10
ENVIRONMENTAL SITE INSPECTION
10.1 Site audits were carried out by ET on a weekly
basis to monitor the timely implementation of proper environmental management practices
and mitigation measures on the Contract site. Summary of the site audits
are presented in Table 10.1 and Appendix
P.
Table 10.1 Summary
of Site Audits
Environmental
Site Inspection |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
|
Weekly site audit with representative of the Supervisor¡¦s
Representative and the Contractor |
2, 9, 17, 23 and 30 Jan 24 |
3, 10, 17, 24 and 31 Jan 24 |
5, 12, 16 and 23 Jan 24 |
4, 11, 15 and 25 Jan 24 |
2, 8, 18, 22 and 29 Jan 24 |
N/A |
5, 12, 19 and 26 Jan 24 |
Joint
Site Audit with representative of the Supervisor¡¦s Representative, the
Contractor and IEC |
17 Jan 24 |
31 Jan
24 |
16
Jan 24 |
15 Jan 24 |
18 Jan 24 |
N/A |
19 Jan 24 |
Remarks:
The weekly site inspection for ND/2019/06 has been terminated starting from
19/10/2023 since the termination proposal was approved by EPD on the same day.
10.2 During site inspections in the reporting month, no non-conformance was
identified. The observations and recommendations made during the audit sessions
are summarised in Table 10.2. Any outstanding and recurrence deficiencies are
presented in Table 10.3.
10.3 All construction activities with significant environmental impact
undertaken by Contract No. ND/2019/06 was substantially completed in March 2022
and the majority of outstanding works were also completed
in April 2022 with defect rectification works remained. The
outstanding installation works were the short-duration works which would be
completed within 2 months during the 1-year defect correction period,
originally estimated.
10.4 Due to problems in material
deliveries from Mainland China in 2022, the completion date of the outstanding
works would be extended to June 2023 tentatively. However, in June 2023, more
defects were found during the handover inspection so the rectification works
were undertaken until July 2023 when all works were completed.
10.5 The weekly site inspection and EM&A Reporting for ND/2019/06 were
maintained until the termination proposal for ND/2019/06 has been endorsed by
the IEC (17 Aug 23), the Engineer (26 Aug 23) and the Project Proponent (19 Sep
23) followed by approval from EPD (19 Oct 23) in accordance. The procedure for
termination proposal for ND/2019/06 is in accordance with section 15.4.2 of
updated EM&A Manual.
Table 10.2 Observations
and Recommendations during Site Audits
Date |
Observations and Recommendations |
Follow-up |
|
Contract No.: ND/2019/01 |
|||
Water Quality |
17/01/2024 |
Temporary drainage system at Pak Shek Au
should be reviewed to prevent muddy water discharge in the coming wet season. |
Improvement/Rectification
was observed during follow-up audit session on 23 Jan 2024. |
23/01/2024 |
Temporary drainage system at Portion 1C
should be maintained. |
Improvement/Rectification
was observed during follow-up audit session on 30 Jan 2024. |
|
23/01/2024 |
Debris and litter in RC2 should be cleared. |
Improvement/Rectification
was observed during follow-up audit session on 30 Jan 2024. |
|
30/01/2024 |
Groundwater pumped out should be redirected
to treatment facilities. |
Follow-up action is needed to be reported in the following month. |
|
Air Quality |
02/01/2024 |
Dust suppression should be enhanced at
Portion 3 and 13. |
Improvement/Rectification
was observed during follow-up audit session on 9 Jan 2024. |
02/01/2024 |
The NRMM label of the generator at Portion 3
should be displayed properly. |
Improvement/Rectification
was observed during follow-up audit session on 9 Jan 2024. |
|
09/01/2024 |
Mitigation measures for dust impact at
Portion 3 should be enhanced. Dust generation of exposed haul road was
observed during the site inspection. |
Improvement/Rectification
was observed during follow-up audit session on 17 Jan 2024. |
|
17/01/2023 |
The haul road at Portion 6A should be kept
clean and free from dust. |
Improvement/Rectification
was observed during follow-up audit session on 23 Jan 2024. |
|
Waste / Chemical Management |
17/01/2024 |
Drip tray for the chemical/fuel containers
should be provided at Pak Shek Au. |
Improvement/Rectification
was observed during follow-up audit session on 23 Jan 2024. |
30/01/2024 |
Drip tray should be provided to chemical
container. |
Follow-up action is needed to be reported in the following month. |
|
Noise |
28/12/2023 |
The NEL of the air compressor at Portion 8a
should be displayed. |
Improvement/Rectification
was observed during follow-up audit session on 2 Jan 2024. |
Contract No.: ND/2019/02 |
|||
Water Quality |
29/12/2023 |
Silt accumulating in
the nullah near the water outlet at the material storage should be cleared continuously.
Contractor was also reminded to enhance water mitigation measures to prevent
further accumulation of silt. |
Item
remarked as 240103-R02. Follow-up action is needed to be review. |
03/01/2024 |
Silt accumulating in
the nullah at Portion 11 should be cleared. Contractor was also reminded to
enhance water mitigation measures to prevent further accumulation. |
Item
remarked as 240110-R02. Follow-up action is needed to be review. |
|
10/01/2024 |
Item
remarked as 240117-R02. Follow-up action is needed to be review. |
||
17/01/2024 |
Item
remarked as 240124-R02. Follow-up action is needed to be review. |
||
24/01/2024 |
Muddy debris in the
U-channel near the nullah at Portion 11 should be cleared. |
Item
remarked as 240131-R02. Follow-up action is needed to be review. |
|
31/01/2024 |
Follow-up
action is needed to be reported in the following month. |
||
29/12/2023 |
Enhance the mitigation
measures to prevent waste or surface runoff for the discharge point of
Portion 1. |
Item
remarked as 240103-R03. Follow-up action is needed to be review. |
|
03/01/2024 |
Improvement/Rectification was
observed during follow-up audit session on 10 Jan 2024. |
||
29/12/2023 |
Provide maintenance to
impervious sheeting on the exposed slope at Portion 5. |
Improvement/Rectification was
observed during follow-up audit session on 3 Jan 2024. |
|
29/12/2023 |
Contractor was reminded
to ensure the vehicles are properly cleaned of dirt and dust before leaving the site. |
Item
remarked as 240103-R04. Follow-up action is needed to be review. |
|
03/01/2024 |
Improvement/Rectification was
observed during follow-up audit session on 10 Jan 2024. |
||
24/01/2024 |
Vehicles should be
properly cleared of earth and dust before leaving the site. |
Improvement/Rectification was
observed during follow-up audit session on 31 Jan 2024. |
|
03/01/2024 |
Proper drainage system
should be established at Portion 2 as soon as possible. |
Item
remarked as 240110-O01. Follow-up action is needed to be review. |
|
10/01/2024 |
Improvement/Rectification was
observed during follow-up audit session on 17 Jan 2024. |
||
03/01/2024 |
Silt accumulating in WetSep should be cleared to ensure water treatment
capacity of the WetSep. |
Item
remarked as 240110-R03. Follow-up action is needed to be review. |
|
10/01/2024 |
Improvement/Rectification was
observed during follow-up audit session on 17 Jan 2024. |
||
10/01/2024 |
Debris and mud were
observed at nearby WetSep. Contractor was reminded
to clean it and enhance the water mitigation measure to avoid surface runoff. |
Improvement/Rectification was
observed during follow-up audit session on 17 Jan 2024. |
|
10/01/2024 |
Clean the mud inside
the silt curtain as maintenance. |
Item
remarked as 240117-R04. Follow-up action is needed to be review. |
|
17/01/2024 |
Improvement/Rectification was
observed during follow-up audit session on 24 Jan 2024. |
||
10/01/2024 |
Provide impervious
sheeting for the exposed slope. |
Improvement/Rectification was
observed during follow-up audit session on 17 Jan 2024. |
|
17/01/2024 |
Treated water was
discharged into inappropriate location. Contractor was reminded to discharge
water into the valid point. |
Item
remarked as 240124-O01. Follow-up action is needed to be review. |
|
24/01/2024 |
Item
remarked as 240131-O01. Follow-up action is needed to be review. |
||
31/01/2024 |
Follow-up
action is needed to be reported in the following month. |
||
17/01/2024 |
Enhance the water
mitigation measure to avoid surface runoff to nearby watercourse. |
Item
remarked as 240124-R04. Follow-up action is needed to be review. |
|
24/01/2024 |
Water mitigation
measures should be provided for the works area next to Shek Sheung River to
prevent muddy runoff from discharging into the river. |
Item
remarked as 240131-R03. Follow-up action is needed to be review. |
|
31/01/2024 |
Follow-up
action is needed to be reported in the following month. |
||
31/01/2024 |
Enhance the water
mitigation measure to avoid surface runoff. (Portion 5) |
Follow-up
action is needed to be reported in the following month. |
|
Air Quality |
29/12/2023 |
Dusty stockpile and
exposed slopes should be covered with tarpaulin sheets. |
Improvement/Rectification was
observed during follow-up audit session on 3 Jan 2024. |
10/01/2024 |
Provide impervious
sheeting for the dusty stockpile. |
Improvement/Rectification was
observed during follow-up audit session on 17 Jan 2024. |
|
Landscape and Visual |
29/12/2023 |
The removed green
hoarding along Sheung Yue River due to the construction works should be
replaced and maintained properly as soon as possible. |
Item
remarked as 240103-R01. Follow-up action is needed to be review. |
03/01/2024 |
Item remarked
as 240110-R01. Follow-up action is needed to be review. |
||
10/01/2024 |
Item
remarked as 240117-R01. Follow-up action is needed to be review. |
||
17/01/2024 |
Item
remarked as 240124-R01. Follow-up action is needed to be review. |
||
24/01/2024 |
Item remarked
as 240131-R01. Follow-up action is needed to be review. |
||
31/01/2024 |
Follow-up
action is needed to be reported in the following month. |
||
Waste / Chemical Management |
03/01/2024 |
Oil leakage was
observed. Contractor was reminded to clear the oil leakage immediately. |
Improvement/Rectification was
observed during follow-up audit session on 10 Jan 2024. |
10/01/2024 |
Keep site tidy and
clean avoid waste accumulation. |
Improvement/Rectification was
observed during follow-up audit session on 17 Jan 2024. |
|
17/01/2024 |
Keep site tidy and
clean to avoid waste accumulation for Dills Corner. |
Improvement/Rectification was
observed during follow-up audit session on 24 Jan 2024. |
|
17/01/2024 |
Provide drip tray for
the chemical/fuel containers for Dills Corner. |
Improvement/Rectification was
observed during follow-up audit session on 24 Jan 2024. |
|
31/01/2024 |
Provide drip tray for
the chemical/fuel containers. (Portion 5) |
Follow-up
action is needed to be reported in the following month. |
|
Ecology |
03/01/2024 |
The removed green
hoarding along Sheung Yue River due to the construction works should be
replaced and maintained properly as soon as possible. |
Item
remarked as 240110-R01. Follow-up action is needed to be review. |
10/01/2024 |
Item
remarked as 240117-R01. Follow-up action is needed to be review. |
||
17/01/2024 |
Item
remarked as 240124-R01. Follow-up action is needed to be review. |
||
24/01/2024 |
Item
remarked as 240131-R01. Follow-up action is needed to be review. |
||
31/01/2024 |
Follow-up
action is needed to be reported in the following month. |
||
Contract No.: ND/2019/03 |
|||
Air Quality |
05/01/2024 |
Exposed work site should be sprayed with water as dust suppression. |
Improvement/Rectification
was observed during follow-up audit session on 12 Jan 2024. |
Water Quality |
23/01/2024 |
Wheel-washing facilities should be provided at the site entrance/exit. |
Follow-up action is needed to be reported in the following month. |
Waste/Chemical Management |
23/01/2024 |
The chemical/fuel containers should be placed inside the drip tray. |
Follow-up action is needed to be reported in the following month. |
Contract No.: ND/2019/04 |
|||
Air Quality |
04/01/2024 |
The exposed haul road at Portion K should be sprayed with water regularly
as dust suppression. |
Improvement/Rectification
was observed during follow-up audit session on 11 Jan 2024. |
15/01/2024 |
Dust suppression measures should be enhanced e.g. water-spraying. |
Improvement/Rectification
was observed during follow-up audit session on 15 Jan 2024. |
|
25/01/2024 |
The haul road at Portion K should be watered regularly as dust
suppression. |
Follow-up action is needed to be reported in the following month. |
|
25/01/2024 |
Dusty stockpile at Portion K should be covered properly to reduce dust
emission. |
Follow-up action is needed to be reported in the following month. |
|
Ecology |
28/12/2023 |
The silt curtain at Bridge F should be maintained properly and
regularly. |
Item remarked as 240104-R01. Follow-up action is needed to be review. |
04/01/2024 |
Improvement/Rectification
was observed during follow-up audit session on 11 Jan 2024. |
||
11/01/2024 |
The 2m high green barrier of the 10m vegetated buffer zone between
A2-03 and A2-04 should be maintained properly and regularly. |
Item remarked as 240115-R03. Follow-up action is needed to be review. |
|
15/01/2024 |
Item remarked as 240125-R04. Follow-up action is needed to be review. |
||
25/01/2024 |
Follow-up action is needed to be reported in the following month. |
||
Waste / Chemical Management |
15/01/2024 |
General refuse should be disposed of regularly and properly at
depressed road A. |
Improvement/Rectification
was observed during follow-up audit session on 15 Jan 2024. |
25/01/2024 |
Drip tray for the chemical/fuel containers should be provided. Oil
spillage was observed. |
Follow-up action is needed to be reported in the following month. |
|
Contract No.: ND/2019/05 |
|||
Waste / Chemical Management |
08/01/2024 |
Drip tray should be provided for the chemical/fuel containers at
C4-01b. |
Improvement/Rectification
was observed during follow-up audit session on 18 Jan 2024. |
Water Quality |
18/01/2024 |
Enhance the water mitigation measure to avoid surface runoff at Bridge
C. |
Improvement/Rectification
was observed during follow-up audit session on 22 Jan 2024. |
29/01/2024 |
Sandbag barriers should be enhanced at D2-01 to make sure the surface
runoff stays in the site boundary. |
Follow-up action is needed to be reported in the following
month. |
|
Air Quality |
18/01/2024 |
Provide valid NRMM label for the generator at C1-03b. |
Improvement/Rectification
was observed during follow-up audit session on 22 Jan 2024. |
Contract No.: ND/2019/06 |
|||
-- |
-- |
-- |
-- |
Contract No.: ND/2019/07 |
|||
Waste/Chemical Management |
19/01/2024 |
Keep site tidy and clean at near Ma Sik Road. |
Improvement/Rectification
was observed during follow-up audit session on 26 Jan 2024. |
Table 10.3 Summary Table for the Outstanding item(s) in the
reporting month
Contract No. |
Outstanding deficiencies
since last reporting month (Dec 2023) |
Deficiencies recorded in the reporting month (Jan 2024) |
Total deficiencies (including
repeated deficiencies) in the reporting month |
Deficiencies rectified in the
reporting month |
Outstanding deficiencies need to be Follow-up in the
next month (Feb 2024) |
Total outstanding deficiencies |
||||||||||||||
A |
N |
W |
W/C |
CH |
L&V |
E |
P/L |
A |
N |
W |
W/C |
CH |
L&V |
E |
P/L |
|||||
ND/2019/01 |
1 |
4 |
1 |
4 |
2 |
/ |
/ |
/ |
/ |
11 |
9 |
/ |
/ |
1 |
1 |
/ |
/ |
/ |
/ |
2 |
ND/2019/02 |
6 |
2 |
/ |
27 |
5 |
/ |
6 |
5 |
/ |
45 |
15 |
/ |
/ |
4 |
1 |
/ |
1 |
1 |
/ |
7 |
ND/2019/03 |
/ |
1 |
/ |
1 |
1 |
/ |
/ |
/ |
/ |
3 |
1 |
/ |
/ |
1 |
1 |
/ |
/ |
/ |
/ |
2 |
ND/2019/04 |
1 |
4 |
/ |
/ |
2 |
/ |
/ |
5 |
/ |
11 |
4 |
2 |
/ |
/ |
1 |
/ |
/ |
1 |
/ |
4 |
ND/2019/05 |
/ |
1 |
/ |
2 |
1 |
/ |
/ |
/ |
/ |
4 |
3 |
/ |
/ |
1 |
/ |
/ |
/ |
/ |
/ |
1 |
ND/2019/06* |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
ND/2019/07 |
/ |
/ |
/ |
/ |
1 |
/ |
/ |
/ |
/ |
1 |
1 |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
/ |
Legends:
A = Air Quality
N = Construction Noise Impact
W = Water Quality
W/C = Waste / Chemical Management
CH = Cultural Heritage
L&V = Landscape & Visual
E = Ecology
P/L = Permit / Licences
* The weekly site inspection
for ND/2019/06 has been terminated starting from 19/10/2023 since the
termination proposal was approved by EPD on the same day.
Implementation
Status of Environmental Mitigation Measures
10.6 According to the EIA Report, EPs and the Updated EM&A Manual, the mitigation
measures detailed in the documents are recommended to be implemented during the
construction phase. An updated summary of the Environmental Mitigation
Implementation Schedule is provided in Appendix
Q. The photographic records of measures as stipulated in EPs to
mitigate environmental impacts in the reporting month are presented in Table 10.4.
Table 10.4 Photographic Records and Implementation Status of
Measures
EP
No. |
Condition |
Photographic
Record |
Implementation
Status |
EP-466/2013/A |
2.9 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m high
solid dull green site barrier fences shall be erected around all active works
areas. |
^[1] |
EP-467/2013/A |
2.9 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the Project, 2m
high solid dull green site barrier fences shall be erected around all active
works areas. |
^[1] |
EP-468/2013/A |
2.11 |
To minimise adverse
impacts on habitats of ecological importance in the vicinity of the Project,
2m high solid dull green site barrier fences shall be erected around all
active works areas. |
^[1] |
EP-469/2013 |
2.7 |
To minimise
adverse impacts on habitats of ecological importance in the vicinity of the
Project, 2m high solid dull green site barrier fences shall be erected around
all active works areas. |
^[1] |
EP-473/2013/A |
2.13 |
To minimise adverse
impacts on habitats of ecological importance in the vicinity of the Project,
2m high solid dull green site barrier fences shall be erected around all
active works areas. |
^[1] |
EP-475/2013/A |
2.7 |
To minimise adverse
impacts on habitats of ecological importance in the vicinity of the Project,
2m high solid dull green site barrier fences shall be erected around all
active works areas. |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance
of mitigation measure ¡P Non-compliance
but rectified by the contractor N/A Not Applicable at this stage as no such
site activities were conducted in the reporting period |
Remark:
[1]: Barrier fences might be
subjected to change according to the phasing plan designed at detailed design
stage
Implementation
Status of Water Quality Mitigation Measures
10.7 The water
quality mitigation measures detailed in the EIA Report and the Updated EM&A
Manual are recommended to be implemented during the construction phase. Water
quality mitigation measures implemented by the contractors were closely
monitored to prevent water pollution, especially during rainy season. An
updated summary of the Environmental Mitigation Implementation Schedule is
provided in Appendix Q. Specific water quality mitigation measures for
major construction works in the reporting month are presented in Table 10.4.
Table 10.5 Specific
Water Quality Mitigation Measures for Major Construction Works in the Reporting
Month
Works Contracts |
Photographic Records |
|
ND/2019/01 |
Hard paved exposed
slope surface |
Hydroseeding for slope
area |
ND/2019/02 |
Hard
paved exposed haul road |
Hard
paved exposed slope surface |
ND/2019/03 |
Hard paved exposed haul
road |
Watering the main haul
road regularly. |
ND/2019/04 |
Hard
paved exposed slope surface |
Deployment
of silt curtain around works area in Ng Tung River |
ND/2019/05 |
Covering dusty
stockpile |
Provision of sand bags around works area |
ND/2019/07 |
Covering exposed slope surface with tarpaulin |
De-silting
waste water before discharge |
Water quality mitigation measures for site(s) in operation
phase, remaining defect works |
||
ND/2019/06 |
Hard paved exposed haul
road |
Hard
paved exposed haul road |
Solid and
Liquid Waste Management Status
10.8 Waste generated from Contract Nos. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04,
ND/2019/05 and ND/2019/07 included inert construction and demolition (C&D)
materials and non-inert C&D wastes in the reporting month. The site of ND/2019/06 was handed over to
AFCD for operation since 4 April 2022.
10.9 The amount of wastes generated by the
construction works of the Contract Nos. ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04,
ND/2019/05 and ND/2019/07 during the reporting month are shown in Appendix R. The site of ND/2019/06 was handed over to AFCD for
operation since 4 April 2022.
10.10 The Contractors are advised to minimise
the wastes generated through recycling or reusing. All mitigation measures
stipulated in the Updated EM&A Manual and waste management plans shall be
fully implemented. The status of implementation of waste management and
reduction measures are summited in Appendix
Q.
Ecological
Mitigation Measures ¡V Creation of Long Valley Nature Park (LVNP)
10.11 Based on the
findings of the EIA Report, the area of Long Valley has been assessed as of high to very
high ecological value and is the largest contiguous area of freshwater wetland
habitats in Hong Kong. To safeguard the ecological value of Long Valley, about
37 hectares of land in Long Valley has been proposed to develop into Long
Valley Nature Park (LVNP) for conserving and enhancing the ecologically
important environment as well as for compensation of the wetland loss due to
the NDA development.
10.12 LVNP is developed according
to the approved Habitat Creation and Management Plan (HCMP) submitted under
EP-468/2013/A. HCMP provides a framework and specifications for development and
management of LVNP and guides the development to maintain and enhance the 37
hectares of low-lying wetland habitats.
10.13 Regarding the design, the zoning of land use in LVNP is intended to
maintain the existing mosaic pattern of wet and dry agriculture, while
controlling the activities that could potentially disturb target habitats and
species. LVNP will be divided into three broad zones of land use as below:
• Biodiversity Zone of about 21 hectares largely designated for
biodiversity conservation through cultivation of specified crops and habitat
management.
• Agricultural Zone of about 11 hectares designated for commercially
focuses crop production and eco-friendly agricultural practice for farming.
• Visitor Zone of about 5 hectares designed to accommodate visitors as
well as storage and other facilities and for educational purposes.
10.14 The construction of LVNP started in late 2019 and was expected to
be completed in 2023. During the construction period, the progress of construction and wetland
enhancement works has been under observation by different stakeholders including AFCD and green
groups. Close communication between AFCD and CEDD were
conducted to exchange views on conservation, restoration
and management of habitats as well as on the planning and design of the park. In addition, advices from green groups, Hong Kong Bird Watching Society (HKBWS) and
The Conservancy Association (CA), have been taken on habitat management of Long Valley
and potential effects on habitat and wildlife of each individual work conducted
in Long Valley. The last meeting was held on 18 November 2022 to share the progress of LVNP with different
stakeholders, including CEDD, AFCD, CA, HKBWS, Contractor, ET, IEC and farmers.
10.15 Proposals on wetland creation and restoration, dry agricultural land
creation, pond creation, water treatment wetland and design of irrigation
channel were submitted by the Contractor to achieve the objectives stated in HCMP
and accepted by the Engineer with consent from AFCD before implementation. The
Contractor would consult the stakeholders for recommendations and suggestions on
mitigation measures to minimise the environmental
impacts arising from construction works. The progress of works would be
arranged to minimise impacts to avifauna and maintain
the habitat for avifauna. The photographic records of site activities in LVNP
are presented in Table 10.5.
Table 10.6 Photographic
Records of Site Activities in LVNP
Continuing agricultural practice in existing
farmland to maintain habitats in Long Valley |
|
Open water Habitat |
Open water Habitat |
Creation of wetland with designated habitat for
biodiversity conservation |
|
Planting of paddy rice to provide foraging ground
for Yellow-breasted Bunting |
|
Enhancement of irrigation channel
to provide reliable water source for farmland in Long Valley |
|
Provision of bird island (hidden area) |
Restoring of water flea pond to provide food
source to water birds |
Construction of storage sheds for farmers |
A
Himantopus himantopus was recorded |
Wet agricultural land |