11.1 One (1) Action Level and
Three (3) Limit Level for DO, Six (6) Limit Level for turbidity,
and Six (6) Limit Level for SS of impact water quality monitoring were
recorded. After investigation, all of the exceedance was considered due to the other
external factors rather than the contract works.
11.2 One
(1) Action Level for construction noise monitoring was recorded.
11.3 No Action/Limit Level exceedance for air
quality, ambient arsenic and landfill gas monitoring was recorded in the
reporting month. The summary of exceedance record in the reporting month is
shown in Appendix O.
11.4 Ecological monitoring was carried out in the reporting
month. Two (2) action level exceedance and one (1) limit level exceedance for
non-aquatic fauna were recorded at T3 and T6. The exceedances recorded were for
herpetofauna at T3 and T6, and for odonates at T3.
The exceedances were considered non-project related, as no evidence to suggest
that the exceedances were related to project activities, supported by
environmental monitoring data.
11.5 Should the monitoring results of the environmental
monitoring parameters at any designated monitoring stations indicate that
Action / Limit Levels are exceeded, the actions in accordance with the Event/Action
Plan in Appendix N would be carried
out.
11.6 No environmental non-compliance was recorded in the
reporting month.
11.7 Two (2) environmental complaints were received in the reporting month. The Cumulative Complaint Log since the
commencement of the Project is presented in Appendix S.
11.8
There was no
successful environmental prosecution or notification of summons received since
the Project commencement. The Cumulative Log for environmental summon and
successful prosecution since the commencement of the Project is presented in Appendix T.