Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site Activities (July to September 2024) |
ND/2019/01 |
(a)
Drainage works,
watermain works, sheet piling, site formation and slope works in Portion 1a (b)
Site
formation, shoving, drainage works and construction of noise barrier in
Portion 1c (c)
Site
formation, construction of subway, road works, drainage works and pipe pile in Portion
2 (d)
Site
formation, excavation, slope work, drainage and watermain works in Portion 3 (e)
Watermain
works, excavation, backfilling, road works and pipe jacking in Portion 5 (f)
Drainage
works, backfilling, road works, watermains works, sheet piling, pipe jacking, construction of retaining wall and slope
works in Portion
6a (g)
Operation
of HAC treatment facility in Portion 6b (h)
Sheet
piling, excavation, stockpile of soil, drainage works, watermain works and road works in Portion
7 (i)
RC
construction of fresh water reservoir, backfilling works, drainage works,
watermain works and ELS construction in Portion 8a (j)
Trenchless
work, excavation, watermain works, ground treatment and ELS construction in Portion
8b (k)
Sheet
piling, pipe pilling, excavation, road works, drainage works and watermain works
in Portion 9b (l)
Site formation, excavation, drainage, watermain and
roadworks in Portion 11b (m)
Stockpile of soil in Portion 13 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet Pile
Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry agricultural land creation -
Construction of Water Treatment Wetland |
ND/2019/04 |
(a)
Pile Cap (b)
Back Filling (c)
Excavation (d)
Grouting (e)
Road works (f)
Formwork and Scaffolding Erection (g)
Rebar Fixing (h)
ELS (i)
Sheet Piling |
ND/2019/05 |
(a)
Backfilling (b)
Drainage works (c)
Bridge fire hydrant
works (d)
Water works (e)
Ducting and Road
works (f)
Slope works (g)
Segments erection (h)
ELS |
ND/2019/06 |
The
construction phase has
been completed
and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2 and 4 (c)
Drainage works, Sewerage works at Portion 1, 2, 3 and 4 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at Portion 4 (f)
Waterworks at Portion 1, 2 and 4 (g)
Construction of noise barrier at Portion 4 and 5 |