3.1
In
accordance with the Updated EM&A Manual, impact 1-hour TSP and 24-hr TSP
monitoring shall be
conducted to monitor the air quality for the Works Contracts. Appendix B shows the established Action/Limit Level
for the air quality monitoring works.
3.2
Impact
1-hour TSP monitoring was conducted for at least three times every 6 days,
while the impact 24-hour TSP monitoring was conducted for at least once every 6
days at the designated air
quality monitoring stations.
3.3
Impact
air quality monitoring was conducted at the monitoring stations under the Works
Contracts, as shown in Figure 1 and
Figure 2 according to Table 1.1 of Updated EM&A Manual and Baseline Air
Quality Monitoring Report (KTN & FLN NDA).
Alternative Monitoring Station for
KTN-DMS4
3.4
As
KTN-DMS4 - Temporary structure near Fanling Highway
(near Pak Shek Au) is no longer as existing ASR, air quality monitoring station
should be relocated to the alternative dust monitoring location according to
the updated EM&A Manual, Section 2.6.2. According to Figure 3.1 of Approved
EIA report and site visits conducted in June 2022, ASR at near KTN-E70 ¡V
Temporary Structure near Fanling Highway near Pak
Shek Au is considered as the most representative alternative station KTN-DMS4(B) for air quality monitoring
for KTN-DMS4 (i.e. KTNE162).
3.5
The
alternative monitoring location KTN-DMS4(B)
is agreed by EPD on 17 August 2022. The 1-hr and 24-hrs TSP monitoring
commenced starting from 24 August 2022.
Table 3.1 describes the location of
the air quality monitoring stations.
Table 3.1 Location for Air Quality Monitoring
Locations
EP No. |
Contract No. |
Monitoring Station |
Location |
EP-473/2013/A |
ND/2019/03 |
FLN-DMS1[2] |
Scattered
Village Houses North of Proposed Potential Ecopark |
ND/2019/04 |
|||
ND/2019/05 |
FLN-DMS3[3] |
House
near Tong Hang |
|
ND/2019/03 |
FLN-DMS5[4] FLN-DMS5A |
Noble
Hill Good
View New Village |
|
ND/2019/04 |
|||
EP-466/2013/A EP-467/2013/A EP-468/2013/A |
ND/2019/01 |
KTN-DMS4(B)[5] |
Temporary
Structure near Fanling Highway (near Pak Shek Au) |
EP-468/2013/A |
ND/2019/03 |
Remarks:
[1]: Noting that
construction phase air quality monitoring at the other proposed monitoring
stations (e.g. planned), where access is permitted, will be conducted during construction
phase of relevant works contract(s).
[2]: Since the
distance between monitoring station and site boundary of ND/2019/05 under
EP-473/2013/A exceeds 500m, the monitoring station is not applicable to
ND/2019/05.
[3]: Since the
distance between monitoring station and site boundary of ND/2019/03 and
ND/2019/04 under EP-473/2013/A exceeds 500m, the monitoring station is not
applicable to ND/2019/03 and ND/2019/04.
[4]: Since the
distance between monitoring station and site boundary of ND/2019/05 under
EP-473/2013/A exceeds 500m, the monitoring station is not applicable to
ND/2019/05
[5] KTN-DMS4(B)
commenced starting from 24 August 2022 as an alternative monitoring station of
KTN-DMS4.
3.6
As
the power supply for High Volume Sampler (HVS) for TSP monitoring at FLN-DMS 5A,
KTN-DMS 4 and KTN-DMS 4(B) were rejected, direct reading dust meter was used to
measure both 1-hour and 24-hour TSP levels:-
The proposal for alternative
monitoring equipment (i.e. direct reading dust meter) for TSP monitoring was
approved by EPD according to the approved Baseline Air Quality
Monitoring Report (KTN & FLN NDA); and
Same measurement methodology (i.e.
direct reading dust meter) was adopted as baseline monitoring for a reliable
comparison.
3.7
The
proposed use of portable direct reading dust meters was also submitted
to IEC and agreement was obtained from the IEC in accordance
with Section 2.4.5 of the Updated EM&A Manual.
3.8
HVS
for 24-hour TSP monitoring will be adopted once
secured supply of electricity become available at FLN-DMS 5A and KTN-DMS 4(B).
3.9
Table 3.2
summarises the equipment used
in the impact air monitoring programme. Copies of
calibration certificates are attached in Appendix
C.
Table 3.2 Air Quality Monitoring Equipment
Monitoring Station |
Equipment |
Manufacturer |
Model
and Make |
Quantity |
FLN-DMS5 FLN-DMS5A KTN-DMS4(B) |
Dust Monitor (1-hour and 24-hour TSP) |
Met One
Instruments |
AEROCET-831 |
8 |
FLN-DMS1 FLN-DMS3 |
Dust Monitor (1-hour TSP) |
HVS Sampler (TSP) (24-hour TSP) |
Tisch |
TISCH
Model: TE-5170 |
2 |
3.10
Meteorological
information extracted from ¡§Hong Kong Observatory - Ta Kwu
Ling Weather Station¡¨ was proposed as the alternative method to obtain
representative wind data. For Ta Kwu Ling Weather
Station, it is located nearby the Project site and situated at approximately
15m above mean sea level. The station¡¦s wind data monitoring equipment is set
above the existing ground 10 meters in compliance with the
general setting up requirements. Furthermore, this station also
provides other meteorological information, such as humidity, rainfall, air
pressure and temperature etc.
3.11
The
general weather conditions (i.e. sunny, cloudy or
rainy) were recorded by the field staffs during the monitoring days.
3.12
Table 3.3 summarises the
monitoring parameters and frequencies of impact dust monitoring during the Works
Contracts activities. The air quality monitoring schedule for the reporting
month is shown in Appendix D.
Table 3.3 Impact Dust Monitoring Parameters, Frequency and
Duration
Parameters |
Frequency |
1-hour TSP |
Three times/ 6 days |
24-hour TSP |
Once / 6 days |
1-hour
and 24-hour TSP Air Quality Monitoring
Instrumentation
3.13
Direct reading
dust meter was deployed for the air quality monitoring as shown in Table 3.2.
3.14
The measuring
procedures of the dust meters were in accordance with the Manufacturer¡¦s
Instruction Manual as follows:
(AEROCET-831)
•
Place the 1-hour
dust meter at least 1.3 meters above ground.
•
Press and hold
the Power key momentarily to power on the unit and make sure that the battery
level was not flash or in low level.
•
Allow the
instrument to stand for about 3 second to display the Sample Screen minutes.
•
Press the START
/ STOP key to run the internal vacuum pump for 1 minute and be ready to use.
•
Use the select
dial to select the PM range and press the START / STOP key to start a
measurement.
•
Finally, push
the START/STOP key to stop the measurement after 1 hour sampling.
•
Information
such as sampling date, time, value and site condition
were recorded during the monitoring period.
•
All data were
recorded in the data logger for further data processing.
Maintenance/Calibration
3.15
The following
maintenance/calibration was
required for the direct dust meters:
•
Check and
calibrate the meters by HVS to check the validity and accuracy of the results
measured by direct reading method at 2-month intervals throughout all stages of
the air quality monitoring.
24-hour
TSP Air Quality Monitoring
Instrumentation
(TISCH Model: TE-5170)
3.16
High volume Samplers
(HVS) completed with appropriate sampling inlets were employed for 24-hour TSP
monitoring. Each sampler was
composed of a motor, a filter holder, a flow controller and a sampling inlet
and its performance specification complies with that required by USEPA Standard
Title 40, Code of Federation Regulations Chapter 1 (Part 50).
HVS Installation
3.17
The following
guidelines were adopted during the installation of HVS:
•
A horizontal
platform with appropriate support was provided to secure the samplers against
gusty wind.
•
No two samplers
were placed less than 2 meters apart.
•
The distance
between the sampler and an obstacle, such as buildings, was at least twice the
height that the obstacle protrudes above the sampler.
•
A minimum of 2
meters of separation from walls, parapets and penthouses was required for
rooftop samples.
•
A minimum of 2
meters separation from any supporting structure, measured horizontally was
required.
•
No furnaces or
incineration flues were nearby.
•
Airflow around
the sampler was unrestricted.
•
The samplers
were more than 20 meters from the drip line.
•
Any wire fence
and gate, to protect the sampler, should not cause any obstruction during
monitoring.
•
Permission and access
to the monitoring stations have been obtained to set up the samplers.
•
A secured
supply of electricity was provided to operate the samplers.
Filters
Preparation
3.18
Wellab Limited (HOKLAS Registration No. HOKLAS083) is a HOKLAS
accredited laboratory and responsible for the preparation of 24-hour
conditioned and pre-weighed filter papers for the monitoring team.
3.19
All filters
were equilibrated in the conditioning environment for 24 hours before
weighing. The conditioning
environment temperature was around 25¢XC and not variable by more than ¡Ó3¢XC; the
relative humidity (RH) was < 50% and not variable by more than ¡Ó5%. A convenient working RH was 40%.
Operating/Analytical
Procedures
3.20
Operating/analytical
procedures for the air quality monitoring were highlighted as follows:
•
Prior to the
commencement of dust sampling, the flow rate of the HVS was properly set
(between 1.1 m3/min. and 1.4 m3/min.) in accordance with
the manufacturer's instruction to within the range recommended in USEPA
Standard Title 40, CFR Part 50;
•
The power
supply was checked to ensure the sampler worked properly;
•
On sampling,
the sampler was operated for 5 minutes to establish thermal equilibrium before
placing any filter media at the designated air quality monitoring station;
•
The filter
holding frame was then removed by loosening the four nuts and carefully a
weighted and conditioned filter was centered with the stamped number upwards,
on a supporting screen;
•
The filter was
aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter. The filter
holding frame was then tightened to the filter holder with swing bolts. The applied pressure should be
sufficient to avoid air leakage at the edges;
•
The shelter lid
was closed and secured with the aluminum strip;
•
The timer was
then programmed. Information was
recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the
filter paper can be found out by using the filter number);
•
After sampling,
the filter was removed and kept in a clean and tightly sealed plastic bag. The
filter paper was then returned to the HOKLAS accredited laboratory (Wellab Ltd.) for reconditioning in the humidity-controlled
chamber followed by accurate weighting by an electronic balance with a readout
down to 0.1mg. The elapsed time was also recorded; and
•
Before
weighing, all filters were equilibrated in a conditioning environment for 24
hours. The conditioning environment temperature should be between 25¢XC and
Maintenance/Calibration
3.21
The following
maintenance/calibration was required for the HVS:
•
The high volume motors and their accessories were properly
maintained. Appropriate maintenance such as routine motor brushes replacement
and electrical wiring checking were made to ensure that the equipment and
necessary power supply are in good working conditions; and
•
All HVS were
calibrated (five point calibration) using Calibration
Kit prior to the commencement of baseline monitoring and thereafter at
bi-monthly intervals.
3.22
The monitoring
results for 1-hour TSP and 24-hour TSP are summarised
in Tables 3.4 and 3.5 respectively. Detailed monitoring results
and graphical presentations of 1-hour and 24-hour TSP monitoring results are
shown in Appendix E.
Table 3.4 Summary
Table of 1-hour TSP Monitoring Results during the
Reporting Month
Monitoring Station |
Concentration (µg/m3) |
Action Level, µg/m3 |
Limit Level, µg/m3 |
|
Average |
Range |
|||
FLN-DMS1 |
75.8 |
48.2
¡V 119.6 |
303 |
500 |
FLN-DMS3 |
74.8 |
36.1
¡V 138.0 |
301 |
500 |
FLN-DMS5 |
52.7 |
18.5
¡V 106.9 |
279 |
500 |
KTN-DMS4(B) |
59.5 |
28.5
¡V 109.4 |
297 |
500 |
Table 3.5 Summary Table of
24-hour TSP Monitoring Results during the
Reporting Month
Monitoring Station |
Concentration (µg/m3) |
Action Level, µg/m3 |
Limit Level, µg/m3 |
|
Average |
Range |
|||
FLN-DMS1 |
69.7 |
27.6
¡V 113.9 |
150 |
260 |
FLN-DMS3 |
42.2 |
30.0
¡V 57.7 |
165 |
260 |
FLN-DMS5A |
57.8 |
28.2
¡V 103.2 |
153 |
260 |
KTN-DMS4(B) |
53.9 |
28.1
¡V 78.1 |
192 |
260 |
3.23
All 1-hour and
24-hour TSP monitoring was conducted as scheduled in the reporting month. No
Action/Limit Level exceedances were recorded.
3.24
According to
our field observations, the major dust sources identified at the designated air
quality monitoring stations in the reporting month are shown in Table 3.6:
Table 3.6 Observation
at Dust Monitoring Stations
Monitoring Station |
Major Dust Sources |
FLN DMS1 |
Mobile crane, Excavator,
piling, road traffic |
FLN-DMS3 |
Excavator, piling, mobile
crane, road traffic |
FLN-DMS5 |
Road traffic |
KTN-DMS4(B) |
Excavator, piling,
mobile crane, dump truck, road traffic |
3.25
Should any non-compliance
of the criteria occur, actions in accordance with the Event/Action Plan in Appendix N shall be carried out.