Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (March 2024) |
ND/2019/01 |
(a)
Drainage
works, watermain works and sheet piles in Portion 1a (b)
Site
formation, erection of hoarding and construction of noise barrier in Portion
1c (c)
Sheet
piling, site clearance, site formation, construction of subway, drainage
works and road works in Portion 2 (d)
Watermain
works and site formation in Portion 3 (e)
Site
formation, excavation
and preparation works for pipe jacking in Portion 5 (f)
Backfilling,
drainage works, watermain works and district cooling system in Portion 6a (g)
Operation
of HAC treatment facility in Portion 6b (h)
Excavation
and drainage works in Portion 7 (i)
RC
construction of fresh water reservoir, drainage works, watermain works, backfilling
works and construction of receiving pit in Portion 8a (j)
Trenchless
work and watermain construction in Portion 8b (k)
Sheet
piling, excavation, drainage, watermain works and district cooling system in
Portion 9b (l)
Excavation and drainage works
in Portion 11b (m)
Site clearance, removal of existing structures, site formation and
erection of hoarding in Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry agricultural land creation -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Dry Weather Flow Interception (DWFI) |
ND/2019/04 |
(a)
Pile Cap (b)
Back Filling (c)
Excavation (d)
Grouting (e)
Road works (f)
Formwork and Scaffolding Erection (g)
Rebar Fixing (h)
ELS |
ND/2019/05 |
(a)
South Team -
E3-04b ¡V Pier in progress -
E4-01 ¡V Pier completed & pier head in progress. -
E4-02 ¡V Pipe pile wall completed. Excavation in progress. -
E4-03M ¡V Pipe pile wall in progress. -
D2-04M ¡V Removal of existing abandoned UU completed. ELS in progress. -
Works in TWSRE A. BBI
cover walkway (Steelwork) ¡V 1st stage completed. B. Extension
of HKY Footbridge ¡V Temporarily opened to public. C. BBI
Toilet ¡V Basement Wall is completed. Backfilling and drainage work in
progress. D. Connecting
Road L201 to D300 ¡V Pavement to base coarse is completed. E. D400
Road Works CH285 to 380 ¡V Backfilled to formation. Subbase in progress. F. FW02 ¡V
Footing and wall are completed. Backfilling completed. Pavement work in
progress. -
Works in TWSRW A. FS04
¡VRock slope strengthening works in progress. Slope toe U-Channel in progress. B. Sewerage
work ¡V Laying 600Dia pipes from FW06 toward FS04 is in progress. C. Gas Pipe
laying (IPA400/HP600 ¡V pipe laying in progress. Target completion in June
2024. D. 1st
Stage fresh watermain diversion completed on 2 February 2024 by WSD. E. Lift
LT02 ¡V ELS in progress. -
Noise barrier NB109 A. Bay
9,10, 11 ¡V Top wall completed. B. Bay 12 ¡V
Backfilling in progress C. Bay 13 ¡V
ELS in progress. D. Bay
16-20 ¡V Site clearance and setting temporary lighting in progress. -
Noise barrier NB70 A.
Bay 1-5 ¡V Site clearance and setting temporary lighting in progress. -
Noise barrier NB69 A.
Bay 5c, 6a ¡V Top wall completed. Backfilling in progress. B.
Bay 2, 3, 4 ¡V ELS is in progress. C.
Bay 6c, 7 ¡V Footing completed. Bottom wall in progress. D.
Bay 8 ¡V ELS in progress. -
Noise barrier NB110 A.
Bay 3, 4, 5, 8, 9 ¡V Footing and wall completed. B.
Bay 6,7 ¡V Removal of existing footings completed. Bay 6 footing
completed. Bay 7 footing in progress. C.
Bay 10 Predrilling completed -
Noise barrier NB 29 A.
Bay 12, 13 ¡V Footing (near Fanling Hwy)
completed. B.
Bay 8 to 13 ¡V Sheetpiling in progress (b)
North Team -
Rebar
fixing for 2 nd pour of C1 02 portal beam
construction in progress -
Side
formwork erection for C1 01 MJ portal construction in progress
. -
Falsework
erection for B2 01 cross head construction in progress. -
Falsework
erection for B2 02 & B2 03 cross head construction completed. Formwork
erection in
progress. -
Construction
of remaining abutment wall near B1 02 portal beam was in progress. -
Backfilling
at C3 03ab, C3 04ab, C4 02 & C4 01b were in progress -
Backfilling
and sheet extraction at C2 01 completed. -
On Kui
Street Construction of manhole & associated DN 900 drain pipe were in progress -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were in progress. -
JCR:
Construction of pipe support for DN 150 exposed pipe in progress. -
JCR &
Tong Hang Village J/O improvement works: Construction of box culvert &
extension head wall
was in progress. -
Temporary
haul road in On Lok Garden was in progress. (c)
Bridges and Structures -
Type A segment fabrication completed in Huizhou
casting yard. Type C precast segment commenced at DongGuan
Casting yard. -
Total 5 78 segments were delivered to site, and
total 5 46 segments erected. -
C2 0 2 T span completed. -
Segment erection at C2 01 by LG in progress. -
Rebar fixing at Bridge B1 in progress. -
Trial panel for type C segment is completed. -
Total 210 pcs of parapet skin fabricated; 93
pcs of parapet skin arrived to site , 72 pcs of parapet skin erected on
Bridge E1. -
Construction of D2 01 SOP in progress. -
Installation of drainage system in the deck
void commenced at Bridge D1&E1. -
Dismantle of E&M for the lifting tower
NF38A completed. (d)
Form Traveler -
T Span at D2 02 completed. -
Form traveler launching for 08th pair segment at D2 03 in progress. -
Form traveler launching for 06th pair segment at E2 01 in progress. -
Form traveler rebar fixing for 2nd pair segment at E2 03 in progress. -
FT02 dismantling at E3 01 in progress -
Completed concreting E2 E2 01 E2 02 S05, E2 E2 01 E1 04 01 S05 -
Completed concreting D2 D2 02 D2 03 S11, D2 D2 02 D2 01 S 11 -
Completed concreting D2 D2 03 D2 04 S07, D2 D2 03 D2 02 S07. -
Completed concreting E2 E2 03 E2 02 S01
& E2 E203 E3 01 S01. |
ND/2019/06 |
The
construction phase was completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road
works at Portion 1, 4 and 5 (b)
C&D
waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at Portion 2, 3, 4
and 5 (d)
Construction of box culvert at Portion 2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at Portion 4 (g)
Waterworks at Portion 1, 2 and 4 |