Table 12.1 Summary Table for Site
Activities, Potential Environmental Impacts and Recommended Mitigation Measures
in the Coming Months
Contract No. |
Major Site
Activities |
Location/
Working Period |
Potential
Environmental Impact |
Recommended
Mitigation Measures |
ND/2019/01 |
(a)
Site
clearance / tree felling |
Portion 2, 13 |
- Construction
Dust impact - Noise
Impact (Construction Phase) - Water
Quality Impact (Construction Phase) - Waste Management (Construction Waste) |
Air -
Watering on exposed earth and haul road. -
Cover the stockpiles or dusty materials. -
Deploy water bowsers to water the haul road. -
Deploy mist-cannon on site -
Provide shelter with top and 3-sides for cement production activities. -
Cover the Arsenic-containing soil. -
Store the bulk cement in enclosed silo tank for soil treatment. -
Close the mechanical cover of the vehicles used for transporting dusty
materials. -
Establish vehicle wheel washing facilities at vehicle exit points. -
Speed control of site vehicles. Noise -
Regular inspect of construction plants in good condition. -
Provide temporary noise screens if necessary. -
Use of Quiet plants (QPME) and working methods if possible. -
Sequencing operation of construction plants where practicable. -
Shut down the machines and plant if not in use. -
Only well-maintained plant to be operated on-site -
Mobile plant to be sited as far away from NSRs as possible
practicable. -
Conduct noise monitoring regularly. -
Erect
silent-up noise barrier at portion 6b. Water -
Set up wastewater treatment system (AquaSed)
on site -
Erect soil bund / temporary drain to divert /collect surface runoff. -
Maintain the drainage and wastewater treatment facilities. Waste /
Chemical Management -
Sort out demolition debris and excavated materials from demolition
works to recover reusable / recyclable portions -
Provide recycling bins on site, encourage reuse and recycle as much as possible. -
Provide drip trays for chemical containers. -
Chemical spill kit
available on site. -
Chemical waste cabinet
available on site. -
Chemical wastes to be
stored in appropriate containers and collected by a licensed chemical waste
collector. -
Delivery of yard waste
to tree shredding facility for upcycling. |
(b)
GI works |
NIL |
|||
(c)
Excavation
/ Backfilling |
Portion 5, 6a, 7, 8a, 9b |
|||
(d)
Construction
of receiving pit |
Portion 8a |
|||
(e)
Construction of noise barrier |
NIL |
|||
(f) Site Formation |
Portion 1c, 2, 5, 13 |
|||
(g)
Removal of
existing structure |
Portion 11b, 13 |
|||
(h)
Construction
of subway |
Portion 2 |
|||
(i)
Operation
of HAC treatment facility |
Portion 6b |
|||
(j)
Drainage works / watermains works |
Portion 1a, 2, 3, 6a, 7, 8a, 8b, 9b |
|||
(k) Road Construction |
Portion 2 |
|||
(l)
Trenchless |
Portion 8b |
|||
(m)
Construction of reservoir |
Portions 8a |
|||
(n)
Ground Treatment |
NIL |
|||
(o) Erection of hoarding |
Portion 1c, 13 |
|||
(p) Sheet
piling / ELS & pipe pile |
Portion 1a, 2, 9b |
|||
ND/2019/02 |
(a)
Pipe
Jacking |
Portions 1, 5 |
Air, Noise, Waste |
-
Dusty works should be
spray water. Idle stockpile or slop should be
covered by Tarpaulin sheet properly. -
Wheel washing should
be carried out at every exit. -
Plants should be well
maintained to prevent dark smoke and oil leakage. Idle plant should be turned
off. -
Drip tray should be
provided for all chemical and stationary plants. -
No construction works
shall be carried out in restricted hours (7:00 pm to 7:00 am) unless CNP is
obtained. -
Erect noise screen
along site boundary. -
Waste should be
sorted and dispose according to the Waste Management Plan -
No direct discharge
of wastewater into storm drains is allowed. Wastewater must be de-silted
before discharged in accordance with the water discharge license. -
Dull green barrier
and ecological measures should be implemented according to the Ecological
protection plan. |
(b) Backfilling |
Portion 4, 7, 8 |
Air, Noise, Waste |
||
(c)
Concreting |
Portions 7, 8, 9 & 10 |
Air, Noise, Water, Waste, Ecology |
||
(d) Bedding & Pipe Laying |
Portion 3, 4 |
Air, Noise, Water, Waste, Ecology |
||
(e)
ELS |
Portions 1, 4, 5 |
Air, Noise, Water, Waste, Ecology |
||
(f)
Sheet Pile Removal |
NIL |
Air, Noise, Water, Waste |
||
(g) Cut and Fill of Slope |
Portion 3, 4 |
Air, Noise, Water, Waste |
||
(h)
Sheet pile installation |
Portion 1, 4 |
|||
ND/2019/03 |
(a)
Excavation
& ELS |
Portion 1, 1A, 2, 3, 4,
4A, 4B, 5, 5A |
-
Waste -
Air pollution -
Noise pollution |
-
Dusty works should be
sprayed with water or stockpile should be covered by Tarpaulin properly. -
Plants should have
maintenance to prevent dark smoke and oil leakage. Idle plant should be
turned off. -
Drip tray should be
provided for all chemical and stationary plants. -
No construction works
shall be carried out in restricted hours (7:00 pm to 7:00 am) unless CNP is
granted. -
Waste should be sorted
and disposed according to Waste Management Plan. -
No direct discharge of
wastewater into storm water drains is allowed. Wastewater must be desilted
before discharging according to water discharge license. |
(b)
Site
Clearance |
Sections 7, 8 and 9 |
-
Waste -
Air pollution -
Noise pollution |
||
(c)
Tree
Felling |
Sections 6, 7, 8 and 9 |
-
Waste -
Air pollution -
Noise pollution |
||
ND/2019/04 |
(a)
Sheet piling |
A2-03, Portion J, K and Footbridge
F4 |
-
Air, Noise, Waste |
-
Dusty works should be
sprayed with water or stockpile should be covered by tarpaulin properly. -
Plants should have
maintenance to prevent dark smoke and oil leakage. Idle plant should be
turned off. -
Drip tray should be
provided for all chemical and stationary plants. -
No construction works
shall be carried out in restricted hours (7:00 pm to 7:00 am) unless CNP is
granted. -
Waste should be sorted
and disposed according to Waste Management Plan. -
No direct discharge of
wastewater into storm water drains is allowed. Wastewater must be desilted
before discharging according to water discharge license. |
(b)
Pile cap |
Bridge A1, A3 and Portion
J, K |
-
Air, Noise, Water, Waste |
||
(c)
Grouting |
Bridge F, A2, A3 and Portion J, K, H |
-
Air, Noise, Water, Waste |
||
(d)
Bore pile |
Bridge G and Footbridge F4 |
-
Air, Noise, Water, Waste |
||
(e)
Excavation & ELS |
Portion J, H, K, X, S, Bridge
A1, A2 and A3 |
-
Air, Noise, Waste |
||
(f)
Road works |
Portion J, H, O, U and VY |
-
Air, Noise, Waste |
||
(g)
Pre-drilling |
NIL |
-
Air, Noise, Water, Waste |
||
(h)
Tree pruning |
Portion K |
-
Air, Noise, Waste |
||
(i)
UU diversion |
Portion J and K |
-
Air, Noise, Waste |
||
ND/2019/05 |
(a)
ELS & Pile Cap
Construction |
NB69 Bay 2~8 NB110 Bay 6~7 |
-
Construction Dust Impact -
Noise Impact -
Water Quality Impact (Construction Phase) -
Waste Management (Construction Waste) -
Landscape and Visual -
Cultural Heritage |
Regular watering on exposed worksites and haul road. -
Stockpiling area should
be provided with covers and water spraying system. -
Only well
maintained plant to be operated on site. -
plant known to emit
noise strongly in one direction, where possible, be orientated so that the
noise is directed away from nearby NSRs. -
mobile plant to be sited
as far away from NSRs as possible practicable. -
All open stockpiles of
construction materials of more than 50m3 to be cove red with tarpaulin. -
Manholes to be
adequately covered and temporarily sealed so as to
prevent silt, construction materials or debris being washed into the drainage
system. -
All vehicles and plant
to be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads. -
Segregate and store
different types of waste in different containers, skip or stockpiles to
enhance reuse or recycling of materials and their proper disposal. -
Sort out demolition
debris and ex cavated materials from demolition
works to recover reusable/recyclable portions. -
Provide training to
workers on appropriate waste management procedures, including waste
reduction, reuse and recycling. -
To adopt other good site
practice, such as arrangements for collection and effective disposal to an
appropriate facility, of all wastes generated at the site and regular
cleaning and maintenance programme for drainage. -
Chemical wastes to be
stored in appropriate containers and collected by a licensed chemical waste
Contractor. Chemical wastes (e.g. spent lubricant oil) should be recycled at
an appropriate facility as far as possible, while the chemical waste that ca nnot be recycled should be disposed of at either the
Chemical Waste Treatment Centre, or another licensed facility, in accordance
with the Waste Disposal (Chemical Waste) (General) Regulation. -
Conducting Construction
Vibration Monitoring -
Tree Protection &
Preservation Exiting trees to be retained within the Project Site should be
carefully protected during construction. In particular OVTs
will be preserved according to ETWB Technical Circular (Works) No. 29/2004. -
Tree Transplantation
Trees unavoidably affected by the Project works should be transplanted where
practical. Trees should be transplanted straight to their final receptor site
and not held in a temporary nursery as far as possible. -
Erect 2m high dull green
site boundary fence. |
(b)
Cap
Construction |
E3-04a, E3-04b, E4-01 and E4-02 |
|||
(c)
Cross head construction |
B2-01, B2-02 and B2-03 |
|||
(d)
Pier
/ Pier head Construction |
D2-01 and E305M |
|||
(e)
Fabrication
for segment |
C2, C1, D1, D2, E1, E4 |
|||
(f)
Form
Traveler |
E3-01 construction 3rd to 6th
pair E2-02 construction 14th pair &
dismantling of FT1 D2-02 construction 6th to 8th
pair D2-03 construction 2nd pair to 4th
pair E2-01 erection of 5th set of form traveler. |
|||
(g) Segment Erection by
Launching Girder & Crane |
bridges C3, C2 |
|||
(h)
SOP construction
(precast & in-situ cast in type) |
D2-01 |
|||
(i)
Road
construction |
TWSRW, TWSRE |
|||
(j)
Road
works |
Jockey Club Rd, TWSRW |
|||
(k) Base slab construction |
NB109 ¡V bay 11~12 |
|||
(l)
Tree
Works |
All works areas |
|||
|
|
|||
ND/2019/06 |
N/A |
N/A |
N/A |
N/A |
ND/2019/07 |
(a)
Road works |
Portion 1, 4, 5 |
-
Construction Dust Impact -
Noise Impact -
Water Quality Impact (Construction Phase) -
Waste Management (Construction Waste) -
Landscape and Visual |
-
Regular watering on
exposed worksites and haul road. -
Stockpiling area should
be provided with covers and water spraying system. -
Only well-maintained
plant to be operated on-site. -
plant known to emit
noise strongly in one direction, where possible, be orientated so that the
noise is directed away from nearby NSRs. -
mobile plant to be sited
as far away from NSRs as possible practicable. -
All open stockpiles of
construction materials of more than 50m3 to be covered with tarpaulin. -
Manholes to be
adequately covered and temporarily sealed so as to
prevent silt, construction materials or debris being washed into the drainage
system. -
All vehicles and plant
to be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads. -
Segregate and store
different types of waste in different containers, skip or stockpiles to
enhance reuse or recycling of materials and their proper disposal. -
Sort out demolition
debris and excavated materials from demolition works to recover
reusable/recyclable portions. -
Provide training to
workers on appropriate waste management procedures, including waste
reduction, reuse and recycling. -
To adopt other good site
practice, such as arrangements for collection and effective disposal to an
appropriate facility, of all wastes generated at the site and regular
cleaning and maintenance programme for drainage. -
Chemical wastes to be
stored in appropriate containers and collected by a licensed chemical waste
Contractor. Chemical wastes (e.g. spent lubricant oil) should be recycled at
an appropriate facility as far as possible, while the chemical waste that
cannot be recycled should be disposed of at either the Chemical Waste
Treatment Centre, or another licensed facility, in accordance with the Waste
Disposal (Chemical Waste) (General) Regulation. -
Tree Protection &
Preservation ¡V Exiting trees to be retained within the Project Site should be
carefully protected during construction. In particular OVTs
will be preserved according to ETWB Technical Circular (Works) No. 29/2004. -
Tree Transplantation ¡V
Trees unavoidably affected by the Project works should be transplanted where
practical. Trees should be transplanted straight to their final receptor site
and not held in a temporary nursery as far as possible. -
Erect 2m high dull green
site boundary fence. -
Light Control ¡V Construction day and night time lighting should be
controlled to minimize glare impact to adjacent VSRs during the Construction
phase. |
(b) C&D waste disposal |
Portion 1, 2, 4, 5 |
|||
(c)
Construction of box
culvert |
Portions 2 |
|||
(d) Filling works |
Portions 1, 2, 4 |
|||
(e)
Construction of site
haul road |
Portions 4 |
|||
(f)
Drainage Works |
Portion 2, 3, 4 |
|||
(g) Sewerage works |
Portion 3, 4 |
|||
(h) Construction of Noise Barrier |
Portion 5 |
|||
(i)
Waterworks |