Table 2.3 Summary Table for Major
Site Activities in the Reporting Month
Contract No. |
Site Activities (December 2024) |
ND/2019/01 |
(a)
Drainage works, watermain works, sheet piling and
slope works in Portion 1a (b)
Site formation,
watermain works and construction of noise barrier in Portion 1c (c)
Site formation, construction
of subway, drainage works, road works, slope works and soil nail in Portion 2 (d)
HAC
soil treatment, watermain works,
drainage works and sheet piles in Portion 3 (e)
Site formation,
watermain works, drainage works and sewage works in Portion 5 (f)
Backfilling, drainage works, watermain works, slope works, road works, district cooling system, and road light works in Portion 6a (g)
Operation of HAC
soil treatment facility in
Portion 6b (h)
Excavation, watermain
works, sewage works, road works and drainage works in Portion 7 (i)
Road
pavement construction, RC construction of fresh water service reservoir, drainage works, watermain works and backfilling works in Portion 8a (j)
Trenchless work,
watermain construction, ELS construction and ground treatment
works in Portion 8b (k)
Sheet piling, excavation, drainage, watermain works and district
cooling system in Portion 9b (l)
No
activity in Portion 11b this month (m)
Stockpile of soil in Portion 13 |
ND/2019/02 |
(a)
Backfilling (b)
Excavation (c)
Concreting (d)
Cut and Fill of Slope (e)
Sheet Piling (f)
Pipe
Jacking (g)
Pipe laying and bedding (h)
Grouting |
ND/2019/03 |
(a)
Portion 2 to Portion 20C - Wetland creation & restoration, Dry agricultural
land creation - Construction of Water Treatment Wetland |
ND/2019/04 |
(a)
Back Filling (b)
Excavation (c)
Grouting (d)
Road works (e)
Formwork and Scaffolding
Erection (f)
Rebar Fixing (g)
ELS |
ND/2019/05 |
(a)
South Team -
BBI Toilet ¡V Roof
construction is in progress and target to complete in 16 December 2024. -
Lift LT01 ¡V Installation
of louvre and glasses completed. Installation of E&M items in progress.
OTIS will commence lift installation in end of Dec 2024. -
Lift LT02 ¡V Lift shaft
in progress. -
Sign Gantry DS20 ¡V Pile
cap completed on 12 November 2024. -
FW54 ¡V ELS in progress.
Footing target to complete by end of December 2024. -
E4 Retaining Wall ¡V Base
slab completed on 29 November 2024. -
E4 Ramp Utrough ¡V Bay 17-18 excavation in progress. -
D2-03 Drainage
Reinstatement ¡V Excavation in progress. Target to complete by end of December
2024. -
Noise barrier NB109 A.
Bay 14 ¡V Wall
construction in progress. Target to complete on 10 December 2024. B.
Bay 15, 16 ¡V ELS completed.
Footing target to completed in 31 December 2024. C.
Bay 1 to 4 ¡V Partially
completed. TTA-423 implemented on 7 December 2024. -
Noise barrier NB70 A.
Bay 2, 4 ¡V Stem wall
completed 4 December 2024. B.
Bay 3 ¡V Footing
completed on 3 December 2024. Wall construction in progress. C.
Bay 1 ¡V Plate Load Test
will complete on 13 December 2024. -
Noise barrier NB69 A.
Bay 1, 2 ¡V Bay 2b wall
construction to be resumed after Bridge E4 segment erection. -
Noise barrier NB110 A.
Bay 10 ¡V Pile caps PC1
and PC2 target to complete on 12 December 2024. -
Noise barrier NB 29 Through Bay 6-15 A.
Footing is 100%
completed B.
Wall (exclude parapet)
is 80% completed. Parapet section will cast after backfilling to formation. -
Noise
barrier NB 30 A.
NB30 Predrilling works
(17/28 nos) completed. B.
Pre-bored Socket H pile
construction (25/220 nos) completed. -
Noise
barrier NB 77 A.
Pre-bored Socket H pile
construction (5/16 nos) completed. (b)
North Team -
Dismantling of truss at B2-01 cross head in progress. -
Rebar fixing for B1abutment wall in progress. -
Reinstatement works & footpath in progress in C4-02 (HD) -
C3-03b & C3-04b for viaduct drainage & water works in progress -
Backfilling of C3-04a, C2-01, C1-02a & C1-02b in progress. -
JCR: Construction of new central median & ducting works for
traffic signal & road light were completed of 90%. -
JCR & Tong Hang Village J/O improvement works (FS 25): slope works
90 % completed. -
JCR & Tong Hang Village J/O (near bus-stop) :
Ducting works for traffic signal & road light was in progress ( 95 %
completed). -
JCR near F63 ¡V Breaking of temporary pavement was in progress. (c)
Bridges and Structures -
All 116 Type C segments
casted in DongGuan Casting yard. -
All Type A segment
fabrication completed. Total 780 segments were delivered to site, and total
774 segments erected. -
B2-02 & B2-03 T-span
segment erection by LG completed, and C1-01M End-span segment erection in
progress. -
Total 1280 pcs of
parapet-skin fabricated; 1080 pcs of parapet skin erected. -
Installation of deck void
drainage at Bridge C2 in progress. -
Segment erection at Bridge
E4 completed. -
Bridge rotation at
D2-01completed. -
Reinstate of lifting tower
NF83A in progress. -
D2-04 end span segment
erection in progress. (d)
Form Traveler -
Form traveller
at 6th pair segment at E3-04 in
progress. -
Form traveller
at 8th pair segment at D2-01 in
progress -
Mid stitching between
E2-01 & E2-02 in progress. -
Mid stitching between
E3-02 & E3-01 completed. -
Dismantling of form traveller at E3-02 in progress -
Completed concreting
E3-E3-04-E3-03-S04 & E3-E3-04-E3-05-S04, E3-E3-04-E3-03-S05 &
E3-E3-04-E3-05-S05. |
ND/2019/06 |
The construction phase was
completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2 and 4 (c)
Drainage works, Sewerage
works at Portion 1, 2, 3
and 4 (d)
Filling works at Portion
2 and 4 (e)
Construction of site
haul road at Portion 4 (f)
Waterworks at Portion 1,
2 and 4 (g)
Construction
of noise barrier at Portion 4 |