Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (September 2023) |
ND/2019/01 |
(a)
Drainage works at Portion 1a (b)
Portion 1b was handed over (c)
Site formation and socket-H piling at Portion 1c (d)
Temporary storage of material at Portion 1e (e)
Site clearance, site formation, construction of subway, drainage
works and road works at Portion 2 (f)
Sheet piling, drainage works and watermain works at Portion 3 (g)
Watermains works at Portion 5 (h)
Drainage works and backfilling at Portion 6a (i)
Operation of HAC soil treatment facility at Portion 6b (j)
Excavation and drainage works at Portion
7 (k)
Construction of retaining wall, RC construction of fresh water
service reservoir, construction of WSD¡¦s maintenance access, drainage
works and backfilling works at Portion 8a (l)
Pipe jacking at LWSC¡¦s car park, trenchless work and watermain construction at Portion
8b (m)
Sheet piling, excavation, drainage and watermain works at Portion
9b (n)
Site clearance and removal of existing
structures at Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road
& Drainage works and watermains works at Yin Kong Road -
Construction of Pavilion at Yin Kong Road (b) Portion 2 to Portion 20C -
Wetland creation & restoration, Dry
agricultural land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) -
Construction of Car Park and Farmer¡¦s Forum |
ND/2019/04 |
(a) Tree Felling (b) Pile Cap (c) Back Filling (d) Excavation (e) Grouting (f) Sheet Piling (g) Road works (h) Formwork Erection (i) Rebar Fixing (j) Pre-drill (k) Bore pile (l)
ELS |
ND/2019/05 |
(a)
The segment erection using launching gantry is
critical to completion of section 4. (b)
The pier D2-01 with bridge rotation system is
critical to completion of section 5. (c)
The erection of 3rd form traveler at
D2-02 is in progress. (d)
5th set of form traveler is under
fabrication off-site to be used at E2-01. |
ND/2019/06 |
The construction phase was completed and handed over to AFCD
since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at
Portion 2, 3, 4 and 5 (d)
Construction of box culvert at Portion
2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at
Portion 4 (g)
Waterworks at Portion 1, 2 and 4 |