Table 12.1 Summary Table for Site Activities, Potential
Environmental Impacts and Recommended Mitigation Measures in the Coming
Months
Contract No. |
Major Site Activities |
Location/ Working Period |
Potential Environmental
Impact |
Recommended Mitigation
Measures |
ND/2019/01 |
(a)
Excavation
/ Backfilling |
Portion 6a, 7, 8a, 9b |
- Construction Dust
impact - Noise Impact
(Construction Phase) - Water Quality Impact
(Construction Phase) - Waste Management
(Construction Waste) |
Air -
Watering
on exposed earth and haul road. -
Cover
the stockpiles or dusty materials. -
Deploy
water bowsers to water the haul road. -
Deploy
mist-cannon on site -
Provide
shelter with top and 3-sides for cement production activities. -
Cover
the Arsenic-containing soil. -
Store
the bulk cement in enclosed silo tank for soil treatment. -
Close
the mechanical cover of the vehicles used for transporting dusty materials. -
Establish
vehicle wheel washing facilities at vehicle exit points. -
Speed
control of site vehicles. Noise -
Regular
inspect of construction plants in good condition. -
Provide
temporary noise screens if necessary. -
Use
of Quiet plants (QPME) and working methods if possible. -
Sequencing
operation of construction plants where practicable. -
Shut
down the machines and plant if not in use. -
Only
well-maintained plant to be operated on-site -
Mobile
plant to be sited as far away from NSRs as possible practicable. -
Conduct
noise monitoring regularly. -
Erect
silent-up noise barrier at portion 6b.
Water -
Set
up wastewater treatment system (AquaSed) on site -
Erect
soil bund / temporary drain to divert /collect surface runoff. -
Maintain
the drainage and wastewater treatment facilities. Waste / Chemical
Management -
Sort
out demolition debris and excavated materials from demolition works to
recover reusable / recyclable portions -
Provide
recycling bins on site, encourage reuse and recycle as much as possible. -
Provide
drip trays for chemical containers. -
Chemical
spill kit available on site. -
Chemical
waste cabinet available on site. -
Chemical
wastes to be stored in appropriate containers and collected by a licensed
chemical waste collector. -
Delivery
of yard waste to tree shredding facility for upcycling. |
(b)
Site
formation |
Portion 1c, 2, 5 |
|||
(c)
Construction
of noise barrier |
Portion 1c |
|||
(d)
Construction
of subway |
Portion 2 |
|||
(e)
Sewage
Works |
Portion 5, 7 |
|||
(f)
RC
Construction of fresh water service reservoir |
Portion 8a |
|||
(g)
Construction
of receiving pit |
NIL |
|||
(h)
Operation
of HAC treatment facility |
Portion 3, 6b |
|||
(i)
Drainage
works / watermains works |
Portion 1a, 1c, 2, 3, 5, 6a, 7, 8a, 8b, 9b |
|||
(j)
Road
works/ Road pavement construction |
Portion 2, 6a, 7, 8a |
|||
(k)
Soil
nail / Slope works |
Portion 1a, 2, 6a |
|||
(l) Trenchless works |
Portion 8b |
|||
(m)
Ground
treatment |
Portion 8b |
|||
(n)
Sheet
piling/ ELS & pipe pile |
Portion 1a, 3, 8b, 9b |
|||
(o)
Stockpile
of soil |
Portion 13 |
|||
ND/2019/02 |
(a)
Pipe
Jacking |
Portions 2, 4 |
Air,
Noise, Waste |
-
Dusty works should be spray water. Idle stockpile
or slop should be covered by Tarpaulin sheet properly. -
Wheel washing should be carried out at every exit. -
Plants should be well maintained to prevent dark
smoke and oil leakage. Idle plant should be turned off. -
Drip tray should be provided for all chemical and
stationary plants. -
No construction works shall be carried out in
restricted hours (7:00 pm to 7:00 am) unless CNP is obtained. -
Erect noise screen along site boundary. -
Waste should be sorted and dispose according to
the Waste Management Plan -
No direct discharge of wastewater into storm
drains is allowed. Wastewater must be de-silted before discharged in
accordance with the water discharge license. -
Dull green barrier and ecological measures should
be implemented according to the Ecological protection plan. |
(b)
Backfilling |
Portion 10, 4, 8 |
Air,
Noise, Waste |
||
(c)
Concreting |
Portions 4, 8, 10 |
Air,
Noise, Water, Waste, Ecology |
||
(d)
Bedding
& Pipe Laying |
Portion 5, 6 |
Air,
Noise, Water, Waste, Ecology |
||
(e)
ELS |
Portions 4, 10 |
Air,
Noise, Water, Waste, Ecology |
||
(f)
Grouting |
Portion 6 |
Air,
Noise, Water |
||
(g)
Cut
and Fill of Slope |
Portion 4, 5 |
Air,
Noise, Water, Waste |
||
(h)
Sheet
pile installation |
Portion 4, 5 |
Air,
Noise, Water, Waste |
||
ND/2019/03 |
(a)
Excavation
& ELS |
Portion 1, 1A, 2, 3, 4,
4A, 4B, 5, 5A |
-
Waste -
Air
pollution -
Noise
pollution |
-
Dusty
works should be sprayed with water or stockpile should be covered by
Tarpaulin properly. -
Plants
should have maintenance to prevent dark smoke and oil leakage. Idle plant
should be turned off. -
Drip
tray should be provided for all chemical and stationary plants. -
No
construction works shall be carried out in restricted hours (7:00 pm to 7:00
am) unless CNP is granted. -
Waste
should be sorted and disposed according to Waste Management Plan. -
No
direct discharge of wastewater into storm water drains is allowed. Wastewater
must be desilted before discharging according to water discharge license. |
(b)
Site
Clearance |
Sections 7, 8 and 9 |
-
Waste -
Air
pollution -
Noise
pollution |
||
(c)
Tree
Felling |
Sections 6, 7, 8 and 9 |
-
Waste -
Air
pollution -
Noise
pollution |
||
ND/2019/04 |
(a)
Rebar
Fixing, formwork erection and scaffolding erection |
Bridge F, A1, A2, A3, Portion J, K, H, A, B |
-
Air,
Noise, Waste |
-
Dusty
works should be sprayed with water or stockpile should be covered by
tarpaulin properly. -
Plants
should have maintenance to prevent dark smoke and oil leakage. Idle plant
should be turned off. -
Drip
tray should be provided for all chemical and stationary plants. -
No
construction works shall be carried out in restricted hours (7:00 pm to 7:00
am) unless CNP is granted. -
Waste
should be sorted and disposed according to Waste Management Plan. -
No
direct discharge of wastewater into storm water drains is allowed. Wastewater
must be desilted before discharging according to water discharge license. |
(b)
Pile
cap |
Bridge G |
-
Air,
Noise, Water, Waste |
||
(c)
Grouting |
Bridge F, A1, A2, A3 and Portion J, K, H |
-
Air,
Noise, Water, Waste |
||
(d)
Sheet
piling removal |
NIL |
-
NIL |
||
(e)
Excavation
& ELS |
Portion A, B, J, K, H |
-
Air,
Noise, Waste |
||
(f)
Road
works |
Portion A, B, J, K, H |
-
Air,
Noise, Waste |
||
(g)
Pre-drilling |
NIL |
-
NIL |
||
(h)
Sheet
piling |
Bridge A1, A2 |
-
Air,
Noise, Waste |
||
(i)
UU
diversion |
Portion J and K |
-
Air,
Noise, Waste |
||
ND/2019/05 |
(a)
ELS
& Pile Cap Construction |
NB69 Bay 2~8 NB110 Bay 6~7 |
-
Construction
Dust Impact -
Noise
Impact -
Water
Quality Impact (Construction Phase) -
Waste
Management (Construction Waste) -
Landscape
and Visual -
Cultural
Heritage |
Regular watering on
exposed worksites and haul road. -
Stockpiling
area should be provided with covers and water spraying system. -
Only
well maintained plant to be operated on site. -
plant
known to emit noise strongly in one direction, where possible, be orientated
so that the noise is directed away from nearby NSRs. -
mobile
plant to be sited as far away from NSRs as possible practicable. -
All
open stockpiles of construction materials of more than 50m3 to be cove red
with tarpaulin. -
Manholes
to be adequately covered and temporarily sealed so as to prevent silt,
construction materials or debris being washed into the drainage system. -
All
vehicles and plant to be cleaned before leaving a construction site to ensure
no earth, mud, debris and the like is deposited by them on roads. -
Segregate
and store different types of waste in different containers, skip or
stockpiles to enhance reuse or recycling of materials and their proper
disposal. -
Sort
out demolition debris and ex cavated materials from demolition works to
recover reusable/recyclable portions. -
Provide
training to workers on appropriate waste management procedures, including
waste reduction, reuse and recycling. -
To
adopt other good site practice, such as arrangements for collection and
effective disposal to an appropriate facility, of all wastes generated at the
site and regular cleaning and maintenance programme for drainage. -
Chemical
wastes to be stored in appropriate containers and collected by a licensed
chemical waste Contractor. Chemical wastes (e.g. spent lubricant oil) should
be recycled at an appropriate facility as far as possible, while the chemical
waste that ca nnot be recycled should be disposed of at either the Chemical
Waste Treatment Centre, or another licensed facility, in accordance with the
Waste Disposal (Chemical Waste) (General) Regulation. -
Conducting
Construction Vibration Monitoring -
Tree
Protection & Preservation Exiting trees to be retained within the Project
Site should be carefully protected during construction. In particular OVTs
will be preserved according to ETWB Technical Circular (Works) No. 29/2004. -
Tree
Transplantation Trees unavoidably affected by the Project works should be
transplanted where practical. Trees should be transplanted straight to their
final receptor site and not held in a temporary nursery as far as possible. -
Erect
2m high dull green site boundary fence. |
(b)
Cap Construction |
E3-04a, E3-04b, E4-01 and E4-02 |
|||
(c)
Cross
head construction |
B2-01, B2-02 and B2-03 |
|||
(d) Pier
/ Pier head Construction |
D2-01 and E305M |
|||
(e)
Fabrication for segment |
C2, C1, D1, D2, E1, E4 |
|||
(f)
Form Traveler |
E3-01 construction 3rd to 6th
pair E2-02 construction 14th pair &
dismantling of FT1 D2-02 construction 6th to 8th
pair D2-03 construction 2nd pair to 4th
pair E2-01 erection of 5th set of form
traveler. |
|||
(g)
Segment Erection by Launching Girder & Crane |
Bridges C3, C2 |
|||
(h) SOP construction (precast
& in-situ cast in type) |
D2-01 |
|||
(i)
Road construction |
TWSRW, TWSRE |
|||
(j)
Road
works |
Jockey Club Rd, TWSRW |
|||
(k)
Base slab construction |
NB109 ¡V bay 11~12 |
|||
(l)
Tree Works |
All works areas |
|||
(m)
Drainage works |
On Kui Street |
|||
ND/2019/06 |
N/A |
N/A |
N/A |
N/A |
ND/2019/07 |
(a)
Road
works |
Portion 1, 4, 5 |
-
Construction
Dust Impact -
Noise
Impact -
Water
Quality Impact (Construction Phase) -
Waste
Management (Construction Waste) -
Landscape
and Visual |
-
Regular
watering on exposed worksites and haul road. -
Stockpiling
area should be provided with covers and water spraying system. -
Only
well-maintained plant to be operated on-site. -
plant
known to emit noise strongly in one direction, where possible, be orientated
so that the noise is directed away from nearby NSRs. -
mobile
plant to be sited as far away from NSRs as possible practicable. -
All
open stockpiles of construction materials of more than 50m3 to be covered
with tarpaulin. -
Manholes
to be adequately covered and temporarily sealed so as to prevent silt,
construction materials or debris being washed into the drainage system. -
All
vehicles and plant to be cleaned before leaving a construction site to ensure
no earth, mud, debris and the like is deposited by them on roads. -
Segregate
and store different types of waste in different containers, skip or
stockpiles to enhance reuse or recycling of materials and their proper
disposal. -
Sort
out demolition debris and excavated materials from demolition works to
recover reusable/recyclable portions. -
Provide
training to workers on appropriate waste management procedures, including
waste reduction, reuse and recycling. -
To
adopt other good site practice, such as arrangements for collection and
effective disposal to an appropriate facility, of all wastes generated at the
site and regular cleaning and maintenance programme for drainage. -
Chemical
wastes to be stored in appropriate containers and collected by a licensed
chemical waste Contractor. Chemical wastes (e.g. spent lubricant oil) should
be recycled at an appropriate facility as far as possible, while the chemical
waste that cannot be recycled should be disposed of at either the Chemical
Waste Treatment Centre, or another licensed facility, in accordance with the
Waste Disposal (Chemical Waste) (General) Regulation. -
Tree
Protection & Preservation ¡V Exiting trees to be retained within the
Project Site should be carefully protected during construction. In particular
OVTs will be preserved according to ETWB Technical Circular (Works) No.
29/2004. -
Tree
Transplantation ¡V Trees unavoidably affected by the Project works should be
transplanted where practical. Trees should be transplanted straight to their
final receptor site and not held in a temporary nursery as far as possible. -
Erect
2m high dull green site boundary fence. -
Light
Control ¡V Construction day and night time lighting should be controlled to
minimize glare impact to adjacent VSRs during the Construction phase. |
(b) C&D waste disposal |
Portion 1, 2, 4 |
|||
(c)
Filling
works |
Portions 2, 4 |
|||
(d) Construction of site haul
road |
Portions 4 |
|||
(e)
Drainage
Works |
Portion 1, 2, 3, 4 |
|||
(f)
Sewerage
works |
Portion 3, 4 |
|||
(g) Construction of Noise
Barrier |
Portion 4 |
|||
(h) Waterworks |
Portion 1, 2, 4 |
|||
|
|