Key
Issues in the Coming Three Months
12.1
The major site activities, potential environmental impacts and recommended
mitigation measures for
the coming three months are shown in Table 12.1.
Table 12.1 Summary Table for Site
Activities, Potential Environmental Impacts and Recommended Mitigation Measures
in the Coming Months
Contract No. |
Major
Site Activities |
Location/
Working Period |
Potential
Environmental Impact |
Recommended
Mitigation Measures |
ND/2019/01 |
(a)
Site clearance / tree
felling |
Portion 2, 13 |
- Construction Dust impact - Noise Impact
(Construction Phase) - Water Quality Impact
(Construction Phase) - Waste Management
(Construction Waste) |
Air -
Watering on exposed earth
and haul road. -
Cover the stockpiles or
dusty materials. -
Deploy water bowsers to
water the haul road. -
Deploy mist-cannon on site -
Provide shelter with top
and 3-sides for cement production activities. -
Cover the
Arsenic-containing soil. -
Store the bulk cement in
enclosed silo tank for soil treatment. -
Close the mechanical cover
of the vehicles used for transporting dusty materials. -
Establish vehicle wheel
washing facilities at vehicle exit points. -
Speed control of site
vehicles. Noise -
Regular inspect of
construction plants in good condition. -
Provide temporary noise
screens if necessary. -
Use of Quiet plants (QPME)
and working methods if possible. -
Sequencing operation of
construction plants where practicable. -
Shut down the machines and
plant if not in use. -
Only well-maintained plant
to be operated on-site -
Mobile plant to be sited
as far away from NSRs as possible practicable. -
Conduct noise monitoring
regularly. -
Erect silent-up noise
barrier at portion 6b. Water -
Set up wastewater
treatment system (AquaSed) on site -
Erect soil bund /
temporary drain to divert /collect surface runoff. -
Maintain the drainage and
wastewater treatment facilities. Waste / Chemical
Management -
Sort out demolition debris
and excavated materials from demolition works to recover reusable /
recyclable portions -
Provide recycling bins on
site, encourage reuse and recycle as much as
possible. -
Provide drip trays for
chemical containers. -
Chemical spill kit
available on site. -
Chemical waste cabinet
available on site. -
Chemical wastes to be
stored in appropriate containers and collected by a licensed chemical waste
collector. -
Delivery of yard waste to
tree shredding facility for upcycling. |
(b)
GI works |
NIL |
|||
(c)
Excavation / Backfilling |
Portion 5, 6a, 7, 8a, 9b |
|||
(d)
Construction of receiving
pit |
Portion 8a |
|||
(e)
Construction of noise
barrier |
NIL |
|||
(f)
Site Formation |
Portion 1c, 2, 5, 13 |
|||
(g)
Removal of existing
structure |
Portion 11b, 13 |
|||
(h)
Construction of subway |
Portion 2 |
|||
(i)
Operation of HAC treatment
facility |
Portion 6b |
|||
(j)
Drainage works /
watermains works |
Portion 1a, 2, 3, 6a, 7, 8a, 8b, 9b |
|||
(k)
Road Construction |
Portion 2 |
|||
(l)
Trenchless |
Portion 8b |
|||
(m)
Construction of reservoir |
Portions 8a |
|||
(n)
Ground Treatment |
NIL |
|||
(o)
Erection of hoarding |
Portion 1c, 13 |
|||
(p)
Sheet piling / ELS &
pipe pile |
Portion 1a, 2, 9b |
|||
ND/2019/02 |
(a)
Pipe Jacking |
Portions
1, 5 |
Air, Noise, Waste |
-
Dusty works should be spray
water. Idle stockpile or slop should be covered by Tarpaulin sheet properly. -
Wheel washing should be carried out at every exit. -
Plants should be well maintained to prevent dark
smoke and oil leakage. Idle plant should be turned off. -
Drip tray should be provided for all chemical and
stationary plants. -
No construction works shall be carried out in
restricted hours (7:00 pm to 7:00 am) unless CNP is obtained. -
Erect noise screen along site boundary. -
Waste should be sorted and dispose according to
the Waste Management Plan -
No direct discharge of wastewater into storm
drains is allowed. Wastewater must be de-silted before discharged in
accordance with the water discharge license. -
Dull green barrier and ecological measures should
be implemented according to the Ecological protection plan. |
(b)
Backfilling |
Portion
4, 7, 8 |
Air, Noise, Waste |
||
(c)
Concreting |
Portions
7, 8, 9 & 10 |
Air, Noise, Water, Waste, Ecology |
||
(d)
Bedding & Pipe Laying |
Portion
3, 4 |
Air, Noise, Water, Waste, Ecology |
||
(e)
ELS |
Portions
1, 4, 5 |
Air, Noise, Water, Waste, Ecology |
||
(f)
Sheet Pile Removal |
NIL |
Air, Noise, Water, Waste |
||
(g)
Cut and Fill of Slope |
Portion
3, 4 |
Air, Noise, Water, Waste |
||
(h)
Sheet pile installation |
Portion
1, 4 |
|||
ND/2019/03 |
(a)
Excavation & ELS |
Portion
1, 1A, 2, 3, 4, 4A, 4B, 5, 5A |
-
Waste -
Air pollution -
Noise pollution |
-
Dusty works should be
sprayed with water or stockpile should be covered by Tarpaulin properly. -
Plants should have
maintenance to prevent dark smoke and oil leakage. Idle plant should be
turned off. -
Drip tray should be
provided for all chemical and stationary plants. -
No construction works
shall be carried out in restricted hours (7:00 pm to 7:00 am) unless CNP is
granted. -
Waste should be sorted and
disposed according to Waste Management Plan. -
No direct discharge of
wastewater into storm water drains is allowed. Wastewater must be desilted
before discharging according to water discharge license. |
(b)
Site Clearance |
Sections
7, 8 and 9 |
-
Waste -
Air pollution -
Noise pollution |
||
(c)
Tree Felling |
Sections
6, 7, 8 and 9 |
-
Waste -
Air pollution -
Noise pollution |
||
ND/2019/04 |
(a)
Sheet piling |
A2-03, Portion J, K and Footbridge F4 |
-
Air, Noise, Waste |
-
Dusty works should be
sprayed with water or stockpile should be covered by tarpaulin properly. -
Plants should have
maintenance to prevent dark smoke and oil leakage. Idle plant should be
turned off. -
Drip tray should be
provided for all chemical and stationary plants. -
No construction works
shall be carried out in restricted hours (7:00 pm to 7:00 am) unless CNP is
granted. -
Waste should be sorted and
disposed according to Waste Management Plan. -
No direct discharge of
wastewater into storm water drains is allowed. Wastewater must be desilted
before discharging according to water discharge license. |
(b)
Pile cap |
Bridge A1, A3 and Portion J, K |
-
Air, Noise, Water, Waste |
||
(c)
Grouting |
Bridge F, A2, A3 and Portion J, K, H |
-
Air, Noise, Water, Waste |
||
(d)
Bore pile |
Bridge G and Footbridge F4 |
-
Air, Noise, Water, Waste |
||
(e)
Excavation & ELS |
Portion J, H, K, X, S, Bridge A1, A2 and A3 |
-
Air, Noise, Waste |
||
(f)
Road works |
Portion J, H, O, U and VY |
-
Air, Noise, Waste |
||
(g)
Pre-drilling |
NIL |
-
Air, Noise, Water, Waste |
||
(h)
Tree pruning |
Portion K |
-
Air, Noise, Waste |
||
(i)
UU diversion |
Portion J and K |
-
Air, Noise, Waste |
||
ND/2019/05 |
(a)
ELS & Pile Cap
Construction |
NB69 Bay 2~8 NB110 Bay 6~7 |
-
Construction Dust Impact -
Noise Impact -
Water Quality Impact
(Construction Phase) -
Waste Management (Construction Waste) -
Landscape and Visual -
Cultural Heritage |
Regular
watering on exposed worksites and haul road. -
Stockpiling area should be
provided with covers and water spraying system. -
Only well
maintained plant to be operated on site. -
plant known to emit noise
strongly in one direction, where possible, be orientated so that the noise is
directed away from nearby NSRs. -
mobile plant to be sited
as far away from NSRs as possible practicable. -
All open stockpiles of
construction materials of more than 50m3 to be cove red with tarpaulin. -
Manholes to be adequately
covered and temporarily sealed so as to prevent
silt, construction materials or debris being washed into the drainage system. -
All vehicles and plant to
be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads. -
Segregate and store
different types of waste in different containers, skip or stockpiles to
enhance reuse or recycling of materials and their proper disposal. -
Sort out demolition debris
and ex cavated materials from demolition works to
recover reusable/recyclable portions. -
Provide training to
workers on appropriate waste management procedures, including waste
reduction, reuse and recycling. -
To adopt other good site
practice, such as arrangements for collection and effective disposal to an
appropriate facility, of all wastes generated at the site and regular
cleaning and maintenance programme for drainage. -
Chemical wastes to be
stored in appropriate containers and collected by a licensed chemical waste
Contractor. Chemical wastes (e.g. spent lubricant oil) should be recycled at
an appropriate facility as far as possible, while the chemical waste that ca nnot be recycled should be disposed of at either the
Chemical Waste Treatment Centre, or another licensed facility, in accordance
with the Waste Disposal (Chemical Waste) (General) Regulation. -
Conducting Construction
Vibration Monitoring -
Tree Protection &
Preservation Exiting trees to be retained within the Project Site should be
carefully protected during construction. In particular OVTs
will be preserved according to ETWB Technical Circular (Works) No. 29/2004. -
Tree Transplantation Trees
unavoidably affected by the Project works should be transplanted where
practical. Trees should be transplanted straight to their final receptor site
and not held in a temporary nursery as far as possible. -
Erect 2m high dull green
site boundary fence. |
(b)
Cap
Construction |
E3-04a, E3-04b, E4-01 and E4-02 |
|||
(c)
Cross head construction |
B2-01, B2-02 and B2-03 |
|||
(d) Pier / Pier head
Construction |
D2-01 and E305M |
|||
(e)
Fabrication
for segment |
C2, C1, D1, D2, E1, E4 |
|||
(f)
Form
Traveler |
E3-01 construction 3rd to 6th
pair E2-02 construction 14th pair &
dismantling of FT1 D2-02 construction 6th to 8th
pair D2-03 construction 2nd pair to 4th
pair E2-01 erection of 5th set of form traveler. |
|||
(g)
Segment
Erection by Launching Girder & Crane |
bridges C3, C2 |
|||
(h) SOP construction (precast & in-situ cast in
type) |
D2-01 |
|||
(i)
Road
construction |
TWSRW, TWSRE |
|||
(j)
Road works |
Jockey Club Rd, TWSRW |
|||
(k)
Base slab
construction |
NB109 ¡V bay 11~12 |
|||
(l)
Tree
Works |
All works areas |
|||
|
|
|||
ND/2019/06 |
N/A |
N/A |
N/A |
N/A |
ND/2019/07 |
(a)
Road works |
Portion
1, 4, 5 |
-
Construction Dust Impact -
Noise Impact -
Water Quality Impact
(Construction Phase) -
Waste Management
(Construction Waste) -
Landscape and Visual |
-
Regular watering on
exposed worksites and haul road. -
Stockpiling area should be
provided with covers and water spraying system. -
Only well-maintained plant
to be operated on-site. -
plant known to emit noise
strongly in one direction, where possible, be orientated so that the noise is
directed away from nearby NSRs. -
mobile plant to be sited
as far away from NSRs as possible practicable. -
All open stockpiles of
construction materials of more than 50m3 to be covered with tarpaulin. -
Manholes to be adequately
covered and temporarily sealed so as to prevent
silt, construction materials or debris being washed into the drainage system. -
All vehicles and plant to
be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads. -
Segregate and store
different types of waste in different containers, skip or stockpiles to
enhance reuse or recycling of materials and their proper disposal. -
Sort out demolition debris
and excavated materials from demolition works to recover reusable/recyclable
portions. -
Provide training to
workers on appropriate waste management procedures, including waste
reduction, reuse and recycling. -
To adopt other good site
practice, such as arrangements for collection and effective disposal to an
appropriate facility, of all wastes generated at the site and regular
cleaning and maintenance programme for drainage. -
Chemical wastes to be
stored in appropriate containers and collected by a licensed chemical waste
Contractor. Chemical wastes (e.g. spent lubricant oil) should be recycled at
an appropriate facility as far as possible, while the chemical waste that
cannot be recycled should be disposed of at either the Chemical Waste
Treatment Centre, or another licensed facility, in accordance with the Waste
Disposal (Chemical Waste) (General) Regulation. -
Tree Protection &
Preservation ¡V Exiting trees to be retained within the Project Site should be
carefully protected during construction. In particular OVTs
will be preserved according to ETWB Technical Circular (Works) No. 29/2004. -
Tree Transplantation ¡V
Trees unavoidably affected by the Project works should be transplanted where
practical. Trees should be transplanted straight to their final receptor site
and not held in a temporary nursery as far as possible. -
Erect 2m high dull green
site boundary fence. -
Light Control ¡V Construction day and night time lighting should be
controlled to minimize glare impact to adjacent VSRs during the Construction
phase. |
(b)
C&D waste disposal |
Portion
1, 2, 4, 5 |
|||
(c)
Construction of box
culvert |
Portions
2 |
|||
(d)
Filling works |
Portions
1, 2, 4 |
|||
(e)
Construction of site haul
road |
Portions
4 |
|||
(f)
Drainage Works |
Portion 2, 3, 4 |
|||
(g)
Sewerage works |
Portion
3, 4 |
|||
(h)
Construction of Noise
Barrier |
Portion 5 |
|||
(i)
Waterworks |
Portion 1, 2, 4 |
|||
|
|
12.2
The
major site activities in coming three months are shown in Table IV.
Monitoring
Schedule for the Next Month
12.3 The tentative environmental
monitoring schedule for the next month is shown in Appendix D.
Construction
Programme for
the Next Month
12.4 A tentative construction programme is provided in Appendix A.