2.1
The
Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs) are one of the important sources of
land and housing supply in the medium and long term. The development of the KTN
and FLN NDAs will be implemented in phase for full completion by 2031. The
Phase 1 of the NDAs development, comprising the Advance Works and First Stage
Works, is targeted to be implemented from the second half of 2019
progressively. The Advance and First Stage Works would include site formation,
engineering infrastructure works (including roads, drainage, sewerage,
waterworks, landscaping works, pumping stations, and fresh water and flushing
water service reservoirs), soil remediation, reprovisioning of North District
Temporary Wholesale Market, development of a nature park at Long Valley and
implementation of environmental mitigation measures.
2.2
The
scope of works under the Advance and First Stage Works comprises the following:
a)
The
Advance Works (PWP item No. 7747CL-2) consist of:
i)
site
formation of land (including soil remediation) in KTN and FLN NDAs for housing,
community facilities and engineering infrastructure;
ii) construction of roads including the
eastern section of Fanling Bypass (FLBP(E))
connecting the FLN NDA to Fanling Highway and other
roads with footpaths and cycle tracks, and associated junction/ road
improvements;
iii) engineering infrastructure works
including drainage. Sewerage (including two sewage
pumping stations), waterworks (including a fresh water service reservoir and a
flushing water service reservoir in the KTN NDA), landscape works and slopeworks;
iv) part expansion and upgrading of Shek
Wu Hui Sewage Treatment Works (SWHSTW);
v)
reprovisioning
works; and
vi) implementation of environmental
mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in (i)
to (v) above.
b)
The
First Stage Works (PWP item No. 7759CL) consist of:
i)
development
of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung Yue River
for connection between these two facilities;
ii) reprovisioning of two egretry sites in the FLN NDA and enhancement works to an
existing egretry site in the KTN NDA;
iii) site formation of land for a village
resite area and a district
police station in the KTN NDA;
iv) engineering infrastructure works
including roads, drainage, sewerage, waterbirds, and landscape works; and
v)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (iv) above.
2.3
The
Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule
3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October
2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director
of Environmental Protection pursuant to the EIA Ordinance. The relevant EPs
under the Project and the respective Work Contracts are summarised in Tables
2.1a and 2.1.b.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP No. |
Designated Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle
Peak Road Diversion |
ü |
¡@ |
|||||||
Kwu Tung North New Development
Area Road P1 and P2 and Associated New Kwu Tung
Interchange and Pak Shek Au Interchange Improvement |
ü |
¡@ |
|||||||
Kwu Tung North New Development
Area Road D1 to D5 |
ü |
ü |
¡@ |
||||||
Sewage
Pumping Stations in Kwu Tung North New Development
Area |
ü |
¡@ |
|||||||
Utilization
of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
|||||||
Fanling Bypass Eastern Section |
ü |
ü |
ü |
¡@ |
|||||
Reprovision
of temporary Wholesale Market in Fanling North New
Development Area |
ü |
¡@ |
|||||||
EP-546/2017 |
Fanling North Temporary Sewage Pumping
Station |
ü |
¡@ |
Notes:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope
of Works under concerned EP
Environmental Permit (EP) No. |
Work Contract(s) |
Scope of Works under
concerned EP(s) |
Site Layout Plan under
concerned EP(s) |
EP-466/2013/A(Part) |
C1 |
Realign Castle Peak
Road and join with the Pak Shek Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction of new
primary distributor road (P1) within Kwu Tung North
New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction of new
primary distributor roads (D1, D3, D4 and part of D5) within Kwu Tung North New Development Area |
Figure 14 |
C3 |
Development of a nature
park at Long Valley and ecological mitigation and enhancement works for the
nature park (Condition 2.9) |
Figure 15 |
|
EP-469/2013(Part) |
C2 |
Construction of one
sewage pumping station in Kwu Tung North with
installed capacity of more than 2,000 m3 per day |
Figure 16 |
EP-470/2013/A(Part) |
C1 |
Construction of service
reservoir and watermain for the reuse of treated sewage effluent for reuse in
Kwu Tung North Development Areas |
Figure 17 |
EP-473/2013/A(Part) |
C3 |
Establishment of alternative egretry sites
and enhance the existing egretry site at Ho Sheung Heung and/or its vicinity
(Condition 2.7) |
Figure 18 |
EP-473/2013/A(Part) |
C5A |
Construction of new
district distributor inside FLN NDA, which provides a linkage between the Man
Kam To Road and the proposed Fanling
Bypass Eastern Section |
Figure 19 |
EP-473/2013/A(Part) |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The re-provisioned
wholesale market will have approximately 1,000 market stalls within a site
area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a
temporary sewage pumping station in Fanling North
with installed capacity (average dry weather flow) of about 3,600m3/day |
Figure 22 |
Remark: The EP(s) not
related to the Project of the First Phase of the Kwu
Tung North (KTN) and Fanling North (FLN) New
Development Area (NDA) Development Areas are not included in the Table.
2.4
The
site boundary of the Project and all Works Contracts are shown in Drawing No. 1.
2.5
The
required submissions and submission status under Environmental Permits are
shown in Appendix U.
2.6
The
site layout
plans
under concerned Environmental Permits are shown in Figures
12 - 22.
2.7
Different
parties with different levels of involvement in the Project organisation include:
Project
Proponent ¡V Civil Engineering and Development Department (CEDD)
Supervisor / Supervisor's Representative
¡V AECOM Asia Co. Ltd.
Environmental
Team (ET) ¡V Wellab Limited
Independent
Environmental Checker (IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The
names and contact numbers of key personnel are summarised in Table
2.2.
Table 2.2 Key
Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
Civil
Engineering and Development Department, HKSAR (CEDD) |
Project Proponent |
Mr.
Ryan Chau |
3797
5387 |
3547 1658 |
Supervisor / Supervisor's Representative (AECOM
Asia Co. Ltd.) |
Chief
Resident Engineer |
Mr.
Alan Lee |
6398 5982 |
2680 9515 |
Senior Resident Engineer |
Mr. King-man Chan |
9651 2635 |
2680 9515 |
|
Environmental
Team (Wellab Limited) |
Environmental Team Leader |
Dr.
Priscilla Choy |
2898 7388 |
2898
7076 |
Independent
Environmental Checker (MottMac) |
Independent
Environmental Checker |
Mr.
Thomas Chan |
2828
5967 |
2827
1823 |
Contract No. ND/2019/01 Contractor (Build King
¡V Richwell Engineering Joint Venture) |
Site
Agent |
Mr.
Ivan Leung |
9640 8340 |
-- |
Environmental
Officer |
Mr.
Edward Tam |
9287 8270 |
||
Contract No. ND/2019/02 Contractor (Chun Wo ¡V
Kwan Lee Joint Venture.) |
Site
Agent |
Mr.
Andy Chan |
3485 9780 |
-- |
Environmental
Officer |
Mr. Sofi So |
9637 1667 |
||
Contract No. ND/2019/03 Contractor (Sang Hing Kuly Joint Venture) |
Site
Agent |
Mr.
Tang Wing Kai |
9300 7037 |
-- |
Environmental
Officer |
Mr.
Ken Cheung |
9803
5297 |
||
Contract No. ND/2019/04 Contractor (Daewoo ¡V
Chun Wo ¡V Kwan Lee Joint Venture) |
Site
Agent |
Mr.
Eric Wu |
9786
8630 |
-- |
Environmental
Officer |
Mr.
Sam Lam |
6178
3179 |
||
Contract No. ND/2019/05 Contractor (CRCC ¡V
Paul Y. Joint Venture) |
Site
Agent |
Mr.
Darvin Lo |
9467
5891 |
-- |
Environmental
Manager |
Mr.
Pan Fong |
9436
9435 |
||
Environmental
Officer |
Mr.
Kevin Cheung |
6117
1344 |
||
Contract No. ND/2019/06 Contractor (New
Concepts Engineering Development Ltd.) |
Project
Manager |
Mr. Joe Cheng |
9861 0060 |
-- |
Environmental
Officer |
Mr.
Alex Choy |
6360
3236 |
||
Contract No. ND/2019/07 Contractor (China Road
and Bridge Corporation) |
Site
Agent |
Mr.
Mac Chow |
9169
9567 |
-- |
Environmental
Officer |
Mr.
K. M. Lui |
5113
8223 |
Environmental
Supervisor |
Mr.
Attlee Chau |
6386
9018 |
2.9
The
major site activities undertaken in the reporting month are shown in Table 2.3.
Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract No. |
Site Activities (March 2024) |
ND/2019/01 |
(a)
Drainage
works, watermain works and sheet piles in Portion 1a (b)
Site
formation, erection of hoarding and construction of noise barrier in Portion
1c (c)
Sheet
piling, site clearance, site formation, construction of subway, drainage
works and road works in Portion 2 (d)
Watermain
works and
site formation in Portion 3 (e)
Site
formation, excavation and preparation works for pipe jacking in Portion
5 (f)
Backfilling,
drainage works, watermain works and district cooling system in Portion 6a (g)
Operation
of HAC treatment facility in Portion 6b (h)
Excavation
and drainage works in Portion 7 (i)
RC
construction of fresh water reservoir, drainage works, watermain works, backfilling
works and construction of receiving pit in Portion 8a (j)
Trenchless
work and watermain construction in Portion 8b (k)
Sheet
piling, excavation, drainage, watermain works and district cooling system in
Portion 9b (l)
Excavation and drainage works
in Portion 11b (m)
Site clearance, removal of existing structures, site formation and
erection of hoarding in Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry agricultural land creation -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Dry Weather Flow Interception (DWFI) |
ND/2019/04 |
(a)
Pile Cap (b)
Back Filling (c)
Excavation (d)
Grouting (e)
Road works (f)
Formwork and Scaffolding Erection (g)
Rebar Fixing (h)
ELS |
ND/2019/05 |
(a)
South Team -
E3-04b ¡V Pier in progress -
E4-01 ¡V Pier completed & pier head in progress. -
E4-02 ¡V Pipe pile wall completed. Excavation in progress. -
E4-03M ¡V Pipe pile wall in progress. -
D2-04M ¡V Removal of existing abandoned UU completed. ELS in progress. -
Works in TWSRE A. BBI
cover walkway (Steelwork) ¡V 1st stage completed. B. Extension
of HKY Footbridge ¡V Temporarily opened to public. C. BBI
Toilet ¡V Basement Wall is completed. Backfilling and drainage work in
progress. D. Connecting
Road L201 to D300 ¡V Pavement to base coarse is completed. E. D400
Road Works CH285 to 380 ¡V Backfilled to formation. Subbase in progress. F. FW02 ¡V
Footing and wall are completed. Backfilling completed. Pavement work in
progress. -
Works in TWSRW A. FS04
¡VRock slope strengthening works in progress. Slope toe U-Channel in progress. B. Sewerage
work ¡V Laying 600Dia pipes from FW06 toward FS04 is in progress. C. Gas Pipe
laying (IPA400/HP600 ¡V pipe laying in progress. Target completion in June
2024. D. 1st
Stage fresh watermain diversion completed on 2 February 2024 by WSD. E. Lift
LT02 ¡V ELS in progress. -
Noise barrier NB109 A. Bay
9,10, 11 ¡V Top wall completed. B. Bay 12 ¡V
Backfilling in progress C. Bay 13 ¡V
ELS in progress. D. Bay
16-20 ¡V Site clearance and setting temporary lighting in progress. -
Noise barrier NB70 A.
Bay 1-5 ¡V Site clearance and setting temporary lighting in progress. -
Noise barrier NB69 A.
Bay 5c, 6a ¡V Top wall completed. Backfilling in progress. B.
Bay 2, 3, 4 ¡V ELS is in progress. C.
Bay 6c, 7 ¡V Footing completed. Bottom wall in progress. D.
Bay 8 ¡V ELS in progress. -
Noise barrier NB110 A.
Bay 3, 4, 5, 8, 9 ¡V Footing and wall completed. B.
Bay 6,7 ¡V Removal of existing footings completed. Bay 6 footing
completed. Bay 7 footing in progress. C.
Bay 10 Predrilling completed -
Noise barrier NB 29 A.
Bay 12, 13 ¡V Footing (near Fanling Hwy)
completed. B.
Bay 8 to 13 ¡V Sheetpiling in progress (b)
North Team -
Rebar
fixing for 2 nd pour of C1 02 portal beam
construction in progress -
Side
formwork erection for C1 01 MJ portal construction in progress
. -
Falsework
erection for B2 01 cross head construction in progress. -
Falsework
erection for B2 02 & B2 03 cross head construction completed. Formwork
erection in
progress. -
Construction
of remaining abutment wall near B1 02 portal beam was in progress. -
Backfilling
at C3 03ab, C3 04ab, C4 02 & C4 01b were in progress -
Backfilling
and sheet extraction at C2 01 completed. -
On Kui
Street Construction of manhole & associated DN 900 drain pipe were in progress -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were in progress. -
JCR:
Construction of pipe support for DN 150 exposed pipe in progress. -
JCR &
Tong Hang Village J/O improvement works: Construction of box culvert &
extension head wall
was in progress. -
Temporary
haul road in On Lok Garden was in progress. (c)
Bridges and Structures -
Type A segment fabrication completed in Huizhou
casting yard. Type C precast segment commenced at DongGuan
Casting yard. -
Total 5 78 segments were delivered to site, and
total 5 46 segments erected. -
C2 0 2 T span completed. -
Segment erection at C2 01 by LG in progress. -
Rebar fixing at Bridge B1 in progress. -
Trial panel for type C segment is completed. -
Total 210 pcs of parapet skin fabricated; 93
pcs of parapet skin arrived to site , 72 pcs of parapet skin erected on Bridge E1. -
Construction of D2 01 SOP in progress. -
Installation of drainage system in the deck
void commenced at Bridge D1&E1. -
Dismantle of E&M for the lifting tower
NF38A completed. (d)
Form Traveler -
T Span at D2 02 completed. -
Form traveler launching for 08th pair segment at D2 03 in progress. -
Form traveler launching for 06th pair segment at E2 01 in progress. -
Form traveler rebar fixing for 2nd pair segment at E2 03 in progress. -
FT02 dismantling at E3 01 in progress -
Completed concreting E2 E2 01 E2 02 S05, E2 E2 01 E1 04 01 S05 -
Completed concreting D2 D2 02 D2 03 S11, D2 D2 02 D2 01 S 11 -
Completed concreting D2 D2 03 D2 04 S07, D2 D2 03 D2 02 S07. -
Completed concreting E2 E2 03 E2 02 S01
& E2 E203 E3 01 S01. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road
works at Portion 1, 4 and
5 (b)
C&D
waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at Portion 2, 3, 4
and 5 (d)
Construction of box culvert at Portion 2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at Portion 4 (g)
Waterworks at Portion 1, 2 and 4 |
2.10 Copies
of Contractors¡¦ construction programmes are
provided in Appendix A.
2.11 A summary of the relevant permits, licences, and/or notifications on environmental protection
for this Project is presented in Table
2.4.
Table 2.4 Status of Environmental
Licences, Notifications and Permits
Contract
No. |
Permit
/ Licence No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental
Permit (EP) |
||||
ND/2019/01 |
EP-466/2013/A |
21/11/2013 |
N/A |
Valid |
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-470/2013/A |
21/11/2013 |
N/A |
Valid |
|
ND/2019/02 |
EP-469/2013 |
21/11/2013 |
N/A |
Valid |
ND/2019/03 |
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
|
ND/2019/04 |
EP/473/2013/A |
27/01/2017 |
N/A |
Valid |
EP/546/2017 |
16/11/2017 |
N/A |
Valid |
|
ND/2019/05 |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
ND/2019/06 |
EP-475/2013/A |
13/01/2017 |
N/A |
Valid |
Construction
Noise Permit (CNP) |
||||
ND/2019/01 |
GW-RN0997-23 |
01/10/2023 |
31/03/2024 |
Cancelled and superseded by GW-RN0238-24 in the reporting month |
GW-RN1328-23 |
25/12/2023 |
24/03/2024 |
Expired in reporting month |
|
GW-RN0053-24 |
21/01/2024 |
20/04/2024 |
Valid |
|
GW-RN0073-24 |
29/01/2024 |
28/04/2024 |
Valid |
|
GW-RN1146-23 |
19/11/2023 |
18/05/2024 |
Valid |
|
GW-RN0187-24 |
29/02/2024 |
28/05/2024 |
Valid |
|
GW-RN0031-24 |
13/01/2024 |
12/04/2024 |
Valid |
|
GW-RN0238-24 |
15/03/2024 |
14/06/2024 |
Valid |
|
GW-RN0069-24 |
01/03/2024 |
31/08/2024 |
Valid |
|
GW-RN0070-24 |
01/03/2024 |
31/08/2024 |
Valid |
|
GW-RN0198-24 |
01/03/2024 |
30/06/2024 |
Valid |
|
GW-RN0290-24 |
25/03/2024 |
24/06/2024 |
Valid |
|
ND/2019/02 |
GW-RN1400-23 |
01/01/2024 |
31/03/2024 |
Expired in reporting month |
GW-RN1163-23 |
08/11/2023 |
07/04/2024 |
Valid |
|
GW-RN0130-23 |
10/02/2024 |
09/06/2024 |
Valid |
|
ND/2019/04 |
GW-RN1408-23 |
29/12/2023 |
28/03/2024 |
Expired in reporting month |
GW-RN0051-24 |
26/01/2024 |
25/03/2024 |
Expired in reporting month |
|
GW-RN0020-24 |
08/01/2024 |
07/04/2024 |
Valid |
|
GW-RN0095-24 |
05/02/2024 |
04/05/2024 |
Valid |
|
GW-RN0246-24 |
13/03/2024 |
12/06/2024 |
Valid |
|
GW-RN0351-24 |
28/03/2024 |
25/05/2024 |
Valid |
|
ND/2019/05 |
GW-RN1366-23 |
01/01/2024 |
31/03/2024 |
Expired in reporting month |
GW-RN1369-23 |
27/12/2023 |
26/03/2024 |
Expired in reporting month |
|
GW-RN1415-23 |
01/01/2024 |
31/03/2024 |
Expired in reporting month |
|
GW-RN0014-24 |
12/01/2024 |
11/04/2024 |
Valid |
|
GW-RN0097-24 |
01/02/2024 |
31/05/2024 |
Valid |
|
GW-RN0147-24 |
29/02/2024 |
28/04/2024 |
Valid |
|
GW-RN0301-24 |
27/03/2024 |
26/06/2024 |
Valid |
|
GW-RN0132-24 |
01/03/2024 |
30/06/2024 |
Valid |
|
GW-RN0165-24 |
01/03/2024 |
31/08/2024 |
Valid |
|
Notification
pursuant to Air Pollution Control (Construction Dust) Regulation |
||||
ND/2019/01 |
451792 |
11/12/2019 |
N/A |
Valid |
477388 |
02/03/2022 |
N/A |
Valid |
|
ND/2019/02 |
454012 |
05/03/2020 |
N/A |
Valid |
ND/2019/03 |
452216 |
24/12/2019 |
N/A |
Valid |
452332 |
31/12/2019 |
N/A |
Valid |
|
452333 |
31/12/2019 |
N/A |
Valid |
|
ND/2019/04 |
461184 |
23/10/2020 |
N/A |
Valid |
ND/2019/05 |
454323 |
13/03/2020 |
N/A |
Valid |
ND/2019/06 |
449369 |
24/09/2019 |
N/A |
Valid |
ND/2019/07 |
459393 |
28/08/2020 |
N/A |
Valid |
Billing
Account for Disposal of Construction Waste |
||||
ND/2019/01 |
7036265 |
17/01/2020 |
N/A |
Valid |
ND/2019/02 |
7036898 |
01/04/2020 |
N/A |
Valid |
ND/2019/03 |
7036378 |
22/01/2020 |
N/A |
Valid |
ND/2019/04 |
7038391 |
22/09/2020 |
N/A |
Valid |
ND/2019/05 |
7036901 |
01/04/2020 |
N/A |
Valid |
ND/2019/06 |
7035473 |
17/10/2019 |
N/A |
Valid |
ND/2019/07 |
7038309 |
14/09/2020 |
N/A |
Valid |
Registration
of Chemical Waste Producer |
||||
ND/2019/01 |
5213-545-B2578-01 |
10/01/2020 |
N/A |
Valid |
ND/2019/02 |
5213-548-C4439-01 |
06/05/2020 |
N/A |
Valid |
ND/2019/03 |
5213-623-S4231-01 |
14/04/2020 |
N/A |
Valid |
ND/2019/04 |
5211-624-D2709-01 |
26/11/2020 |
N/A |
Valid |
ND/2019/05 |
5213-625-C4464-01 |
20/05/2020 |
N/A |
Valid |
ND/2019/06 |
5213-625-N2716-01 |
02/10/2019 |
N/A |
Valid |
ND/2019/07 |
5213-625-C4498-01 |
21/09/2020 |
N/A |
Valid |
Effluent
Discharge License under Water Pollution Control Ordinance |
||||
ND/2019/01 |
WT00036071-2020 |
22/06/2020 |
30/06/2025 |
Valid |
WT00036073-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036067-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036075-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036076-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00037191-2020 |
21/04/2022 |
28/02/2026 |
Valid |
|
WT00037204-2020 |
16/11/2022 |
28/02/2026 |
Valid |
|
WT00037412-2021 |
16/11/2022 |
30/04/2026 |
Valid |
|
WT00037564-2021 |
19/04/2021 |
30/04/2026 |
Valid |
|
WT00037886-2021 |
28/06/2021 |
30/06/2026 |
Valid |
|
WT00041311-2022 |
21/06/2022 |
30/06/2027 |
Valid |
|
ND/2019/02 |
WT00036584-2020 |
21/10/2020 |
31/10/2025 |
Valid |
WT00036952-2020 |
17/12/2020 |
31/12/2025 |
Valid |
|
ND/2019/03 |
WT00035847-2020 |
12/08/2020 |
31/08/2025 |
Valid |
WT00036414-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
WT00037771-2021 |
08/07/2021 |
31/07/2026 |
Valid |
|
WT00035984-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
ND/2019/04 |
WT00037539-2021 |
02/06/2022 |
30/04/2026 |
Valid |
ND/2019/05 |
WT00036996-2020 |
22/12/2020 |
31/12/2025 |
Valid |
ND/2019/06 |
WT00035415-2019 |
20/03/2020 |
31/03/2025 |
Valid |
ND/2019/07 |
WT00037526-2021 |
21/04/2022 |
31/05/2026 |
Valid |