Table IV Summary Table for Site Activities in the coming Three
Months
Contract No. |
Site
Activities (February to April 2024) |
|
ND/2019/01 |
(a)
Drainage works,
watermain works and sheet piles in Portion 1a (b)
Site
formation, erection of hoarding and construction of noise barrier in Portion
1c (c)
Sheet
Piling, Site formation work, construction of subway, road works and drainage
works in Portion 2 (d)
Site
formation, site clearance, excavation, slope work, drainage and watermain
works in Portion 3 (e)
Watermain
works, excavation, backfilling, road works and pipe jacking in Portion 5 (f)
Drainage
works, backfilling, road works and watermains works in Portion 6a (g)
Operation
of HAC treatment facility in Portion 6b (h)
Sheet
piling, excavation, stockpile of soil, drainage works and watermain work in
Portion 7 (i)
Construction
of retaining wall, RC construction of fresh water reservoir, excavation at WSD¡¦s
maintenance access, backfilling works, drainage works and pipe pile wall
installation in Portion 8a (j)
Trenchless
work, excavation, watermain works and ground treatment in Portion 8b (k)
Sheet
piling, excavation, road works, drainage works and watermain works in Portion
9b (l)
Removal of existing
structure in Portion 11b (m)
Site
clearance, tree felling, removal of existing structure, site formation and
stockpile of soil in Portion 13 |
|
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
|
ND/2019/03 |
(a)
Portion 2
to Portion 20C -
Wetland
creation & restoration, Dry agricultural land creation -
Construction
of compacted earth path -
Construction
of Water Treatment Wetland -
Tree
felling and tree pruning work -
Construction
of Dry Weather Flow Interception (DWFI) -
Construction of Car Park
and Farmer¡¦s Forum |
|
ND/2019/04 |
(a)
Tree Pruning (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork and Scaffolding Erection (i)
Rebar Fixing (j)
Bore pile (k)
ELS |
|
ND/2019/05 |
(a)
North
Team Works -
Backfilling
and drainage work at C4-02 & C4-01.
-
Backfilling
at C3-03, C3-04, portion II & C2-01. -
Haul Road
to bridge deck In On Lok Garden. -
Construction
of remaining abutment wall near portal B2-01. -
Construction
of FW 53. -
Water
works & drainage works at Jockey Club Rd. -
Road
works of northbound of Jockey Club Rd & ducting works at central median
and across Jockey Club Rd. -
Sampling
of existing pavement in southbound of Jockey Club Rd for CSD. -
Construction
of new box culvert extension & retaining wall & slope works at Tong
Hang Tsuen. -
Drainage
works ¡VDN 900 at On Kui Street near B1. -
Cross
head construction at B2-01, B2-02 & B2-03. -
Segment
fabrication for bridge D2, E4 -
Segments
erection by LG at bridges C2, C1 -
SOP
construction at D2-01 -
Parapet
skin fabrication and parapet construction -
Segment
fabrication for bridge B2. (b)
South
Team Works -
TWSRW ¡V
Road work and UUs laying (Section P800 CH 450 to 600). -
TWSRW ¡V
Construction of lower berm and Hydroseeding at FS04. -
TWSRW ¡VGas
(IPA400 and HP600) diversion work -
TWSRW ¡V 450mm
Freshwater main 1st stage diversion -
TWSRW ¡V Construction
of D2-04M pile cap. -
HKY FB
(East) ¡V Installation of floor tiles and railing. -
HKY FB
(West) ¡V Construction of LT2 pile cap -
E3-04a,
E304b, E4-01 and E4-02 ¡V cap construction -
E305M
Pier Head construction -
NB109 ¡V
Bay 13~20 ELS works -
NB69 ¡V
Bay 2~8 ELS works -
NB110 ¡V
Bay 6~7 ELS works -
NB29 U-through ¡V Bay 9~10 footing construction -
Retaining
Wall FW02 -
Removal
Sign Gantry DS64 (c)
Form
Traveler -
E3-01 ¡V construction 6th
pair -
E2-02 ¡VFT erection -
D2-02 ¡V construction 10th
to 11th pair -
D2-03 ¡V construction 5th
pair to 8th pair -
E2-01 - construction 3rd
pair to 7th pair |
|
ND/2019/06 |
The construction phase has
been completed and handed over to AFCD since 4 April 2022. |
|
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (a)
C&D waste disposal at Portion 1, 2, 4 and 5 (b)
Construction of box culvert at Portion 2 (c)
Filling works at Portion 2 and 4 (d)
Construction of site haul road at Portion 4 (e)
Drainage works, Sewerage works at Portion 2, 3, 4 (f)
Construction of noise barrier at Portion 4 and 5 (b)
Waterworks at Portion 1, 2 and 4 |
|