Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (May to July 2024)

ND/2019/01

(a)          Drainage works, watermain works, sheet piling, site formation and slope works in Portion 1a

(b)         Site formation, sheet piling, shoving, pipe jacking, drainage works and construction of noise barrier in Portion 1c

(c)          Sheet Piling, Site formation, construction of subway, road works and drainage works in Portion 2

(d)         Site formation, site clearance, excavation, slope work, drainage and watermain works in Portion 3

(e)          Watermain works, excavation, backfilling, road works and pipe jacking in Portion 5

(f)          Drainage works, backfilling, road works, watermains works and construction of retaining wall in Portion 6a

(g)         Operation of HAC treatment facility in Portion 6b

(h)         Sheet piling, excavation, stockpile of soil, drainage works and watermain works in Portion 7

(i)           RC construction of fresh water reservoir, backfilling works, drainage works, watermain works and ELS installation for receiving pit in Portion 8a

(j)           Trenchless work, excavation, watermain works and ground treatment in Portion 8b

(k)         Sheet piling, pipe pilling, excavation, road works, drainage works, watermain works and district cooling system in Portion 9b

(l)           Site formation, excavation, drainage, sewage, watermain and roadworks in Portion 11b

(m)       Site clearance, removal of existing structure, site formation and stockpile of soil in Portion 13

ND/2019/02

(a)           Pipe Jacking

(b)           Backfilling

(c)           Concreting

(d)           Bedding & Pipe Laying

(e)           ELS

(f)            Sheet Pile Installation

(g)           Cut and Fill of Slope

ND/2019/03

(a)      Portion 2 to Portion 20C

-          Wetland creation & restoration, Dry agricultural land creation

-          Construction of Water Treatment Wetland

-          Tree felling and tree pruning work

ND/2019/04

(a)           Pile Cap

(b)           Back Filling

(c)           Excavation

(d)           Grouting

(e)           Road works

(f)            Formwork and Scaffolding Erection

(g)           Rebar Fixing

(h)           ELS

ND/2019/05

(a)        Piling, pile cap, column, piers and ELS works.

(b)       Drainage works at TWSRW.

(c)        Outfall along Ma Wat River.

(d)       HKY Footbridge TWSRE & TWSRW

(e)        PT BBI at TWSRE

(f)        Road Works at JCR and Tong Hang Village Road Junction

ND/2019/06

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 1, 4 and 5

(b)        C&D waste disposal at Portion 1, 2, 4 and 5

(c)        Construction of box culvert at Portion 2

(d)        Filling works at Portion 2 and 4

(e)        Construction of site haul road at Portion 4

(f)         Drainage works, Sewerage works at Portion 2, 3, 4

(g)        Construction of noise barrier at Portion 4 and 5

(h)        Waterworks at Portion 1, 2 and 4