Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (September to November 2024)

ND/2019/01

(a)          Drainage works, watermain works, sheet piling, site formation and slope works in Portion 1a

(b)         Site formation, drainage works, watermain works and construction of noise barrier in Portion 1c

(c)          Site formation, construction of subway, road works, drainage works, slope works and soil nail in Portion 2

(d)         Site formation, excavation, slope work, drainage and watermain works and soil nail in Portion 3

(e)          Watermain works, drainage work, excavation, backfilling and road works in Portion 5

(f)          Drainage works, backfilling, road works, watermains works, construction of retaining wall and slope works in Portion 6a

(g)         Operation of HAC treatment facility in Portion 6b

(h)         Sheet piling, excavation, stockpile of soil, drainage works, watermain works and road works in Portion 7

(i)           RC construction of fresh water reservoir, backfilling works, drainage works and watermain works in Portion 8a

(j)           Trenchless work, excavation, watermain works, ground treatment and ELS construction in Portion 8b

(k)         Sheet piling, excavation, road works, drainage works, watermain works and district cooling system in Portion 9b

(l)           Site formation, excavation, drainage works and roadworks in Portion 11b

(m)       Stockpile of soil in Portion 13

ND/2019/02

(a)            Pipe Jacking

(b)           Backfilling

(c)            Concreting

(d)           Bedding and pipe laying

(e)            ELS

(f)            Sheet Pile Installation

(g)           Cut and Fill of Slope

ND/2019/03

(a)      Portion 2 to Portion 20C

-          Wetland creation & restoration, Dry agricultural land creation

-          Construction of Water Treatment Wetland

ND/2019/04

(a)           Pile Cap

(b)           Back Filling

(c)           Excavation

(d)           Grouting

(e)           Road works

(f)            Formwork and Scaffolding Erection

(g)           Rebar Fixing

(h)           ELS

(i)            Sheet Piling

ND/2019/05

(a)        Backfilling

(b)       Drainage works

(c)        Water works

(d)       Ducting and Road works

(e)        Bridge Rotation

(f)        Slope works

(g)       Segments erection

(h)       ELS

ND/2019/06

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 1, 4 and 5

(b)        C&D waste disposal at Portion 1, 2 and 4

(c)        Drainage works, Sewerage works at Portion 1, 2, 3 and 4

(d)        Filling works at Portion 2 and 4

(e)        Construction of site haul road at Portion 4

(f)         Waterworks at Portion 1, 2 and 4

(g)        Construction of noise barrier at Portion 4 and 5