Table 10.2       Observations and Recommendations during Site Audits

Parameters

Date

Observations and Recommendations

Follow-up

Contract No.: ND/2019/01

 

Water Quality

25/06/2024

Provide maintenance for the drainage system to avoid unnecessary water accumulation. (Portion 1B)

Improvement/Rectification was observed during follow-up audit session on 2 July 2024.

09/07/2024

Sediment should be cleaned regularly to ensure adequate capacity (Portion 13)

Improvement/Rectification was observed during follow-up audit session on 16 July 2024.

30/07/2024

Enhance bunding to prevent untreated runoff discharge near the discharge point at Portion

RC3.

Follow-up action is needed to be reported in the following month.

Waste/Chemical Management

25/06/2024

Keep site clean and tidy. (Portion 6A)

Improvement/Rectification was observed during follow-up audit session on 2 July 2024.

02/07/2024

Keep site clean and tidy.

Improvement/Rectification was observed during follow-up audit session on 9 July 2024.

09/07/2024

Keep site clean and tidy.(Portion 10A)

Improvement/Rectification was observed during follow-up audit session on 16 July 2024.

Contract No.: ND/2019/02

Water Quality

26/06/2024

Contractors were reminded to immediately establish proper drainage system for muddy runoff at Portion 11.

Item remarked as 240703-O01. Follow-up action is needed to be review.

03/07/2024

Item remarked as 240710-O01. Follow-up action is needed to be review.

10/07/2024

Item remarked as 240717-O01. Follow-up action is needed to be review.

17/07/2024

Item remarked as 240724-O01. Follow-up action is needed to be review.

24/07/2024

Item remarked as 240731-O01. Follow-up action is needed to be review.

31/07/2024

Follow-up action is needed to be reported in the following month.

26/06/2024

Contractors were reminded to immediately establish proper drainage system for pumped groundwater at Portion 7.

Item remarked as 240703-O02. Follow-up action is needed to be review.

03/07/2024

Item remarked as 240710-O02. Follow-up action is needed to be review.

10/07/2024

Item remarked as 240717-O02. Follow-up action is needed to be review.

17/07/2024

Item remarked as 240724-O02. Follow-up action is needed to be review.

24/07/2024

Item remarked as 240731-O02. Follow-up action is needed to be review.

31/07/2024

Follow-up action is needed to be reported in the following month.

26/06/2024

Sandbag bund should be enhanced to avoid muddy runoff discharge. (Portion 4)

Item remarked as 240703-R02. Follow-up action is needed to be review.

03/07/2024

Improvement/Rectification was observed during follow-up audit session on 10 July 2024.

03/07/2024

Provide complete drainage system to avoid untreated water accumulation. (VC)

Item remarked as 240710-R04. Follow-up action is needed to be review.

10/07/2024

Item remarked as 240717-R04. Follow-up action is needed to be review.

17/07/2024

Item remarked as 240724-R04. Follow-up action is needed to be review.

24/07/2024

Item remarked as 240731-R04. Follow-up action is needed to be review.

31/07/2024

Follow-up action is needed to be reported in the following month.

10/07/2024

Provide complete drainage system to treat wastewater. (Shek Wu Hui Treatment Plant works area)

Item remarked as 240717-R05. Follow-up action is needed to be review.

17/07/2024

Item remarked as 240724-R05. Follow-up action is needed to be review.

24/07/2024

Item remarked as 240731-R05. Follow-up action is needed to be review.

31/07/2024

Follow-up action is needed to be reported in the following month.

10/07/2024

Provide water mitigation measures to the manholes to avoid untreated wastewater discharge from wheel washing facility. (Dill’s Corner)

Item remarked as 240717-R06. Follow-up action is needed to be review.

17/07/2024

Improvement/Rectification was observed during follow-up audit session on 24 July 2024.

26/06/2024

Provide wheel washing facilities for the vehicles exit at Portion 11.

Item remarked as 240703-R03. Follow-up action is needed to be review.

03/07/2024

Item remarked as 240710-R02. Follow-up action is needed to be review.

10/07/2024

Item remarked as 240717-R02. Follow-up action is needed to be review.

17/07/2024

Item remarked as 240724-R02. Follow-up action is needed to be review.

24/07/2024

Item remarked as 240731-R02. Follow-up action is needed to be review.

31/07/2024

Follow-up action is needed to be reported in the following month.

26/06/2024

Review the capacity of the wastewater treatment facilities at Portion 5.

Item remarked as 240703-R04. Follow-up action is needed to be review.

03/07/2024

Item remarked as 240710-R03. Follow-up action is needed to be review.

10/07/2024

Item remarked as 240717-R03. Follow-up action is needed to be review.

17/07/2024

Item remarked as 240724-R03. Follow-up action is needed to be review.

24/07/2024

Item remarked as 240731-R03. Follow-up action is needed to be review.

31/07/2024

Follow-up action is needed to be reported in the following month.

17/07/2024

Enhance the earth bund to prevent muddy runoff.

Item remarked as 240724-R07. Follow-up action is needed to be review.

24/07/2024

Item remarked as 240731-R07. Follow-up action is needed to be review.

31/07/2024

Follow-up action is needed to be reported in the following month.

17/07/2024

Connect the water treatment facility to the drainage system.

Item remarked as 240724-R08. Follow-up action is needed to be review.

24/07/2024

Item remarked as 240731-R08. Follow-up action is needed to be review.

31/07/2024

Follow-up action is needed to be reported in the following month.

24/07/2024

Enhance water mitigation measures to avoid surface runoff out of site boundary. (Portion 6)

Item remarked as 240731-R06. Follow-up action is needed to be review.

31/07/2024

Follow-up action is needed to be reported in the following month.

Air Quality

24/07/2024

Keep site entrance free from dusty debris. (Shek Sheung River)

Item remarked as 240731-R09. Follow-up action is needed to be review.

31/07/2024

Follow-up action is needed to be reported in the following month.

Waste/Chemical Management

03/07/2024

Provide drip tray for chemical/fuel containers. (VC)

Improvement/Rectification was observed during follow-up audit session on 10 July 2024.

Ecology

26/06/2024

Dull green hoarding should be erected along the site boundary as according to the submitted location plan.

Item remarked as 240703-R01. Follow-up action is needed to be review.

03/07/2024

Item remarked as 240710-R01. Follow-up action is needed to be review.

10/07/2024

Item remarked as 240717-R01. Follow-up action is needed to be review.

17/07/2024

Item remarked as 240724-R01. Follow-up action is needed to be review.

24/07/2024

Item remarked as 240731-R01. Follow-up action is needed to be review.

31/07/2024

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/03

--

--

--

--

Contract No.: ND/2019/04

Air Quality

27/06/2024

Provide impervious sheeting for the dusty stockpile.

Improvement/Rectification was observed during follow-up audit session on 4 July 2024.

25/07/2024

Haul road should be water-sprayed regularly as dust suppression.

Follow-up action is needed to be reported in the following month.

Ecology

04/07/2024

The 2m high green barrier of the 10m vegetated buffer zone should be maintained properly and regularly.

Improvement/Rectification was observed during follow-up audit session on 11 July 2024.

Water Quality

04/07/2024

Enhance the water mitigation measure to avoid surface runoff. (A301)

Improvement/Rectification was observed during follow-up audit session on 11 July 2024.

Waste / Chemical Management

27/06/2024

Keep site clean and tidy.

Improvement/Rectification was observed during follow-up audit session on 4 July 2024.

Permit/Licences

25/07/2024

EP should be displayed properly at A3-01.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/05

Air Quality

02/07/2024

Dusty stockpile at C3-02 should be covered by tarpaulin properly to prevent dust generation.

Item remarked as 240708-F02. Follow-up action is needed to be review.

08/07/2024

Improvement/Rectification was observed during follow-up audit session on 18 July 2024.

Water Quality

02/07/2024

Water mitigation measures near C3-01 should be enhanced to avoid surface runoff overflow. Sand bag barrier should be supplemented also.

Item remarked as 240708-F01. Follow-up action is needed to be review.

08/07/2024

Improvement/Rectification was observed during follow-up audit session on 18 July 2024.

29/07/2024

Water mitigation measures at Kwu Tung storage area should be enhanced. Muddy surface runoff overflow was observed after heavy rainfall.

Follow-up action is needed to be reported in the following month.

Contract No.: ND/2019/06

--

--

--

--

Contract No.: ND/2019/07

 

--

--

--

--