Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract No. |
Site Activities (January 2024) |
|
|
ND/2019/01 |
(a)
Drainage
works, watermain works and sheet piles in Portion 1a (b)
Site
formation and erection of hoarding in Portion 1c (c)
Sheet
piling, site clearance, site formation, construction of subway, drainage
works and road works in Portion 2 (d)
Drainage
works in Portion 3 (e)
Site
formation and excavation in Portion 5 (f)
Backfilling,
drainage and watermain works in Portion 6a (g)
Operation
of HAC treatment facility in Portion 6b (h)
Excavation
and drainage works in Portion 7 (i)
RC
construction of fresh water reservoir, drainage works, backfilling works and construction
of receiving pit in Portion 8a (j)
Trenchless
work and watermain construction in Portion 8b (k)
Sheet
piling, excavation, drainage and watermain works in Portion 9b (l)
Removal of existing
structure in Portion 11b (m)
Site
clearance, removal of existing structures, site formation and erection of
hoarding in Portion 13 |
|
|
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
|
|
ND/2019/03 |
Portion 2 to Portion 20C -
Wetland
creation & restoration, Dry agricultural land creation -
Construction
of compacted earth path -
Construction
of Water Treatment Wetland -
Tree
felling and tree pruning work -
Construction
of Lodging Facility -
Construction
of Dry Weather Flow Interception (DWFI) -
Construction of Car Park
and Farmer¡¦s Forum |
|
|
ND/2019/04 |
(a)
Tree Pruning (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork and Scaffolding Erection (i)
Rebar Fixing (j)
Bore pile (k)
ELS |
|
|
ND/2019/05 |
(a)
South
Team -
E3-05M ¡V
Pier head construction in progress. -
E3-04a ¡V
Column construction in progress. -
E3-04b ¡V
ELS in progress. Unforeseen obstruction encountered and removed. -
E4-01 ¡V
ELS in progress. -
E4-02 ¡V
ELS pipe pile wall in progress. Unforeseen obstruction encountered. -
D2-04M ¡V
Bored Piling completed on 22 Nov 2023. -
FS04 ¡V
Raking drain completed. Middle berm and U-channel construction in progress. -
Works in
TWSRE A.
BBI cover
walkway (Steelwork) ¡V 1st stage was completed. B.
HKY
Footbridge/Staircase ¡V Temporarily opened to public. C.
BBI
Toilet ¡V Base slab was casted. Wall construction is in progress. D.
Connecting
Road L201 to D300 ¡V Drainage and Kerb construction
are in progress. -
Works in
TWSRW A.
TWRSW
Stage 2 TTA completed on 22 Nov 2023. B.
FS04 ¡V raking drain
completed. Middle berm and U-channel construction in progress. C.
11kv
cable laying (near HKY entrance) in progress. D.
Drainage
work ¡V Laying 2x1200Dia Pipes to Manhole (FL9110) in progress. E.
Sewerage
work ¡V Laying 600Dia pipes at FW06 is in progress. F.
Gas Pipe
laying (IPA400/HP600 ¡V near HKY entrance) in progress. G.
Fresh
watermain diversion in progress. Connection works to be carried out by WSD in
Late Jan 2024. H.
Lift LT02
¡V Piling works completed. Proof drilling completed. Loading tests are in
progress. -
NB109 A.
Bay 5, 6, 7, 8 ¡V Top wall
in progress B.
Bay 9, 10, 11, 12 ¡V Bottom
wall completed. Backfilling in progress. C.
Bay 13
Site Clearance completed. ELS in progress. -
NB69 A.
Bay 5,
Bay 6 ¡V Top Wall in progress. B.
Bay 2,
Bay 3 ¡V ELS is in progress. Unforeseen obstruction encountered and removed. C.
Bay 6,
Bay 7, Bay 8 ¡V ELS is in progress. Uncharted 150 dia. Watermain encountered. -
NB110 A.
Bay 3 to
5 - Backfilling reached formation. Temporary FVMS is installed for removal of
Sign Gantry DS64. B.
Bay 8 -
Wall was completed on 10 Nov 2023. C.
Bay 9 ¡V Footing
completed. Wall in progress. -
NB 29 A.
Trial Panel
for wall is completed. B.
2 nos
Plate Load Test were carried out and completed. C.
Bay 10, 11 ¡V Footing is in
progress. (b)
North
Team -
C2-01 crosshead
completed. -
Side
formwork for C1-02 portal beam construction completed. -
Truss
erection for C1-01 MJ portal construction in completed. -
Falsework
erection for B2-01, B2-02 & B2-03 cross head construction in progress. -
Sheet
pile extraction of B1-Abutment wall-phase 2 completed. -
Construction
of remaining abutment wall near B1-02 portal beam was in progress. -
Backfilling
& extraction of sheet pile at C2-02 completed. -
Backfilling
at C4-02, C4-01a & C4-01b were in progress -
Permanent
reinstatement of footpath near C4-01a was in progress. -
JCR:
Construction of new central median was in progress. -
JCR:
Construction of pipe support for DN 150 exposed pipe & trench excavation
for WSD were in progress. -
JCR &
Tong Hang Village J/O improvement works: Construction of box-culvert &
extension head wall was in progress. -
On Kui
Street Construction of manhole & associated DN 900 drain pipe were in progress (c)
Bridges
and Structures -
Total 782 segments were
casted in Huizhou casting yard. -
Total 524 segments were
delivered to site, and total 492 segments erected. -
C2 03 to C2 04 end span
segment erection by LG in progress. -
Fabrication of steel
support for Bridge B1 completed at Zhengzhou. -
Erection of Bridge B1
steel platform in progress. -
The fabrication of 2 sets
of steel molds for Bridge B2 precast segment in progress. -
Fabrication of parapet
skin commenced at ShenZhen casting yard, total 120
pieces parapet skin fabricated. -
Construction of D2 01 SOP
in progress. (d)
Form Traveler -
Form
traveler rebar fixing for 06th pair segment at E3 01 in progress. -
Form
traveler rebar fixing for 09th pair segment at D2 02 in progress. -
Form
traveler rebar fixing for 05th pair segment at D2 03 in progress. -
Form
traveler rebar fixing for 03rd pair segment at E2 02 in progress. -
FT01
dismantling at E2 01 completed. -
Completed
concreting E2 E2 01 E2 02 S01, E2 E2 01 E1 04 01 S01. E2 E2 01 E2
02 S02, E2 E2 01 E1 04 01 S02. -
Completed
concreting D2 D2 02 D2 03 S07, D2 D2 02 D2 01 S07, D2 D2 02 D2 03
S08, D2 D2 02 D2 01 S08. -
Completed
concreting D2 D2 03 D2 04 S03, D2 D2 03 D2 02 S03, D2 D2 03 D2 04
S04, D2 D2 03 D2 02 S04. -
Completed
concreting E3 E3 01 E2 03 S04 & E3 E3 01 E3 02 S04, E3 E3 01 E2 03
S05 & E3 E3 01 E3 02 S05. |
|
|
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
|
|
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at Portion 2, 3, 4
and 5 (d)
Construction of box culvert at Portion 2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at Portion 4 (g)
Waterworks at Portion 1, 2 and 4 |
||