2.1
The Kwu
Tung North (KTN) and Fanling North (FLN) New
Development Areas (NDAs) are one of the important sources of land and housing
supply in the medium and long term. The development of the KTN and FLN NDAs
will be implemented in phase for full completion by 2031. The Phase 1 of the
NDAs development, comprising the Advance Works and First Stage Works, is
targeted to be implemented from the second half of 2019 progressively. The
Advance and First Stage Works would include site formation, engineering
infrastructure works (including roads, drainage, sewerage, waterworks,
landscaping works, pumping stations, and fresh water and flushing water service
reservoirs), soil remediation, reprovisioning of North District Temporary
Wholesale Market, development of a nature park at Long Valley and
implementation of environmental mitigation measures.
2.2
The scope of works under the Advance
and First Stage Works comprises the following:
a)
The Advance Works (PWP item No.
7747CL-2) consist of:
i)
site formation of land (including
soil remediation) in KTN and FLN NDAs for housing, community facilities and
engineering infrastructure;
ii)
construction of roads including the
eastern section of Fanling Bypass (FLBP(E))
connecting the FLN NDA to Fanling Highway and other
roads with footpaths and cycle tracks, and associated junction/ road
improvements;
iii)
engineering infrastructure works
including drainage. Sewerage (including two sewage
pumping stations), waterworks (including a fresh water service reservoir and a
flushing water service reservoir in the KTN NDA), landscape works and slopeworks;
iv)
part expansion and upgrading of Shek
Wu Hui Sewage Treatment Works (SWHSTW);
v)
reprovisioning works; and
vi)
implementation of environmental
mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in (i)
to (v) above.
b)
The First Stage Works (PWP item No.
7759CL) consist of:
i)
development of a nature park at Long
Valley including provision of a visitor centre and a
footbridge spanning across Sheung Yue River for connection between these two
facilities;
ii)
reprovisioning of two egretry sites in the FLN NDA and enhancement works to an
existing egretry site in the KTN NDA;
iii)
site formation of land for a village
resite area and a district
police station in the KTN NDA;
iv)
engineering infrastructure works
including roads, drainage, sewerage, waterbirds, and landscape works; and
v)
implementation of environmental
mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in (i)
to (iv) above.
2.3
The Project which covers KTN and FLN
NDAs is a designated project (DP) under Schedule 3 of the Environmental Impact
Assessment (EIA) Ordinance (Cap. 499). In October 2013, the EIA Report
(AEIAR-175/2013) for the Project was approved by the Director of Environmental
Protection pursuant to the EIA Ordinance. The relevant EPs under the Project
and the respective Work Contracts are summarised
in Tables 2.1a
and
2.1.b.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP No. |
Designated Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle
Peak Road Diversion |
ü |
¡@ |
|||||||
Kwu Tung North New Development
Area Road P1 and P2 and Associated New Kwu Tung
Interchange and Pak Shek Au Interchange Improvement |
ü |
¡@ |
|||||||
Kwu Tung North New Development
Area Road D1 to D5 |
ü |
ü |
¡@ |
||||||
Sewage
Pumping Stations in Kwu Tung North New Development
Area |
ü |
¡@ |
|||||||
Utilization
of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
|||||||
Fanling Bypass Eastern Section |
ü |
ü |
ü |
¡@ |
|||||
Reprovision
of temporary Wholesale Market in Fanling North New
Development Area |
ü |
¡@ |
|||||||
EP-546/2017 |
Fanling North Temporary Sewage Pumping
Station |
ü |
¡@ |
Notes:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope
of Works under concerned EP
Environmental Permit (EP) No. |
Work Contract(s) |
Scope of Works under
concerned EP(s) |
Site Layout Plan under
concerned EP(s) |
EP-466/2013/A(Part) |
C1 |
Realign Castle Peak
Road and join with the Pak Shek Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction of new
primary distributor road (P1) within Kwu Tung North
New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction of new
primary distributor roads (D1, D3, D4 and part of D5) within Kwu Tung North New Development Area |
Figure 14 |
C3 |
Development of a nature
park at Long Valley and ecological mitigation and enhancement works for the
nature park (Condition 2.9) |
Figure 15 |
|
EP-469/2013(Part) |
C2 |
Construction of one
sewage pumping station in Kwu Tung North with
installed capacity of more than 2,000 m3 per day |
Figure 16 |
EP-470/2013/A(Part) |
C1 |
Construction of service
reservoir and watermain for the reuse of treated sewage effluent for reuse in
Kwu Tung North Development Areas |
Figure 17 |
EP-473/2013/A(Part) |
C3 |
Establishment of alternative egretry sites
and enhance the existing egretry site at Ho Sheung Heung and/or its vicinity
(Condition 2.7) |
Figure 18 |
EP-473/2013/A(Part) |
C5A |
Construction of new
district distributor inside FLN NDA, which provides a linkage between the Man
Kam To Road and the proposed Fanling
Bypass Eastern Section |
Figure 19 |
EP-473/2013/A(Part) |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The re-provisioned
wholesale market will have approximately 1,000 market stalls within a site
area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a
temporary sewage pumping station in Fanling North
with installed capacity (average dry weather flow) of about 3,600m3/day |
Figure 22 |
Remark: The EP(s) not
related to the Project of the First Phase of the Kwu
Tung North (KTN) and Fanling North (FLN) New
Development Area (NDA) Development Areas are not included in the Table.
2.4
The site boundary of the Project and
all Works Contracts are shown in Drawing
No. 1.
2.5
The required submissions and
submission status under Environmental Permits are shown in Appendix U.
2.6
The site layout plans under concerned Environmental
Permits are shown in Figures 12 - 22.
2.7
Different parties with different
levels of involvement in the Project organisation
include:
Project Proponent ¡V Civil
Engineering and Development Department (CEDD)
Supervisor
/ Supervisor's Representative ¡V AECOM Asia Co. Ltd.
Environmental Team (ET) ¡V Wellab Limited
Independent Environmental Checker (IEC) ¡V Mott MacDonald
Hong Kong Ltd (MottMac)
2.8
The names and contact numbers of
key
personnel are summarised in Table 2.2.
Table 2.2 Key Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
Civil
Engineering and Development Department, HKSAR (CEDD) |
Project Proponent |
Mr.
Ryan Chau |
3797
5387 |
3547 1658 |
Supervisor / Supervisor's Representative (AECOM
Asia Co. Ltd.) |
Chief
Resident Engineer |
Mr.
Alan Lee |
6398 5982 |
2680 9515 |
Senior Resident Engineer |
Mr. King-man Chan |
9651 2635 |
2680 9515 |
|
Environmental
Team (Wellab Limited) |
Environmental Team Leader |
Dr.
Priscilla Choy |
2898 7388 |
2898
7076 |
Independent
Environmental Checker (MottMac) |
Independent
Environmental Checker |
Mr.
Thomas Chan |
2828
5967 |
2827
1823 |
Contract No. ND/2019/01 Contractor (Build King
¡V Richwell Engineering Joint Venture) |
Site
Agent |
Mr.
Ivan Leung |
9640 8340 |
-- |
Environmental
Officer |
Mr.
Edward Tam |
9287 8270 |
||
Contract No. ND/2019/02 Contractor (Chun Wo ¡V
Kwan Lee Joint Venture.) |
Site
Agent |
Mr.
Andy Chan |
3485 9780 |
-- |
Environmental
Officer |
Mr. Sofi So |
9637 1667 |
||
Contract No. ND/2019/03 Contractor (Sang Hing Kuly Joint Venture) |
Site
Agent |
Mr.
Tang Wing Kai |
9300 7037 |
-- |
Environmental
Officer |
Mr.
Ken Cheung |
9803
5297 |
||
Contract No. ND/2019/04 Contractor (Daewoo ¡V
Chun Wo ¡V Kwan Lee Joint Venture) |
Site
Agent |
Mr.
Eric Wu |
9786
8630 |
-- |
Environmental
Officer |
Mr.
Sam Lam |
6178
3179 |
||
Contract No. ND/2019/05 Contractor (CRCC ¡V
Paul Y. Joint Venture) |
Site
Agent |
Mr.
Darvin Lo |
9467
5891 |
-- |
Environmental
Manager |
Mr.
Pan Fong |
9436
9435 |
||
Environmental
Officer |
Mr.
Kevin Cheung |
6117
1344 |
||
Contract No. ND/2019/06 Contractor (New
Concepts Engineering Development Ltd.) |
Project
Manager |
Mr. Joe Cheng |
9861 0060 |
-- |
Environmental
Officer |
Mr.
Alex Choy |
6360
3236 |
||
Contract No. ND/2019/07 Contractor (China Road
and Bridge Corporation) |
Site
Agent |
Mr.
Mac Chow |
9169
9567 |
-- |
Environmental
Manager |
Mr.
K. M. Lui |
5113
8223 |
||
Environmental
Officer |
Ms. Sedo Sze |
5111
8018 |
2.9
The major site activities undertaken
in the reporting month are shown in Table
2.3.
Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract No. |
Site Activities (December 2024) |
ND/2019/01 |
(a)
Drainage works, watermain works, sheet piling and slope works in Portion 1a (b)
Site formation, watermain works and construction of noise barrier in Portion 1c (c)
Site formation, construction of subway, drainage works, road works, slope works and soil nail in Portion 2 (d)
HAC
soil treatment, watermain works,
drainage works and
sheet piles in Portion 3 (e)
Site formation, watermain works, drainage works and
sewage works in Portion 5 (f)
Backfilling, drainage works, watermain works,
slope works, road works, district cooling system,
and road light works in Portion 6a (g)
Operation of HAC soil treatment facility in Portion 6b (h)
Excavation, watermain works, sewage works,
road works and drainage works in Portion 7 (i)
Road
pavement construction, RC construction of fresh
water service reservoir, drainage works, watermain works and backfilling works in Portion 8a (j)
Trenchless work, watermain construction, ELS construction and ground treatment
works in Portion 8b (k)
Sheet piling, excavation, drainage, watermain works and district
cooling system in Portion 9b (l)
No
activity in Portion 11b this month (m) Stockpile of soil in Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying
and bedding (h)
Grouting |
ND/2019/03 |
(a)
Portion 2 to Portion 20C -
Wetland creation &
restoration, Dry agricultural land creation -
Construction of Water
Treatment Wetland |
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding
Erection (f)
Rebar Fixing (g)
ELS |
ND/2019/05 |
(a)
South Team -
BBI Toilet ¡V Roof
construction is in progress and target to complete in 16 December 2024. -
Lift LT01 ¡V Installation
of louvre and glasses completed. Installation of E&M items in progress.
OTIS will commence lift installation in end of Dec 2024. -
Lift LT02 ¡V Lift shaft
in progress. -
Sign Gantry DS20 ¡V Pile
cap completed on 12 November 2024. -
FW54 ¡V ELS in progress.
Footing target to complete by end of December 2024. -
E4 Retaining Wall ¡V Base
slab completed on 29 November 2024. -
E4 Ramp Utrough ¡V Bay 17-18 excavation in progress. -
D2-03 Drainage
Reinstatement ¡V Excavation in progress. Target to complete by end of December
2024. -
Noise barrier NB109 A.
Bay 14 ¡V Wall
construction in progress. Target to complete on 10 December 2024. B.
Bay 15, 16 ¡V ELS completed.
Footing target to completed in 31 December 2024. C.
Bay 1 to 4 ¡V Partially
completed. TTA-423 implemented on 7 December 2024. -
Noise barrier NB70 A.
Bay 2, 4 ¡V Stem wall
completed 4 December 2024. B.
Bay 3 ¡V Footing
completed on 3 December 2024. Wall construction in progress. C.
Bay 1 ¡V Plate Load Test
will complete on 13 December 2024. -
Noise barrier NB69 A.
Bay 1, 2 ¡V Bay 2b wall
construction to be resumed after Bridge E4 segment erection. -
Noise barrier NB110 A.
Bay 10 ¡V Pile caps PC1
and PC2 target to complete on 12 December 2024. -
Noise barrier NB
29 Through Bay 6-15 A.
Footing is 100%
completed B.
Wall (exclude parapet)
is 80% completed. Parapet section will cast after backfilling to formation. -
Noise
barrier NB 30 A.
NB30 Predrilling works
(17/28 nos) completed. B.
Pre-bored Socket H pile
construction (25/220 nos) completed. -
Noise
barrier NB 77 A.
Pre-bored Socket H pile
construction (5/16 nos)
completed. (b)
North Team -
Dismantling of truss at B2-01 cross head in progress. -
Rebar fixing for B1abutment wall in progress. -
Reinstatement works & footpath in progress in C4-02 (HD) -
C3-03b & C3-04b for viaduct drainage & water works in progress -
Backfilling of C3-04a, C2-01, C1-02a & C1-02b in progress. -
JCR: Construction of new central median & ducting works for
traffic signal & road light were completed of 90%. -
JCR & Tong Hang Village J/O improvement works (FS 25): slope works
90 % completed. -
JCR & Tong Hang Village J/O (near bus-stop) :
Ducting works for traffic signal & road light was in progress ( 95 %
completed). -
JCR near F63 ¡V Breaking of temporary pavement was in progress. (c)
Bridges and Structures -
All 116 Type C segments
casted in DongGuan Casting yard. -
All Type A segment
fabrication completed. Total 780 segments were delivered to site, and total
774 segments erected. -
B2-02 & B2-03 T-span
segment erection by LG completed, and C1-01M End-span segment erection in
progress. -
Total 1280 pcs of
parapet-skin fabricated; 1080 pcs of parapet skin erected. -
Installation of deck void
drainage at Bridge C2 in progress. -
Segment erection at Bridge
E4 completed. -
Bridge rotation at
D2-01completed. -
Reinstate of lifting tower
NF83A in progress. -
D2-04 end span segment
erection in progress. (d)
Form Traveler -
Form traveller
at 6th
pair segment at E3-04 in progress. -
Form traveller
at 8th
pair segment at D2-01 in progress -
Mid stitching between
E2-01 & E2-02 in progress. -
Mid stitching between
E3-02 & E3-01 completed. -
Dismantling of form traveller at E3-02 in progress -
Completed concreting
E3-E3-04-E3-03-S04 & E3-E3-04-E3-05-S04, E3-E3-04-E3-03-S05 &
E3-E3-04-E3-05-S05. |
ND/2019/06 |
The construction phase was completed and
handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2
and 4 (c)
Drainage works, Sewerage
works at Portion 1, 2, 3
and 4 (d)
Filling works at Portion
2 and 4 (e)
Construction of site
haul road at Portion 4 (f)
Waterworks at Portion 1,
2 and 4 (g)
Construction
of noise barrier at Portion 4 |
2.10 Copies of Contractors¡¦ construction programmes are provided in Appendix A.
2.11
A summary of the relevant permits, licences, and/or notifications on environmental protection
for this Project is presented in Table
2.4.
Table 2.4 Status of Environmental Licences, Notifications and Permits