Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site Activities (September to November 2024) |
ND/2019/01 |
(a)
Drainage works,
watermain works, sheet piling, site formation and slope works in Portion 1a (b)
Site
formation, drainage works, watermain works and construction of noise barrier in
Portion 1c (c)
Site
formation, construction of subway, road works, drainage works, slope works and soil nail in Portion 2 (d)
Site
formation, excavation, slope work, drainage and watermain works and soil nail in Portion
3 (e)
Watermain
works, drainage work, excavation, backfilling and road works
in Portion 5 (f)
Drainage
works, backfilling, road works, watermains works, construction of retaining wall and slope works in Portion 6a (g)
Operation
of HAC treatment facility in Portion 6b (h)
Sheet
piling, excavation, stockpile of soil, drainage works, watermain works and road works in Portion
7 (i)
RC
construction of fresh water reservoir, backfilling works, drainage works and watermain
works in Portion 8a (j)
Trenchless
work, excavation, watermain works, ground treatment and ELS construction in Portion
8b (k)
Sheet
piling, excavation, road works, drainage works, watermain works and district cooling system in Portion 9b (l)
Site formation, excavation, drainage works and
roadworks in Portion 11b (m)
Stockpile of soil in Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry agricultural land creation -
Construction of Water Treatment Wetland |
ND/2019/04 |
(a)
Pile Cap (b)
Back Filling (c)
Excavation (d)
Grouting (e)
Road works (f)
Formwork and Scaffolding Erection (g)
Rebar Fixing (h)
ELS (i)
Sheet Piling |
ND/2019/05 |
(a)
Backfilling (b)
Drainage works (c)
Water works (d)
Ducting and Road
works (e)
Bridge Rotation (f)
Slope works (g)
Segments erection (h)
ELS |
ND/2019/06 |
The
construction phase has
been completed
and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2 and 4 (c)
Drainage works, Sewerage works at Portion 1, 2, 3 and 4 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at Portion 4 (f)
Waterworks at Portion 1, 2 and 4 (g)
Construction of noise barrier at Portion 4 and 5 |