1.
This is the 47th monthly Environmental Monitoring
and Audit (EM&A) Report for the First Phase Development of Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs), comprising the Advance Works and
First Stage Works (hereinafter
called the ¡§the
Project¡¨). This report is prepared
by Wellab Limited under ¡§Service Contract No. NDO
04/2019 Environmental Team for Environmental Monitoring and Audit Works in
Construction Phase for the First Phase Development of KTN and FLN NDAs¡¨ (hereinafter called the ¡§Service
Contract¡¨). This report documents the findings of EM&A works conducted in September
2023.
2.
During the reporting month, the following Works
Contracts under relevant Environmental Permit(s) were undertaken for the
Project:
Table I Works
Contracts under relevant Environmental Permit(s) in the Reporting Month
Works Contracts |
Environmental Permit No. |
Designated Project (DP) |
Commencement date of construction |
Contract No. ND/2019/01 ¡V Kwu Tung North New Development Area,
Phase 1: Site Formation and Infrastructure Works |
EP-466/2013/A |
Castle Peak Road Diversion |
12 August 2020 |
EP-467/2013/A |
Kwu Tung North New Development Area Road P1 and
P2 and Associated New Kwu Tung Interchange and Pak
Shek Au Interchange Improvement |
12 August 2020 |
|
Kwu Tung North New Development Area Road D1 to
D5 |
1 June 2020 |
||
Utilization of Treated Sewage Effluent (TSE)
from Shek Wu Hui Sewage Treatment Works |
23
March 2020 |
||
Contract No. ND/2019/02 ¡V Kwu Tung North New Development Area,
Phase 1: Roads and Drains between Kwu Tung North
New Development Area and Shek Wu Hui |
EP-469/2013 |
Sewage Pumping Stations in Kwu Tung North New Development Area |
28 October
2020 |
Contract No. ND/2019/03 ¡V Kwu Tung North and Fanling North New Development Areas, Phase 1: Development
of Long Valley Nature Park |
Kwu Tung North New Development Area Road D1 to
D5 |
3 July
2020 |
|
EP-473/2013/A |
Fanling Bypass Eastern Section (New Road) |
6 October
2020 |
|
Contract No. ND/2019/04 ¡V
Fanling North New Development Area, Phase 1:
Fanling Bypass Eastern Section (Shek Wu San Tsuen
North to Lung Yeuk Tau) |
EP-473/2013/A |
Fanling Bypass Eastern Section (New Road) |
23
February 2021 |
EP-546/2017 |
Fanling North Temporary Sewage Pumping Station |
16
February 2021 |
|
Contract
No. ND/2019/05 ¡V
Fanling North New Development Area, Phase 1:
Fanling Bypass Eastern Section (Shung Him Tong to
Kau Lung Hang) |
EP-473/2013/A |
Fanling Bypass Eastern Section (New Road) |
1
August 2020 |
Contract No. ND/2019/06 ¡V
Fanling North
New Development Area, Phase 1: Re-provisioning of North District Temporary
Wholesale Market for Agricultural Products |
Reprovision of temporary Wholesale Market in
Fanling North New Development Area |
29
October 2019 |
|
Contract No. ND/2019/07 ¡V
Fanling North New
Development Area, Phase 1: Site Formation and Infrastructure Works |
Works
area not under relevant Environmental Permit for Phase 1 of the Project. |
1 March
2021 |
3.
A summary of the EM&A activities in
this reporting month is listed in Table
II below:
Table II Summary Table for EM&A Activities in
the Reporting Month
EM&A Activities |
Monitoring Station (s) |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
||
1-hr
Total Suspended Particulates (TSP) Monitoring |
FLN-DMS1 |
N/A |
N/A |
4, 14, 20, 26 and 28
Sep 23 |
4, 14, 20, 26 and 28
Sep 23 |
N/A |
N/A |
N/A |
FLN-DMS3 |
N/A |
N/A |
4, 14, 20, 26 and 28
Sep 23 |
|||||
FLN-DMS5 |
7, 13, 19, 25 and 29
Sep 23 |
7, 13, 19, 25 and 29
Sep 23 |
N/A |
|||||
KTN-DMS4(B) |
7, 13, 19, 25 and 29
Sep 23 |
7, 13, 19, 25 and 29
Sep 23 |
N/A |
|||||
24-hr
TSP Monitoring |
FLN-DMS1 |
N/A |
N/A |
7, 19, 25 and 29 Sep
23 |
7, 19, 25 and 29 Sep
23 |
N/A |
N/A |
N/A |
FLN-DMS3 |
N/A |
N/A |
7, 13, 19, 25 and 29
Sep 23 |
|||||
FLN-DMS5A |
7, 13, 19, 25 and 29
Sep 23 |
7, 13, 19, 25 and 29
Sep 23 |
N/A |
|||||
KTN-DMS4(B) |
7, 13, 19, 25 and 29
Sep 23 |
7, 13, 19, 25 and 29
Sep 23 |
N/A |
|||||
Noise Monitoring |
CP-FLN-NMS1 |
N/A |
4, 14, 20 and 26 Sep 23 |
N/A |
||||
CP-FLN-NMS2 |
N/A |
4, 14, 20 and 26 Sep
23 |
N/A |
|||||
CP-KTN-NMS2 |
7, 13, 19 and 25 Sep
23 |
N/A |
N/A |
|||||
CP-KTN-NMS3 |
||||||||
CP-KTN-NMS5 |
||||||||
CP-KTN-NMS6 |
N/A |
7, 13, 19 and 25 Sep
23 |
||||||
Ecological
Survey |
Monitoring
of Measures to Minimise Disturbance to Water Birds
on Ng Tung River, Sheung Yue
River, and Long Valley |
N/A* |
N/A* |
5,
6, 11, 12, 18, 20, 26 and 27 Sep 23 |
5,
11, 18 and 26 Sep 23 |
N/A* |
N/A* |
N/A* |
Monitoring of Measures to Minimise Impacts
to Ma Tso Lung Stream and Siu Hang San Tsuen Stream |
15 Sep 23 |
N/A* |
15 Sep 23 |
15 Sep 23 |
N/A* |
N/A* |
N/A* |
|
Monitoring of Measures to Minimise Impacts on
Ecological Sensitive Habitats from Disturbance and Pollution |
14
and 21 Sep 23 |
14
and 21 Sep 23 |
21
Sep 23 |
21
Sep 23 |
21
Sep 23 |
N/A* |
N/A* |
|
Egretry Monitoring |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
24-hr RSP (Ambient Arsenic) Monitoring for Land Contamination |
6, 12, 18, 22 and 28
Sep 23 |
N/A |
6, 12, 18, 22 and 28
Sep 23 |
N/A |
N/A |
N/A |
N/A |
|
Water
Quality Monitoring |
N/A |
4, 6, 11, 13, 15, 18,
20, 22, 25, 27 and 29 Sep 23 |
N/A |
4, 6, 11, 13, 15, 18,
20, 22, 25, 27 and 29 Sep 23 |
N/A |
N/A |
N/A |
|
Landfill
Gas Monitoring |
28 Sep 23 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Built
Heritage Monitoring |
N/A |
N/A |
N/A |
N/A |
Daily
assessment subject to construction works conducted within assessment area |
N/A |
N/A |
|
5, 12, 18 and 26 Sep 23 |
6, 13, 22 and 27 Sep 23 |
14, 19 and 29 Sep 23 |
7, 13, 21 and 28 Sep 23 |
4, 14, 18 and 26 Sep 23 |
7, 13, 21 and 28 Sep 23 |
15, 19 and 25 Sep 23 |
Remarks:
N/A ¡V No relevant monitoring is required according
to the updated EM&A Manual
N/A* ¡V No relevant monitoring is required according to
the Baseline Ecological Monitoring Plan (Table 3.1)
[1] Since the distance
between monitoring station CP-KTN-NMS2 and site boundary of ND/2019/03 under EP-468/2013/A
exceeds 300m, the monitoring station is not applicable to ND/2019/03
[2] Since the distance
between monitoring station CP-KTN-NMS3 and site boundary of ND/2019/03 under
EP-468/2013/A exceeds 300m, the monitoring station is not applicable to
ND/2019/03
[3] Since the distance
between monitoring station CP-KTN-NMS1 and site boundary of ND/2019/02 under
EP-469/2013 exceeds 300m, the monitoring station is not applicable to
ND/2019/02
[4] Since the distance
between monitoring station FLN-DMS1 and site boundary of ND/2019/05 under
EP-473/2013/A exceeds500m, the monitoring station is not applicable to
ND/2019/05
[5] Since the distance
between monitoring station FLN-DMS3 and site boundary of ND/2019/03 and
ND/2019/04 under EP-473/2013/A exceeds 500m, the monitoring station is not
applicable to ND/2019/03 and ND/2019/04
[6] Since the distance
between monitoring station FLN-DMS5 and site boundary of ND/2019/05 under
EP-473/2013/A exceeds 500m, the monitoring station is not applicable to
ND/2019/05
[7] Since the distance
between monitoring station CP-FLN-NMS2 and site boundary of ND/2019/03 and
ND/2019/04 under EP-473/2013/A exceeds 300m, the monitoring station is not
applicable to ND/2019/03 and ND/2019/04
[8] Since the distance
between monitoring station CP-FLN-NMS1 and site boundary of ND/2019/03 under
EP-473/2013/A exceeds 300m, the monitoring station is not
applicable to ND/2019/03
4.
Summary of the environmental exceedances
of the reporting month is tabulated in Table
III.
Table III Summary Table for Events Recorded
in the Reporting Month
Environmental Monitoring |
Parameter |
No. of non-project related
Exceedances |
Total
No. of non-project related
Exceedances |
No. of Exceedance
related to the Construction Works of the Contract |
Total
No. of Exceedance related to the Construction Works of the Contract |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
||||
Air Quality |
1-hr
TSP |
0 |
0 |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
0 |
0 |
|
24-hr RSP (Ambient Arsenic) |
0 |
0 |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
0 |
0 |
Water Quality |
DO |
0 |
3 |
3 |
0 |
0 |
0 |
Turbidity |
0 |
2 |
2 |
0 |
0 |
0 |
|
SS |
0 |
0 |
0 |
0 |
0 |
0 |
|
Arsenic |
1 |
0 |
1 |
0 |
0 |
0 |
|
Landfill
Gas |
O2 |
0 |
0 |
0 |
0 |
0 |
0 |
CH4 |
|||||||
CO2 |
|||||||
Cultural
heritage |
Built Heritage Monitoring |
0 |
0 |
0 |
0 |
0 |
0 |
Ecological
Monitoring |
Avifauna |
0 |
0 |
0 |
0 |
0 |
0 |
Aquatic fauna |
0 |
0 |
0 |
0 |
0 |
0 |
|
Non-aquatic fauna |
1 |
1 |
2 |
0 |
0 |
0 |
Air Quality
5. All
construction air quality monitoring was conducted as scheduled in the reporting
month except
1
and 8 September 2023 due to adverse weather, and 13 September 2023 due to power
failure. No
Action/Limit Level exceedance was recorded.
Construction Noise
6.
All construction noise monitoring was
conducted as scheduled in the reporting month. No
Action/Limit Level exceedance was recorded.
Water
Quality
7. All
additional water quality monitoring was conducted as scheduled in the reporting
month except 1 and 8 September 2023 due to the adverse weather (Typhoon Signal No. 8 on 1 Sep and Black Rainstorm
Warning Signal on 8 Sep). Three (3) Limit Level for DO, Two (2) Limit Level for turbidity, and One (1) Action Level
for Arsenic of impact water quality monitoring were recorded. No construction
of channel for alternation of natural streams was carried out in the reporting
month. Therefore, no water quality monitoring was
conducted according to the Updated
EM&A Manual and Baseline Water Quality Monitoring Report (KTN & FLN
NDA). Relevant details are given in Section
5.
Land Contamination
8. All ambient
arsenic monitoring was conducted as scheduled in the reporting month. No
Action/Limit Level exceedance was recorded.
Landfill Gas Monitoring
9. Monitoring
of landfill gas in the reporting month was carried out by the Contractor under ND/2019/01
at excavation location Portion 6b. No Limit Level exceedance was recorded.
Built Heritage Monitoring
10. Built
heritage monitoring was carried out in the reporting month by the Contractor under ND/2019/05 for surveyed
cultural heritage. No Limit Level exceedance was recorded.
Ecological Monitoring
11. All
ecological monitoring was conducted as scheduled in the reporting month. One (1)
action level exceedance and one (1) limit level
exceedance for non-aquatic fauna were recorded at T3. The exceedance were considered non-project
related, as large proportion of vegetative habitat along T3 were observed
either removed and tarmacked as haul road by construction works outside of
project, first reported in the Monthly Monitoring Report in December 2021.
The ecological monitoring result in the Reporting Month is shown in Appendix L.
Complaint Log
12. One
environmental complaint was received in the reporting month. The complaint
regarding soil/muddy water discharged is for ND/2019/04, which was referred by
EPD on 4 September 2023 for the complaint case received by EPD on the same day.
On 11 September 2023, supplementary information of the same case was referred
by EPD also.
Notification of Summons and Successful
Prosecutions
13. No
notification of summons or successful prosecutions was received in the
reporting month.
14. This
report has been prepared in compliance with the reporting requirements for the
subsequent monthly EM&A Report as required by the ¡§Updated Environmental
Monitoring and Audit Manual for Advance and First Stage Works of Kwu Tung North and Fanling North
New Development Areas¡¨ (Updated EM&A Manual).
15.
The major site
activities for the coming three months are shown in Table IV.
Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site Activities (October to December 2023) |
ND/2019/01 |
(a)
Drainage works
and sheet pile in Portion 1a (b)
Site
formation and construction of noise barrier in Portion 1c (c)
Temporary
storage of material in Portion 1e (d)
Site
formation work, construction of subway, road works and drainage works in Portion 2 (e)
Excavation,
backfilling, drainage and watermain works in Portion 3 (f)
Watermain
works, excavation, backfilling, road works, sheet piling and pipe jacking in
Portion 5 (g)
Drainage
works, backfilling, road works, watermains works in Portion 6a (h)
Operation
of HAC treatment facility in Portion 6b (i)
Sheet
piling, excavation and drainage works and watermain works in Portion 7 (j)
Construction
of retaining wall, RC construction of fresh water reservoir, excavation at WSD¡¦s
maintenance access, backfilling works and drainage works in Portion 8a (k)
Trenchless
work, excavation and watermain works in Portion 8b (l)
Sheet
piling, excavation, drainage works and watermain works in Portion 9b (m)
Site clearance, tree felling and removal of
existing structure in Portion 13 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road &
Drainage works and watermains works at Yin Kong Road -
Construction of Pavilion at Yin Kong Road (b)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry
agricultural land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) -
Construction of Car Park and Farmer¡¦s Forum |
ND/2019/04 |
(a)
Tree Felling (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork Erection (i)
Rebar Fixing (j)
Pre-drill (k)
Bore pile (l)
ELS |
ND/2019/05 |
(a)
North Team Works -
ELS works and Pile cap construction at B2-01 -
Backfilling and drainage work at C4-02 &
C4-01. -
Backfilling at C2-02. -
Slope works at On Lok Garden FS 30. -
Construction of B1-abutment wall, backfill &
extraction of sheet pile. -
Exposed water main of Jockey Club Rd ¡VF63. -
Road works of northbound of Jockey Club Rd. -
Laying ducting for traffic signal, traffic light
& street light & construction of permanent footpath for subsequent
pedestrian diversion at J/O of JCR and Tong Hang Tsuen -
Construction of new box culvert & retaining
wall at Tong Hang Tsuen -
Drainage works ¡VDN 900 at On Kui Street near B1. -
Pier construction at D2-01 & B2-01 -
Pier head construction at D2-01 -
Cross head construction at B2-02 & B2-03 (b)
Viaduct Works -
Segment fabrication for bridge C2, D1, D2& E1 -
Segments erection by LG at bridges C3, C2 -
Segments erection by crane at bridge D1 and E1 -
SOP construction at E2-01, E2-03, D2-01 -
Construction of pile cap and installation of
bridge rotation components at pier D2-01 -
Design and fabrication of falsework for Bridge B1 -
Parapet skin fabrication and parapet construction (c)
South Team Works -
TWSRW ¡V
Road work and UUs laying (Section P800 CH 300 to 450). -
TWSRW ¡V Construction of lower berm and
Hydroseeding at FS04. -
TWSRW - CLP 11 kv
cable diversion work (1ST) -
TWSRW ¡V Gas (IPA400 and HP600) diversion work -
TWSRW ¡V Foundation work of D2-04M -
TWSRE ¡V Form Road L201, BBI Steelworks,
relocation of existing BBI and road diversion -
TWSRE ¡V Pavement Works (D400, L201, Temporary
Road to match D300) -
HKY FB (East) ¡V Installation of cladding and
E&M works -
HKY FB (West) ¡V Construction of LT2 (Mini-piles) -
E3-04a, E3-04b, E4-01 and E4-02 ¡V cap
construction. -
NB109 ¡V Bay 11~12 base slab construction. Bay 5
to 12 wall construction. -
NB69 ¡V Bay 5~6 base slap construction. -
NB110 ¡V Bay 8 ELS and base slab construction. (d)
Form Traveler -
E3-03 ¡V construction 2nd to 4th
pair -
E2-02 ¡V construction 10th to 14th
pair -
D2-02 ¡V construction 1st to 5th
pair -
D2-03 ¡V erection of form traveler no. 4 and
construction 1st to 2nd pair -
E2-01 - Fabrication & erection of 5th
set of form traveler. |
ND/2019/06 |
The construction phase has been completed and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1,
2, 4 and 5 (c)
Construction of box culvert at Portion
2 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at
Portion 4 (f)
Drainage works, Sewerage works at
Portion 2, 3, 4 and 5 (g)
Mini piling works at Portion 4 (h)
Construction of noise barrier at
Portion 4 and 5 (i)
Waterworks at Portion 1, 2 and 4 |