artamus fuscus was recorded

Wet agricultural land