Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site Activities (May to July 2024) |
ND/2019/01 |
(a)
Drainage works,
watermain works, sheet piling, site formation and slope works in Portion 1a (b)
Site
formation, sheet piling, shoving, pipe jacking, drainage
works and
construction of noise barrier in Portion 1c (c)
Sheet
Piling, Site formation, construction of subway, road works and drainage works
in Portion 2 (d)
Site
formation, site clearance, excavation, slope work, drainage and watermain
works in Portion 3 (e)
Watermain
works, excavation, backfilling, road works and pipe jacking in Portion 5 (f)
Drainage
works, backfilling, road works, watermains works and construction of retaining wall in Portion 6a (g)
Operation
of HAC treatment facility in Portion 6b (h)
Sheet
piling, excavation, stockpile of soil, drainage works and watermain works in
Portion 7 (i)
RC
construction of fresh water reservoir, backfilling works, drainage works,
watermain works and ELS installation for receiving pit in Portion 8a (j)
Trenchless
work, excavation, watermain works and ground treatment in Portion 8b (k)
Sheet
piling, pipe pilling, excavation, road works, drainage works, watermain works
and district cooling system in Portion 9b (l)
Site formation, excavation, drainage, sewage,
watermain and roadworks in Portion 11b (m)
Site clearance, removal of existing structure, site formation and
stockpile of soil in Portion 13 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet Pile
Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry agricultural land creation -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work |
ND/2019/04 |
(a)
Pile Cap (b)
Back Filling (c)
Excavation (d)
Grouting (e)
Road works (f)
Formwork and Scaffolding Erection (g)
Rebar Fixing (h)
ELS |
ND/2019/05 |
(a)
Piling, pile cap, column, piers
and ELS works. (b)
Drainage works at TWSRW. (c)
Outfall along Ma Wat River. (d)
HKY Footbridge TWSRE & TWSRW (e)
PT BBI at TWSRE (f)
Road Works at JCR and Tong Hang Village Road
Junction |
ND/2019/06 |
The
construction phase has
been completed
and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Construction of box culvert at Portion 2 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at Portion 4 (f)
Drainage works, Sewerage works at Portion 2, 3, 4 (g)
Construction of noise barrier at Portion 4 and 5 (h)
Waterworks at Portion 1, 2 and 4 |