Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (April to June 2024)

ND/2019/01

(a)          Drainage works, watermain works, sheet piles, site formation and slope works in Portion 1a

(b)         Site formation and construction of noise barrier in Portion 1c

(c)          Sheet Piling, Site formation work, construction of subway, road works and drainage works in Portion 2

(d)         Site formation, site clearance, excavation, slope work, drainage and watermain works in Portion 3

(e)          Watermain works, excavation, backfilling, road works and pipe jacking in Portion 5

(f)          Drainage works, backfilling, road works and watermains works in Portion 6a

(g)         Operation of HAC treatment facility in Portion 6b

(h)         Sheet piling, excavation, stockpile of soil, drainage works and watermain works in Portion 7

(i)           RC construction of fresh water reservoir, backfilling works, drainage works, watermain works and ELS installation for receiving pit in Portion 8a

(j)           Trenchless work, excavation, watermain works and ground treatment in Portion 8b

(k)         Sheet piling, excavation, road works, drainage works, watermain works and district cooling system in Portion 9b

(l)           Site formation, excavation , drainage, sewage, watermain and roadworks in Portion 11b

(m)       Site clearance, removal of existing structure, site formation and stockpile of soil in Portion 13

ND/2019/02

(a)           Pipe Jacking

(b)           Backfilling

(c)           Concreting

(d)           Bedding & Pipe Laying

(e)           ELS

(f)            Sheet Pile Installation

(g)           Cut and Fill of Slope

ND/2019/03

(a)      Portion 2 to Portion 20C

-          Wetland creation & restoration, Dry agricultural land creation

-          Construction of Water Treatment Wetland

-          Tree felling and tree pruning work

ND/2019/04

(a)           Pile Cap

(b)           Back Filling

(c)           Excavation

(d)           Grouting

(e)           Road works

(f)            Formwork and Scaffolding Erection

(g)           Rebar Fixing

(h)           ELS

ND/2019/05

(a)           North Team Works

-          Backfilling, drainage work & reinstatement of grasscrete at C4 02, C4 01ab, C3 03ab & C3 03ab.

-          Haul Road to bridge deck In On Lok Garden.

-          Construction of remaining abutment wall near portal B2 01.

-          Construction of FW 53.

-          Water works & drainage works at Jockey Club Rd.

-          Slope toe drainage works of FS05 at Jockey Club Rd.

-          Road works of northbound of Jockey Club Rd & ducting works at central median and across Jockey Club Rd.

-          Construction of new box culvert extension & retaining wall & slope works at Tong Hang Tsuen.

-          Drainage works DN 900 at On Kui Street near B1.

(b)          Viaduct Works

-          Segments erection by LG at Bridges nos. C1 & C2.

-          SOP construction at D2-01.

-          Trimming of existing lift tower no. NF83A.

-          Construction of Bridge B1.

-          Precast parapet skin fabrication.

-          Parapet construction at Bridge nos. C4, D1 and E1.

-          Segment fabrication for Bridge no. B2.

-          Carrier drain installation at Bridge nos. C3, C4, D1 and E1.

-          Deck void lighting installation at Bridge nos. C3, C4, D1 and E1.

(c)          South Team Works

-          E4-02 pier & pier head construction

-          TWSRW ¡V Road work and UUs laying (Section P800 CH 450 to 600).

-          TWSRW ¡V Hydroseeding at FS04, strengthening work of rock surface at FS04

-          TWSRW ¡V Construction of FS04 slope toe u-channel

-          TWSRW ¡V Gas (IPA400 and HP600) diversion work

-          TWRSW ¡V Sewerage Ø600mm pipe laying to FS04

-          TWSRW ¡V Construction of D2-04M pile cap

-          HKY FB (East) ¡V Installation of floor tiles and railing

-          HKY FB (West) ¡V Construction of LT2 pile cap

-          TWRSE ¡V Implementation of TTA376 (BBI TTA stage 3 diversion)

-          TWRSE ¡V Construction of BBI Toilet to Roof Top

-          E4-02 and E4-03M ¡V Construction of pile cap

-          NB109 ¡V Bay 13~20 ELS works

-          NB70 ¡V Bay 1~5 ELS works

-          NB69 ¡V Bay 2~8 Footing

-          NB110 ¡V Bay 6~7 Footing and Wall

-          NB29 U-trough ¡V Bay 10~13 footing construction

(d)         Form Traveler

-          E3-01 ¡V FT dismantling

-          E3-02 ¡V construction 1st pair

-          E2-03 ¡V construction 2st to 4th pair

-          D2-02 ¡V FT dismantling

-          D2-03 ¡V construction 8th pair to 9th pair

ND/2019/06

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 1, 4 and 5

(b)        C&D waste disposal at Portion 1, 2, 4 and 5

(c)        Construction of box culvert at Portion 2

(d)        Filling works at Portion 2 and 4

(e)        Construction of site haul road at Portion 4

(f)         Drainage works, Sewerage works at Portion 2, 3, 4

(g)        Construction of noise barrier at Portion 4 and 5

(h)        Waterworks at Portion 1, 2 and 4