Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (February to April 2024)

ND/2019/01

(a)          Drainage works, watermain works and sheet piles in Portion 1a

(b)         Site formation, erection of hoarding and construction of noise barrier in Portion 1c

(c)          Sheet Piling, Site formation work, construction of subway, road works and drainage works in Portion 2

(d)         Site formation, site clearance, excavation, slope work, drainage and watermain works in Portion 3

(e)          Watermain works, excavation, backfilling, road works and pipe jacking in Portion 5

(f)          Drainage works, backfilling, road works and watermains works in Portion 6a

(g)         Operation of HAC treatment facility in Portion 6b

(h)         Sheet piling, excavation, stockpile of soil, drainage works and watermain work in Portion 7

(i)           Construction of retaining wall, RC construction of fresh water reservoir, excavation at WSD¡¦s maintenance access, backfilling works, drainage works and pipe pile wall installation in Portion 8a

(j)           Trenchless work, excavation, watermain works and ground treatment in Portion 8b

(k)         Sheet piling, excavation, road works, drainage works and watermain works in Portion 9b

(l)           Removal of existing structure in Portion 11b

(m)       Site clearance, tree felling, removal of existing structure, site formation and stockpile of soil in Portion 13

ND/2019/02

(a)           Pipe Jacking

(b)           Backfilling

(c)           Concreting

(d)           Bedding & Pipe Laying

(e)           ELS

(f)            Sheet Pile Installation

(g)           Cut and Fill of Slope

ND/2019/03

(a)      Portion 2 to Portion 20C

-          Wetland creation & restoration, Dry agricultural land creation

-          Construction of compacted earth path

-          Construction of Water Treatment Wetland

-          Tree felling and tree pruning work

-          Construction of Dry Weather Flow Interception (DWFI)

-          Construction of Car Park and Farmer¡¦s Forum

ND/2019/04

(a)           Tree Pruning

(b)           Pile Cap

(c)           Back Filling

(d)           Excavation

(e)           Grouting

(f)            Sheet Piling

(g)           Road works

(h)           Formwork and Scaffolding Erection

(i)            Rebar Fixing

(j)            Bore pile

(k)           ELS

ND/2019/05

(a)           North Team Works

-          Backfilling and drainage work at C4-02 & C4-01. 

-          Backfilling at C3-03, C3-04, portion II & C2-01.

-          Haul Road to bridge deck In On Lok Garden.

-          Construction of remaining abutment wall near portal B2-01.

-          Construction of FW 53.

-          Water works & drainage works at Jockey Club Rd.

-          Road works of northbound of Jockey Club Rd & ducting works at central median and across Jockey Club Rd. 

-          Sampling of existing pavement in southbound of Jockey Club Rd for CSD.

-          Construction of new box culvert extension & retaining wall & slope works at Tong Hang Tsuen.

-          Drainage works ¡VDN 900 at On Kui Street near B1.

-          Cross head construction at B2-01, B2-02 & B2-03.

-          Segment fabrication for bridge D2, E4

-          Segments erection by LG at bridges C2, C1

-          SOP construction at D2-01

-          Parapet skin fabrication and parapet construction

-          Segment fabrication for bridge B2.

(b)         South Team Works

-          TWSRW ¡V Road work and UUs laying (Section P800 CH 450 to 600).

-          TWSRW ¡V Construction of lower berm and Hydroseeding at FS04.

-          TWSRW ¡VGas (IPA400 and HP600) diversion work

-          TWSRW ¡V 450mm Freshwater main 1st stage diversion

-          TWSRW ¡V Construction of D2-04M pile cap.

-          HKY FB (East) ¡V Installation of floor tiles and railing.

-          HKY FB (West) ¡V Construction of LT2 pile cap

-          E3-04a, E304b, E4-01 and E4-02 ¡V cap construction

-          E305M Pier Head construction

-          NB109 ¡V Bay 13~20 ELS works

-          NB69 ¡V Bay 2~8 ELS works

-          NB110 ¡V Bay 6~7 ELS works

-          NB29 U-through ¡V Bay 9~10 footing construction

-          Retaining Wall FW02

-          Removal Sign Gantry DS64

(c)          Form Traveler

-          E3-01 ¡V construction 6th pair

-          E2-02 ¡VFT erection

-          D2-02 ¡V construction 10th to 11th pair

-          D2-03 ¡V construction 5th pair to 8th pair

-          E2-01 - construction 3rd pair to 7th pair

ND/2019/06

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 1, 4 and 5

(a)        C&D waste disposal at Portion 1, 2, 4 and 5

(b)        Construction of box culvert at Portion 2

(c)        Filling works at Portion 2 and 4

(d)        Construction of site haul road at Portion 4

(e)        Drainage works, Sewerage works at Portion 2, 3, 4

(f)         Construction of noise barrier at Portion 4 and 5

(b)       Waterworks at Portion 1, 2 and 4