11.1 Four (4)
Limit Level for Suspended Solid (SS) and Four (4)
Limit Level for turbidity of impact water quality monitoring were recorded.
After investigation, Three (3) Limit Level for SS and
Three (3) Limit Level for turbidity was considered partially due to Contract No. ND/2019/04. The other exceedance
was considered due to the other external factors rather than the contract
works.
11.2 No Action/Limit Level exceedance for air
quality, ambient arsenic and landfill gas monitoring was recorded in the
reporting month.
11.3 One (1) Action Level for construction noise
monitoring was recorded. The summary of exceedance record in the reporting
month is shown in Appendix O.
11.4 Ecological monitoring was carried out in the reporting
month. Five (5) action level exceedance and four (4) limit level exceedance for non-aquatic
fauna were recorded at T1, T3, T4 & T6. The exceedance were considered non-project
related.
11.5 Should the monitoring results of the environmental
monitoring parameters at any designated monitoring stations indicate that
Action / Limit Levels are exceeded, the actions in accordance with the Event/Action
Plan in Appendix N would be carried
out.
11.6 No environmental non-compliance was recorded in the
reporting month.
11.7 Two (2) environmental complaint were received in the reporting month. The Cumulative
Complaint Log since the commencement of the Project is presented in Appendix
S.
11.8
There was no
successful environmental prosecution or notification of summons received since
the Project commencement. The Cumulative Log for environmental summon and
successful prosecution since the commencement of the Project is presented in Appendix T.