Table IV Summary Table for Site Activities in the coming Three
Months
Contract No. |
Site Activities (January to March 2025) |
ND/2019/01 |
(a)
Drainage works, watermain works, sheet piling, site formation and slope works in Portion 1a (b)
Site formation,
drainage works, watermain works and construction of noise barrier and road lighting works in Portion 1c (c)
Site formation, construction of subway, road works, drainage works, slope works and soil nail in Portion 2 (d)
HAC
soil treatment, site formation, excavation, road works, slope work, drainage
works, watermain works and soil nail in Portion 3 (e)
Sewage
works, excavation, backfilling, road works and construction of public lighting in Portion 5 (f)
Drainage works, backfilling, road works, watermains works,
construction of retaining wall, slope works, district cooling system works
and road lighting works in Portion 6a (g)
Operation of HAC treatment facility in Portion 6b (h)
Sheet piling, excavation, stockpile of soil, drainage works, watermain works and road works in Portion 7 (i)
Road
pavement construction, backfilling works, drainage works, watermain works
and soil nail in Portion 8a (j)
Trenchless works, watermain works, ground treatment and ELS construction in Portion 8b (k)
Sheet piling, excavation, road works, drainage works, watermain works, district cooling system works and grouting works in Portion 9b (l)
Sewage
works, drainage works, road works, backfilling, excavation and sheet piling
in Portion 10b (m)
Site
formation, excavation, drainage works, roadworks and watermain works in
Portion 11b (n)
Stockpile of soil in Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
(a) Portion 2 to Portion 20C -
Defect
Rectification of Lodging Facility |
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding
Erection (f)
Rebar Fixing (g)
ELS |
ND/2019/05 |
(a)
Backfilling (b)
Drainage works (c)
Water works (d)
Ducting and Road works (e)
Slope works (f)
Segments erection (g)
ELS (h)
Wall construction |
ND/2019/06 |
The construction phase has been completed and handed over to AFCD since 4 April
2022. |
ND/2019/07 |
(a)
Road works at Portion 1,
4 and 5 (b)
C&D waste disposal
at Portion 1, 2 and 4 (c)
Drainage works, Sewerage
works at Portion 1, 2, 3
and 4 (d)
Filling works at Portion
2 and 4 (e)
Construction of site
haul road at Portion 4 (f)
Waterworks at Portion 1,
2 and 4 (g)
Construction of noise
barrier at Portion 4 |