Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (February 2024) |
ND/2019/01 |
(a)
Drainage
works, watermain works and sheet piles in Portion 1a (b)
Site
formation, erection of hoarding and construction of noise barrier in Portion
1c (c)
Sheet
piling, site clearance, site formation, construction of subway, drainage
works and road works in Portion 2 (d)
Watermain
works in Portion 3 (e)
Site
formation and excavation in Portion 5 (f)
Backfilling,
drainage works, watermain works and district cooling system in Portion 6a (g)
Operation
of HAC treatment facility in Portion 6b (h)
Excavation
and drainage works in Portion 7 (i)
RC
construction of fresh water reservoir, drainage works, backfilling works and construction
of receiving pit in Portion 8a (j)
Trenchless
work and watermain construction in Portion 8b (k)
Sheet
piling, excavation, drainage, watermain works and district cooling system in
Portion 9b (l)
Removal of existing structure in Portion 11b (m)
Site clearance, removal of existing structures, site formation and
erection of hoarding in Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry agricultural land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Dry Weather Flow Interception (DWFI) -
Construction of Car Park and Farmer¡¦s Forum |
ND/2019/04 |
(a)
Pile Cap (b)
Back Filling (c)
Excavation (d)
Grouting (e)
Sheet Piling (f)
Road works (g)
Formwork and Scaffolding Erection (h)
Rebar Fixing (i)
Bore pile (j)
ELS |
ND/2019/05 |
(a)
South Team -
E3-05M ¡V Pier head construction completed. -
E3-04a ¡V Column construction completed. -
E3-04b ¡V Pile cap completed. -
E4-01 ¡V Pile cap completed. -
E4-02 ¡V Pipe pile wall in progress. -
E4-03 ¡V Pipe
pile wall in progress -
Works in TWSRE A. BBI
cover walkway (Steelwork) ¡V 1st stage completed. B. Extension
of HKY Footbridge ¡V Temporarily opened to public. C. BBI
Toilet ¡V Base slab was casted. Wall construction is in progress. D. Connecting
Road L201 to D300 ¡V Drainage and Kerb construction completed. E. D400
Road Works CH285 to 380 ¡V Backfilled to formation. Subbase in progress. -
Works in TWSRW A. FS04 ¡V Middle berm and U-channel construction completed. Rock slope
strengthening works in progress. B. 11kv
cable laying (near HKY entrance) in progress. C. Drainage
work ¡V Laying 2x1200Dia Pipes to Manhole (FL9110) completed. D. Sewerage
work ¡V Laying 600Dia pipes from FW06 toward FS04 is in progress. E. Gas Pipe
laying (IPA400/HP600 ¡V near HKY entrance) in progress. F. 1st
stage fresh watermain diversion completed on 2 February 2024 by WSD. G. Lift
LT02 ¡V Piling works completed. Loading test will be completed on 9 February
2024. -
Noise barrier NB109 A. Bay 10 ¡V Top wall completed. B. Bay 9, 11 ¡V Top wall in progress. C. Bay 11, 12 ¡V Backfilling in progress. D. Bay 13 ¡V ELS in progress. -
Noise barrier NB69 A.
Bay 5, Bay 6 ¡V Top wall completed. Backfilling in progress. B.
Bay 2, Bay 3 ¡V ELS is in progress. C.
Bay 6, Bay 7, Bay 8 ¡V ELS is in progress. -
Noise barrier NB110 A.
Bay 3 to 5 - Backfilling reached formation. B.
Bay 6, 7 ¡V Removal of existing DS64 footing and uncharted high mass
footing in progress. C.
Bay 8, 9 ¡V Wall completed. -
Noise barrier NB 29 A.
Bay 12, 13 ¡V Footing construction in progress. (b)
North Team -
C2-01
crosshead completed. -
Concreting
for 1st pour of C1-02 portal beam construction completed. -
Soffit
formwork erection for C1-01 MJ portal construction in completed. -
Falsework
erection for B2-01, B2-02 & B2-03 cross head construction in progress. -
Construction
of remaining abutment wall near B1-02 portal beam was in progress. -
Backfilling
at C3-03a, C3-04a, C4-02, C4-01b were in progress -
Permanent
reinstatement of footpath near C4-01a completed and opened to public on 19
Jan 23. -
On Kui
Street ¡V Construction of manhole & associated DN 900 drain pipe were in progress. -
JCR:
Construction of new central median & ducting works for traffic signal
& road light were in progress. -
JCR:
Construction of pipe support for DN 150 exposed pipe in progress. Trench
excavation for WSD were completed and backfilling after WSD works in
progress. -
JCR &
Tong Hang Village J/O improvement works: Construction of box-culvert &
extension head wall was in progress. -
Sampling of existing pavement in southbound of
Jockey Club Rd for CSD. (c)
Bridges and Structures -
Total 791 segments were casted in Huizhou
casting yard. -
Total 552 segments were delivered to site, and
total 502 segments erected. -
C2-03 segment erection by LG in progress. -
Soffit formwork
erection for in-situ construction of Bridge B1 is in progress. -
Trial panel for type
C segment is completed. -
Fabrication of parapet skin commenced at ShenZhen casting yard, total 175 pieces parapet skin
fabricated. 23 pieces of parapet skin erected on Bridge E1. -
Construction of D2-01 SOP in progress. (d)
Form Traveler -
T-Span at E3-01 completed. -
Form traveler launching for 10th pair segment at D2-02 in
progress. -
Form traveler launching for 07th pair segment at D2-03 in
progress -
Form traveler launching for 05th pair segment at E2-01 in
progress. -
Form traveler rebar fixing (DN) for 1st pair segment at E2-03
in progress. -
FT01 dismantling at E2-02 completed & -
Completed concreting E2 E2 01 E2 02 S03, E2 E2 01 E1 04 01 S03. E2 E2 01 E2
02 S04, E2 E2 01 E1 04 01 S04. -
Completed concreting D2 D2 02 D2 03 S09, D2 D2 02 D2 01 S09, D2 D2 02 D2 03
S10, D2 D2 02 D2 01 S10. -
Completed concreting D2 D2 03 D2 04 S05, D2 D2 03 D2 02 S05, D2 D2 03 D2 04
S06, D2 D2 03 D2 02 S06. -
Completed concreting E3 E3 01 E2 03 S06
& E3 E3 01 E3 02 S06, E2 E2
03 E3 01 S01 |
ND/2019/06 |
The
construction phase was completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road
works at Portion 1, 4 and 5 (b)
C&D
waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at Portion 2, 3, 4
and 5 (d)
Construction of box culvert at Portion 2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at Portion 4 (g)
Waterworks at Portion 1, 2 and 4 |