Table II Summary
Table for EM&A Activities in the Reporting Month
EM&A Activities |
Monitoring Station (s) |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
||
1-hr Total Suspended Particulates (TSP) Monitoring |
FLN-DMS1 |
N/A |
N/A |
6, 10,
14, 20, 24 and 30 May 24 |
6, 10,
14, 20, 24 and 30 May 24 |
N/A |
N/A |
N/A |
FLN-DMS3 |
N/A |
N/A |
6, 10,
14, 20, 24 and 30 May 24 |
|||||
FLN-DMS5 |
3, 9, 13,
17, 23 and 29 May 24 |
3, 9, 13,
17, 23 and 29 May 24 |
N/A |
|||||
KTN-DMS4(B) |
3, 9, 13,
17, 23 and 29 May 24 |
3, 9, 13,
17, 23 and 29 May 24 |
N/A |
|||||
24-hr TSP Monitoring |
FLN-DMS1 |
N/A |
N/A |
3, 9, 13,
17, 23 and 29 May 24 |
3, 9, 13,
17, 23 and 29 May 24 |
N/A |
N/A |
N/A |
FLN-DMS3 |
N/A |
N/A |
3, 9, 13,
17, 23 and 29 May 24 |
|||||
FLN-DMS5A |
3, 9, 13,
17, 23 and 29 May 24 |
3, 9, 13,
17, 23 and 29 May 24 |
N/A |
|||||
KTN-DMS4(B) |
3, 9, 13,
17, 23 and 29 May 24 |
3, 9, 13,
17, 23 and 29 May 24 |
N/A |
|||||
Noise Monitoring |
CP-FLN-NMS1 |
N/A |
6, 14, 20 and 30 May 24 |
N/A |
||||
CP-FLN-NMS2 |
N/A |
6, 14, 20
and 30 May 24 |
N/A |
|||||
CP-KTN-NMS2 |
9, 13, 23
and 29 May 24 |
N/A |
N/A |
|||||
CP-KTN-NMS3 |
||||||||
CP-KTN-NMS5 |
||||||||
CP-KTN-NMS6 |
N/A |
9, 13, 23
and 29 May 24 |
||||||
Ecological Survey |
Monitoring
of Measures to Minimise Disturbance to Water Birds
on Ng Tung River,
Sheung Yue River, and Long Valley |
N/A |
N/A |
3, 6, 7,
14, 17, 20, 23, 30 and 31 May 2024 |
7, 14,
23 and 30 May 2024 |
N/A |
N/A |
N/A |
Monitoring of Measures to Minimise Impacts
to Ma Tso Lung Stream and Siu Hang San Tsuen Stream |
13 May 2024 |
N/A* |
13 May 2024 |
13 May 2024 |
N/A* |
N/A* |
N/A* |
|
Monitoring of Measures to Minimise Impacts on
Ecological Sensitive Habitats from Disturbance and Pollution |
22 and
28 May 24 |
22 and 28
May 24 |
22 May
24 |
22 May
24 |
22 May
24 |
N/A* |
N/A* |
|
Egretry Monitoring |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
24-hr RSP (Ambient
Arsenic) Monitoring for Land Contamination |
6, 10,
16, 22 and 28 May 24 |
N/A |
6, 10,
16, 22 and 28 May 24 |
N/A |
N/A |
N/A |
N/A |
|
Water Quality Monitoring |
N/A |
2, 4, 6,
8, 10, 14, 16, 18, 20, 22, 24, 27, 29 and 31 May 24 |
N/A |
2, 4, 6,
8, 10, 14, 16, 18, 20, 22, 24, 27, 29 and 31 May 24 |
N/A |
N/A |
N/A |
|
Landfill Gas Monitoring |
24
May 24 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Built Heritage Monitoring |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
10, 14, 21 and 28 May 24 |
2, 8, 14, 22 and 29 May 24 |
3, 10, 17, 24 and 31 May 24 |
2, 9, 13, 23 and 30 May 24 |
6, 16, 20 and 27 May 24 |
NIL |
3, 10, 17, 24 and 31 May 24 |
Remarks:
N/A
– No relevant monitoring is required according to the updated EM&A Manual
N/A*
– No relevant monitoring is required according to the Baseline Ecological
Monitoring Plan (Table 3.1)
[1] Since the distance between monitoring
station CP-KTN-NMS2 and site boundary of ND/2019/03 under EP-468/2013/A exceeds
300m, the monitoring station is not applicable to ND/2019/03
[2] Since the distance between monitoring
station CP-KTN-NMS3 and site boundary of ND/2019/03 under EP-468/2013/A exceeds
300m, the monitoring station is not applicable to ND/2019/03
[3] Since the distance between monitoring
station CP-KTN-NMS1 and site boundary of ND/2019/02 under EP-469/2013 exceeds
300m, the monitoring station is not applicable to ND/2019/02
[4] Since the distance between monitoring
station FLN-DMS1 and site boundary of ND/2019/05 under EP-473/2013/A
exceeds500m, the monitoring station is not applicable to ND/2019/05
[5] Since the distance between monitoring
station FLN-DMS3 and site boundary of ND/2019/03 and ND/2019/04 under
EP-473/2013/A exceeds 500m, the monitoring station is not applicable to
ND/2019/03 and ND/2019/04
[6] Since the distance between monitoring
station FLN-DMS5 and site boundary of ND/2019/05 under EP-473/2013/A exceeds
500m, the monitoring station is not applicable to ND/2019/05
[7] Since the distance between monitoring
station CP-FLN-NMS2 and site boundary of ND/2019/03 and ND/2019/04 under
EP-473/2013/A exceeds 300m, the monitoring station is not applicable to
ND/2019/03 and ND/2019/04
[8] Since the distance between monitoring
station CP-FLN-NMS1 and site boundary of ND/2019/03 under EP-473/2013/A exceeds
300m, the monitoring station is not applicable to ND/2019/03