Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (January to March 2025)

ND/2019/01

(a)          Drainage works, watermain works, sheet piling, site formation and slope works in Portion 1a

(b)         Site formation, drainage works, watermain works and construction of noise barrier and road lighting works in Portion 1c

(c)          Site formation, construction of subway, road works, drainage works, slope works and soil nail in Portion 2

(d)         HAC soil treatment, site formation, excavation, road works, slope work, drainage works, watermain works and soil nail in Portion 3

(e)          Sewage works, excavation, backfilling, road works and construction of public lighting in Portion 5

(f)          Drainage works, backfilling, road works, watermains works, construction of retaining wall, slope works, district cooling system works and road lighting works in Portion 6a

(g)         Operation of HAC treatment facility in Portion 6b

(h)         Sheet piling, excavation, stockpile of soil, drainage works, watermain works and road works in Portion 7

(i)           Road pavement construction, backfilling works, drainage works, watermain works and soil nail in Portion 8a

(j)           Trenchless works, watermain works, ground treatment and ELS construction in Portion 8b

(k)         Sheet piling, excavation, road works, drainage works, watermain works, district cooling system works and grouting works in Portion 9b

(l)           Sewage works, drainage works, road works, backfilling, excavation and sheet piling in Portion 10b

(m)       Site formation, excavation, drainage works, roadworks and watermain works in Portion 11b

(n)         Stockpile of soil in Portion 13

ND/2019/02

(a)            Backfilling

(b)           Excavation

(c)            Concreting

(d)           Cut and Fill of Slope

(e)            Sheet Piling

(f)            Pipe Jacking

(g)           Pipe laying and bedding

(h)           Grouting

ND/2019/03

(a)      Portion 2 to Portion 20C

-          Defect Rectification of Lodging Facility

ND/2019/04

(a)           Back Filling

(b)           Excavation

(c)           Grouting

(d)           Road works

(e)           Formwork and Scaffolding Erection

(f)            Rebar Fixing

(g)           ELS

ND/2019/05

(a)        Backfilling

(b)       Drainage works

(c)        Water works

(d)       Ducting and Road works

(e)        Slope works

(f)        Segments erection

(g)       ELS

(h)       Wall construction

ND/2019/06

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 1, 4 and 5

(b)        C&D waste disposal at Portion 1, 2 and 4

(c)        Drainage works, Sewerage works at Portion 1, 2, 3 and 4

(d)        Filling works at Portion 2 and 4

(e)        Construction of site haul road at Portion 4

(f)         Waterworks at Portion 1, 2 and 4

(g)        Construction of noise barrier at Portion 4