2.1
The Kwu Tung North
(KTN) and Fanling North (FLN) New Development Areas
(NDAs) are one of the important sources of land and housing supply in the
medium and long term. The development of the KTN and FLN NDAs will be
implemented in phase for full completion by 2031. The Phase 1 of the NDAs development,
comprising the Advance Works and First Stage Works, is targeted to be
implemented from the second half of 2019 progressively. The Advance and First
Stage Works would include site formation, engineering infrastructure works
(including roads, drainage, sewerage, waterworks, landscaping works, pumping
stations, and fresh water and flushing water service reservoirs), soil
remediation, reprovisioning of North District Temporary Wholesale Market,
development of a nature park at Long Valley and implementation of environmental
mitigation measures.
2.2
The scope of works under the Advance and First
Stage Works comprises the following:
a)
The Advance Works (PWP item No. 7747CL-2)
consist of:
i)
site formation of land (including soil
remediation) in KTN and FLN NDAs for housing, community facilities and
engineering infrastructure;
ii) construction of roads including the eastern section of Fanling Bypass (FLBP(E)) connecting the FLN NDA to Fanling Highway and other roads with footpaths and cycle
tracks, and associated junction/ road improvements;
iii) engineering infrastructure works including drainage. Sewerage (including
two sewage pumping stations), waterworks (including a
fresh water service reservoir and a flushing water service reservoir in the KTN
NDA), landscape works and slopeworks;
iv) part expansion and upgrading of Shek Wu Hui Sewage Treatment Works
(SWHSTW);
v)
reprovisioning works; and
vi) implementation of environmental mitigation measures and environmental
monitoring and audit (EM&A) programme for the
works mentioned in (i) to (v) above.
b)
The First Stage Works (PWP item No. 7759CL)
consist of:
i)
development of a nature park at Long Valley
including provision of a visitor centre and a
footbridge spanning across Sheung Yue River for connection between these two
facilities;
ii) reprovisioning of two egretry sites in the FLN
NDA and enhancement works to an existing egretry site
in the KTN NDA;
iii) site formation of land for a village resite area and a district police station in the KTN
NDA;
iv) engineering infrastructure works including roads, drainage, sewerage,
waterbirds, and landscape works; and
v)
implementation of environmental mitigation
measures and environmental monitoring and audit (EM&A) programme
for the works mentioned in (i) to (iv) above.
2.3
The Project which covers KTN and FLN NDAs is a
designated project (DP) under Schedule 3 of the Environmental Impact Assessment
(EIA) Ordinance (Cap. 499). In October 2013, the EIA Report (AEIAR-175/2013)
for the Project was approved by the Director of Environmental Protection
pursuant to the EIA Ordinance. The relevant EPs under the Project and the
respective Work Contracts are summarised in Tables 2.1a and 2.1.b.
Table 2.1a Summary of
EPs under the Project and the Respective Work Contracts
EP No. |
Designated Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle
Peak Road Diversion |
ü |
¡@ |
|||||||
Kwu Tung North New Development
Area Road P1 and P2 and Associated New Kwu Tung
Interchange and Pak Shek Au Interchange Improvement |
ü |
¡@ |
|||||||
Kwu Tung North New Development
Area Road D1 to D5 |
ü |
ü |
¡@ |
||||||
Sewage
Pumping Stations in Kwu Tung North New Development
Area |
ü |
¡@ |
|||||||
Utilization
of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
|||||||
Fanling Bypass Eastern Section |
ü |
ü |
ü |
¡@ |
|||||
Reprovision
of temporary Wholesale Market in Fanling North New
Development Area |
ü |
¡@ |
|||||||
EP-546/2017 |
Fanling North Temporary Sewage
Pumping Station |
ü |
¡@ |
Notes:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope of Works under concerned EP
Environmental
Permit (EP) No. |
Work
Contract(s) |
Scope
of Works under concerned EP(s) |
Site
Layout Plan under concerned EP(s) |
EP-466/2013/A(Part) |
C1 |
Realign
Castle Peak Road and join with the Pak Shek Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction
of new primary distributor road (P1) within Kwu
Tung North New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction
of new primary distributor roads (D1, D3, D4 and part of D5) within Kwu Tung North New Development Area |
Figure 14 |
C3 |
Development
of a nature park at Long Valley and ecological mitigation and enhancement
works for the nature park (Condition 2.9) |
Figure 15 |
|
EP-469/2013(Part) |
C2 |
Construction
of one sewage pumping station in Kwu Tung North
with installed capacity of more than 2,000 m3 per day |
Figure 16 |
EP-470/2013/A(Part) |
C1 |
Construction
of service reservoir and watermain for the reuse of treated sewage effluent
for reuse in Kwu Tung North Development Areas |
Figure 17 |
EP-473/2013/A(Part) |
C3 |
Establishment of alternative egretry
sites and enhance the existing egretry site at Ho Sheung Heung and/or its vicinity
(Condition 2.7) |
Figure 18 |
EP-473/2013/A(Part) |
C5A |
Construction
of new district distributor inside FLN NDA, which provides a linkage between
the Man Kam To Road and the proposed Fanling Bypass Eastern Section |
Figure 19 |
EP-473/2013/A(Part) |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The
re-provisioned wholesale market will have approximately 1,000 market stalls
within a site area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct
and operate a temporary sewage pumping station in Fanling
North with installed capacity (average dry weather flow) of about 3,600m3/day |
Figure 22 |
Remark: The EP(s) not related to the Project of the First Phase of the Kwu Tung North (KTN) and Fanling
North (FLN) New Development Area (NDA) Development Areas are not included in
the Table.
2.4
The site boundary of the Project and all Works
Contracts are shown in Drawing No. 1.
2.5
The required submissions and submission status
under Environmental Permits are shown in Appendix
U.
2.6
The site layout plans under
concerned Environmental Permits are shown in Figures 12 - 22.
2.7
Different parties with different levels of
involvement in the Project organisation include:
Project Proponent ¡V Civil Engineering and Development Department (CEDD)
Supervisor
/ Supervisor's Representative ¡V AECOM
Asia Co. Ltd.
Environmental Team (ET) ¡V Wellab Limited
Independent Environmental Checker (IEC) ¡V Mott
MacDonald Hong Kong Ltd (MottMac)
2.8
The names and contact numbers of key
personnel are summarised in Table 2.2.
Table 2.2 Key Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax
No. |
Civil Engineering and
Development Department, HKSAR (CEDD) |
Project Proponent |
Mr. Ryan Chau |
3797 5387 |
3547 1658 |
Supervisor
/ Supervisor's Representative (AECOM Asia Co. Ltd.) |
Chief Resident Engineer |
Mr. Alan Lee |
6398 5982 |
2680 9515 |
Senior Resident Engineer |
Mr. King-man
Chan |
9651 2635 |
2680 9515 |
|
Environmental Team (Wellab Limited) |
Environmental Team Leader |
Dr. Priscilla Choy |
2898 7388 |
2898 7076 |
Independent Environmental
Checker (MottMac) |
Independent Environmental
Checker |
Mr. Thomas Chan |
2828 5967 |
2827 1823 |
Contract
No. ND/2019/01 Contractor (Build King ¡V Richwell Engineering Joint Venture) |
Site Agent |
Mr. Ivan Leung |
9640
8340 |
-- |
Environmental Officer |
Mr. Edward Tam |
9287
8270 |
||
Contract
No. ND/2019/02 Contractor (Chun Wo ¡V Kwan
Lee Joint Venture.) |
Site Agent |
Mr. Andy Chan |
3485
9780 |
-- |
Environmental Officer |
TBC |
-- |
||
Contract
No. ND/2019/03 Contractor (Sang Hing Kuly Joint Venture) |
Site Agent |
Mr. Tang Wing Kai |
9300
7037 |
-- |
Environmental Officer |
Mr. Ken Cheung |
9803 5297 |
||
Contract
No. ND/2019/04 Contractor (Daewoo ¡V Chun
Wo ¡V Kwan Lee Joint Venture) |
Site Agent |
Mr. Eric Wu |
9786 8630 |
-- |
Environmental Officer |
Mr. Sam Lam |
6178 3179 |
||
Contract
No. ND/2019/05 Contractor (CRCC ¡V Paul Y.
Joint Venture) |
Site Agent |
Mr. Darvin Lo |
9467 5891 |
-- |
Environmental Manager |
Mr. Pan Fong |
9436 9435 |
||
Environmental Officer |
Mr. Kevin Cheung |
6117 1344 |
||
Contract
No. ND/2019/06 Contractor (New Concepts
Engineering Development Ltd.) |
Project Manager |
Mr. Joe
Cheng |
9861
0060 |
-- |
Environmental Officer |
Mr. Alex Choy |
6360 3236 |
||
Contract
No. ND/2019/07 Contractor (China Road and
Bridge Corporation) |
Site Agent |
Mr. Mac Chow |
9169 9567 |
-- |
Environmental Officer |
Mr. K. M. Lui |
5113 8223 |
||
Environmental Supervisor |
Mr. Attlee Chau |
6386 9018 |
Summary of Construction Works Undertaken During
Reporting Month
2.9
The major site activities undertaken in the
reporting month are shown in Table 2.3.
Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract No. |
Site Activities (January 2024) |
ND/2019/01 |
(a)
Drainage
works, watermain works and sheet piles in Portion 1a (b)
Site
formation and erection of hoarding in Portion 1c (c)
Sheet
piling, site clearance, site formation, construction of subway, drainage
works and road works in Portion 2 (d)
Drainage
works in Portion 3 (e)
Site
formation and excavation in Portion 5 (f)
Backfilling,
drainage and watermain works in Portion 6a (g)
Operation
of HAC treatment facility in Portion 6b (h)
Excavation
and drainage works in Portion 7 (i)
RC
construction of fresh water reservoir, drainage works, backfilling works and construction
of receiving pit in Portion 8a (j)
Trenchless
work and watermain construction in Portion 8b (k)
Sheet
piling, excavation, drainage and watermain works in Portion 9b (l)
Removal of existing
structure in Portion 11b (m)
Site
clearance, removal of existing structures, site formation and erection of
hoarding in Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
Portion 2 to Portion 20C -
Wetland
creation & restoration, Dry agricultural land creation -
Construction
of compacted earth path -
Construction
of Water Treatment Wetland -
Tree
felling and tree pruning work -
Construction
of Lodging Facility -
Construction
of Dry Weather Flow Interception (DWFI) -
Construction of Car Park
and Farmer¡¦s Forum |
ND/2019/04 |
(a)
Tree Pruning (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork and Scaffolding Erection (i)
Rebar Fixing (j)
Bore pile (k)
ELS |
ND/2019/05 |
(a)
South
Team -
E3-05M ¡V
Pier head construction in progress. -
E3-04a ¡V
Column construction in progress. -
E3-04b ¡V
ELS in progress. Unforeseen obstruction encountered and removed. -
E4-01 ¡V
ELS in progress. -
E4-02 ¡V
ELS pipe pile wall in progress. Unforeseen obstruction encountered. -
D2-04M ¡V
Bored Piling completed on 22 Nov 2023. -
FS04 ¡V
Raking drain completed. Middle berm and U-channel construction in progress. -
Works in
TWSRE A.
BBI cover
walkway (Steelwork) ¡V 1st stage was completed. B.
HKY
Footbridge/Staircase ¡V Temporarily opened to public. C.
BBI
Toilet ¡V Base slab was casted. Wall construction is in progress. D.
Connecting
Road L201 to D300 ¡V Drainage and Kerb construction
are in progress. -
Works in
TWSRW A.
TWRSW
Stage 2 TTA completed on 22 Nov 2023. B.
FS04 ¡V raking drain
completed. Middle berm and U-channel construction in progress. C.
11kv
cable laying (near HKY entrance) in progress. D.
Drainage
work ¡V Laying 2x1200Dia Pipes to Manhole (FL9110) in progress. E.
Sewerage
work ¡V Laying 600Dia pipes at FW06 is in progress. F.
Gas Pipe
laying (IPA400/HP600 ¡V near HKY entrance) in progress. G.
Fresh
watermain diversion in progress. Connection works to be carried out by WSD in
Late Jan 2024. H.
Lift LT02
¡V Piling works completed. Proof drilling completed. Loading tests are in
progress. -
NB109 A.
Bay 5, 6, 7, 8 ¡V Top wall
in progress B.
Bay 9, 10, 11, 12 ¡V Bottom
wall completed. Backfilling in progress. C.
Bay 13
Site Clearance completed. ELS in progress. -
NB69 A.
Bay 5,
Bay 6 ¡V Top Wall in progress. B.
Bay 2,
Bay 3 ¡V ELS is in progress. Unforeseen obstruction encountered and removed. C.
Bay 6,
Bay 7, Bay 8 ¡V ELS is in progress. Uncharted 150 dia. Watermain encountered. -
NB110 A.
Bay 3 to
5 - Backfilling reached formation. Temporary FVMS is installed for removal of
Sign Gantry DS64. B.
Bay 8 -
Wall was completed on 10 Nov 2023. C.
Bay 9 ¡V Footing
completed. Wall in progress. -
NB 29 A.
Trial Panel
for wall is completed. B.
2 nos
Plate Load Test were carried out and completed. C.
Bay 10, 11 ¡V Footing is in
progress. (b)
North
Team -
C2-01 crosshead
completed. -
Side
formwork for C1-02 portal beam construction completed. -
Truss
erection for C1-01 MJ portal construction in completed. -
Falsework
erection for B2-01, B2-02 & B2-03 cross head construction in progress. -
Sheet
pile extraction of B1-Abutment wall-phase 2 completed. -
Construction
of remaining abutment wall near B1-02 portal beam was in progress. -
Backfilling
& extraction of sheet pile at C2-02 completed. -
Backfilling
at C4-02, C4-01a & C4-01b were in progress -
Permanent
reinstatement of footpath near C4-01a was in progress. -
JCR:
Construction of new central median was in progress. -
JCR:
Construction of pipe support for DN 150 exposed pipe & trench excavation
for WSD were in progress. -
JCR &
Tong Hang Village J/O improvement works: Construction of box-culvert &
extension head wall was in progress. -
On Kui
Street Construction of manhole & associated DN 900 drain pipe were in progress (c)
Bridges
and Structures -
Total 782 segments were
casted in Huizhou casting yard. -
Total 524 segments were
delivered to site, and total 492 segments erected. -
C2 03 to C2 04 end span
segment erection by LG in progress. -
Fabrication of steel
support for Bridge B1 completed at Zhengzhou. -
Erection of Bridge B1
steel platform in progress. -
The fabrication of 2 sets
of steel molds for Bridge B2 precast segment in progress. -
Fabrication of parapet
skin commenced at ShenZhen casting yard, total 120
pieces parapet skin fabricated. -
Construction of D2 01 SOP
in progress. (d)
Form Traveler -
Form
traveler rebar fixing for 06th pair segment at E3 01 in progress. -
Form
traveler rebar fixing for 09th pair segment at D2 02 in progress. -
Form
traveler rebar fixing for 05th pair segment at D2 03 in progress. -
Form
traveler rebar fixing for 03rd pair segment at E2 02 in progress. -
FT01
dismantling at E2 01 completed. -
Completed
concreting E2 E2 01 E2 02 S01, E2 E2 01 E1 04 01 S01. E2 E2 01 E2
02 S02, E2 E2 01 E1 04 01 S02. -
Completed
concreting D2 D2 02 D2 03 S07, D2 D2 02 D2 01 S07, D2 D2 02 D2 03
S08, D2 D2 02 D2 01 S08. -
Completed
concreting D2 D2 03 D2 04 S03, D2 D2 03 D2 02 S03, D2 D2 03 D2 04
S04, D2 D2 03 D2 02 S04. -
Completed
concreting E3 E3 01 E2 03 S04 & E3 E3 01 E3 02 S04, E3 E3 01 E2 03
S05 & E3 E3 01 E3 02 S05. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at Portion 2, 3, 4
and 5 (d)
Construction of box culvert at Portion 2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at Portion 4 (g)
Waterworks at Portion 1, 2 and 4 |
Construction Programme
2.10
Copies of Contractors¡¦ construction programmes
are provided
in Appendix A.
Status of Environmental Licences, Notifications and Permits
2.11 A summary of the relevant permits, licences,
and/or notifications on environmental protection for this Project is presented
in Table 2.4.
Table 2.4 Status of Environmental
Licences,
Notifications and Permits
Contract No. |
Permit / Licence No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental Permit (EP) |
||||
ND/2019/01 |
EP-466/2013/A |
21/11/2013 |
N/A |
Valid |
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-470/2013/A |
21/11/2013 |
N/A |
Valid |
|
ND/2019/02 |
EP-469/2013 |
21/11/2013 |
N/A |
Valid |
ND/2019/03 |
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
|
ND/2019/04 |
EP/473/2013/A |
27/01/2017 |
N/A |
Valid |
EP/546/2017 |
16/11/2017 |
N/A |
Valid |
|
ND/2019/05 |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
ND/2019/06 |
EP-475/2013/A |
13/01/2017 |
N/A |
Valid |
Construction Noise Permit (CNP) |
||||
ND/2019/01 |
GW-RN1057-23 |
13/10/2023 |
12/01/2024 |
Expired
in reporting month |
GW-RN0840-23 |
01/09/2023 |
29/02/2024 |
Valid |
|
GW-RN0877-23 |
01/09/2023 |
29/02/2024 |
Valid |
|
GW-RN0997-23 |
01/10/2023 |
31/03/2024 |
Valid |
|
GW-RN1224-23 |
21/11/2023 |
20/02/2024 |
Valid |
|
GW-RN1146-23 |
19/11/2023 |
18/05/2024 |
Valid |
|
GW-RN1329-23 |
20/12/2023 |
28/02/2024 |
Valid |
|
GW-RN1330-23 |
20/12/2023 |
19/03/2024 |
Valid |
|
GW-RN1235-23 |
01/12/2023 |
29/02/2024 |
Valid |
|
GW-RN1328-23 |
25/12/2023 |
24/03/2024 |
Valid |
|
GW-RN0053-24 |
21/01/2024 |
20/04/2024 |
Valid |
|
GW-RN0073-24 |
29/01/2024 |
28/04/2024 |
Valid |
|
ND/2019/02 |
GW-RN1178-23 |
10/11/2023 |
09/02/2024 |
Valid |
GW-RN1163-23 |
08/11/2023 |
07/04/2024 |
Valid |
|
GW-RN1400-23 |
01/01/2024 |
31/03/2024 |
Valid |
|
ND/2019/03 |
GW-RN0733-23 |
01/09/2023 |
29/02/2024 |
Valid |
ND/2019/04 |
GW-RN1039-23 |
08/10/2023 |
07/01/2024 |
Expired
in reporting month |
GW-RN1408-23 |
29/12/2023 |
28/03/2024 |
Valid |
|
GW-RN0020-24 |
08/01/2024 |
07/04/2024 |
Valid |
|
GW-RN0051-24 |
26/01/2024 |
25/03/2024 |
Valid |
|
ND/2019/05 |
GW-RN1138-23 |
09/11/2023 |
31/01/2024 |
Expired
in reporting month |
GW-RN0897-23 |
01/09/2023 |
29/02/2024 |
Valid |
|
GW-RN1248-23 |
01/12/2023 |
29/02/2024 |
Valid |
|
GW-RN1334-23 |
13/12/2023 |
29/02/2024 |
Valid |
|
GW-RN1366-23 |
01/01/2024 |
31/03/2024 |
Valid |
|
GW-RN1368-23 |
27/12/2023 |
31/01/2024 |
Expired
in reporting month |
|
GW-RN1367-23 |
29/12/2023 |
28/02/2024 |
Valid |
|
GW-RN1369-23 |
27/12/2023 |
26/03/2024 |
Valid |
|
GW-RN1414-23 |
01/01/2024 |
31/01/2024 |
Expired
in reporting month |
|
GW-RN1415-23 |
01/01/2024 |
31/03/2024 |
Valid |
|
Notification pursuant to Air Pollution Control (Construction
Dust) Regulation |
||||
ND/2019/01 |
451792 |
11/12/2019 |
N/A |
Valid |
477388 |
02/03/2022 |
N/A |
Valid |
|
ND/2019/02 |
454012 |
05/03/2020 |
N/A |
Valid |
ND/2019/03 |
452216 |
24/12/2019 |
N/A |
Valid |
452332 |
31/12/2019 |
N/A |
Valid |
|
452333 |
31/12/2019 |
N/A |
Valid |
|
ND/2019/04 |
461184 |
23/10/2020 |
N/A |
Valid |
ND/2019/05 |
454323 |
13/03/2020 |
N/A |
Valid |
ND/2019/06 |
449369 |
24/09/2019 |
N/A |
Valid |
ND/2019/07 |
459393 |
28/08/2020 |
N/A |
Valid |
Billing Account for Disposal of Construction
Waste |
||||
ND/2019/01 |
7036265 |
17/01/2020 |
N/A |
Valid |
ND/2019/02 |
7036898 |
01/04/2020 |
N/A |
Valid |
ND/2019/03 |
7036378 |
22/01/2020 |
N/A |
Valid |
ND/2019/04 |
7038391 |
22/09/2020 |
N/A |
Valid |
ND/2019/05 |
7036901 |
01/04/2020 |
N/A |
Valid |
ND/2019/06 |
7035473 |
17/10/2019 |
N/A |
Valid |
ND/2019/07 |
7038309 |
14/09/2020 |
N/A |
Valid |
Registration of Chemical
Waste Producer |
||||
ND/2019/01 |
5213-545-B2578-01 |
10/01/2020 |
N/A |
Valid |
ND/2019/02 |
5213-548-C4439-01 |
06/05/2020 |
N/A |
Valid |
ND/2019/03 |
5213-623-S4231-01 |
14/04/2020 |
N/A |
Valid |
ND/2019/04 |
5211-624-D2709-01 |
26/11/2020 |
N/A |
Valid |
ND/2019/05 |
5213-625-C4464-01 |
20/05/2020 |
N/A |
Valid |
ND/2019/06 |
5213-625-N2716-01 |
02/10/2019 |
N/A |
Valid |
ND/2019/07 |
5213-625-C4498-01 |
21/09/2020 |
N/A |
Valid |
Effluent Discharge License
under Water Pollution Control Ordinance |
||||
ND/2019/01 |
WT00036071-2020 |
22/06/2020 |
30/06/2025 |
Valid |
WT00036073-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036067-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036075-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036076-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00037191-2020 |
21/04/2022 |
28/02/2026 |
Valid |
|
WT00037204-2020 |
16/11/2022 |
28/02/2026 |
Valid |
|
WT00037412-2021 |
16/11/2022 |
30/04/2026 |
Valid |
|
WT00037564-2021 |
19/04/2021 |
30/04/2026 |
Valid |
|
WT00037886-2021 |
28/06/2021 |
30/06/2026 |
Valid |
|
WT00041311-2022 |
21/06/2022 |
30/06/2027 |
Valid |
|
ND/2019/02 |
WT00036584-2020 |
21/10/2020 |
31/10/2025 |
Valid |
WT00036952-2020 |
17/12/2020 |
31/12/2025 |
Valid |
|
ND/2019/03 |
WT00035847-2020 |
12/08/2020 |
31/08/2025 |
Valid |
WT00036414-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
WT00037771-2021 |
08/07/2021 |
31/07/2026 |
Valid |
|
WT00035984-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
ND/2019/04 |
WT00037539-2021 |
02/06/2022 |
30/04/2026 |
Valid |
ND/2019/05 |
WT00036996-2020 |
22/12/2020 |
31/12/2025 |
Valid |
ND/2019/06 |
WT00035415-2019 |
20/03/2020 |
31/03/2025 |
Valid |
ND/2019/07 |
WT00037526-2021 |
21/04/2022 |
31/05/2026 |
Valid |