2.1
The
Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs) are one of the important sources of
land and housing supply in the medium and long term. The development of the KTN
and FLN NDAs will be implemented in phase for full completion by 2031. The
Phase 1 of the NDAs development, comprising the Advance Works and First Stage
Works, is targeted to be implemented from the second half of 2019
progressively. The Advance and First Stage Works would include site formation,
engineering infrastructure works (including roads, drainage, sewerage,
waterworks, landscaping works, pumping stations, and fresh water and flushing
water service reservoirs), soil remediation, reprovisioning of North District
Temporary Wholesale Market, development of a nature park at Long Valley and
implementation of environmental mitigation measures.
2.2
The
scope of works under the Advance and First Stage Works comprises the following:
a)
The
Advance Works (PWP item No. 7747CL-2) consist of:
i)
site
formation of land (including soil remediation) in KTN and FLN NDAs for housing,
community facilities and engineering infrastructure;
ii)
construction
of roads including the eastern section of Fanling
Bypass (FLBP(E)) connecting the FLN NDA to Fanling
Highway and other roads with footpaths and cycle tracks, and associated
junction/ road improvements;
iii)
engineering
infrastructure works including drainage. Sewerage (including two sewage pumping stations), waterworks (including a fresh
water service reservoir and a flushing water service reservoir in the KTN NDA),
landscape works and slopeworks;
iv)
part
expansion and upgrading of Shek Wu Hui Sewage Treatment Works (SWHSTW);
v)
reprovisioning
works; and
vi)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (v) above.
b)
The
First Stage Works (PWP item No. 7759CL) consist of:
i)
development
of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung Yue River
for connection between these two facilities;
ii)
reprovisioning
of two egretry sites in the FLN NDA and enhancement
works to an existing egretry site in the KTN NDA;
iii)
site
formation of land for a village resite
area and a district police station in the KTN NDA;
iv)
engineering
infrastructure works including roads, drainage, sewerage, waterbirds, and
landscape works; and
v)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (iv) above.
2.3
The
Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule
3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October
2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director
of Environmental Protection pursuant to the EIA Ordinance. The relevant EPs
under the Project and the respective Work Contracts are summarised in Tables
2.1a and 2.1.b.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP No. |
Designated Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
¡@ |
|||||||
Kwu Tung North New
Development Area Road P1 and P2 and Associated New Kwu
Tung Interchange and Pak Shek Au Interchange Improvement |
ü |
¡@ |
|||||||
Kwu Tung North New
Development Area Road D1 to D5 |
ü |
ü |
¡@ |
||||||
Sewage Pumping Stations in Kwu
Tung North New Development Area |
ü |
¡@ |
|||||||
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
|||||||
Fanling Bypass Eastern
Section |
ü |
ü |
ü |
¡@ |
|||||
Reprovision of temporary Wholesale Market in Fanling North New Development Area |
ü |
¡@ |
|||||||
EP-546/2017 |
Fanling North Temporary
Sewage Pumping Station |
ü |
¡@ |
Notes:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope of Works under concerned EP
Environmental
Permit (EP) No. |
Work
Contract(s) |
Scope
of Works under concerned EP(s) |
Site
Layout Plan under concerned EP(s) |
EP-466/2013/A(Part) |
C1 |
Realign Castle Peak Road and join with the Pak
Shek Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction of new primary distributor road (P1)
within Kwu Tung North New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction of new primary distributor roads (D1,
D3, D4 and part of D5) within Kwu Tung North New
Development Area |
Figure 14 |
C3 |
Development of a nature park at Long Valley and
ecological mitigation and enhancement works for the nature park (Condition
2.9) |
Figure 15 |
|
EP-469/2013(Part) |
C2 |
Construction of one sewage pumping station in Kwu Tung North with installed capacity of more than 2,000
m3 per day |
Figure 16 |
EP-470/2013/A(Part) |
C1 |
Construction of service reservoir and watermain
for the reuse of treated sewage effluent for reuse in Kwu
Tung North Development Areas |
Figure 17 |
EP-473/2013/A(Part) |
C3 |
Establishment of alternative egretry sites and enhance
the existing egretry site at Ho Sheung Heung and/or
its vicinity (Condition 2.7) |
Figure 18 |
EP-473/2013/A(Part) |
C5A |
Construction of new district distributor inside
FLN NDA, which provides a linkage between the Man Kam To
Road and the proposed Fanling Bypass Eastern
Section |
Figure 19 |
EP-473/2013/A(Part) |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The re-provisioned wholesale market will have
approximately 1,000 market stalls within a site area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a temporary sewage pumping
station in Fanling North with installed capacity
(average dry weather flow) of about 3,600m3/day |
Figure 22 |
Remark: The EP(s) not related to the Project of the First Phase of the Kwu
Tung North (KTN) and Fanling North (FLN) New
Development Area (NDA) Development Areas are not included in the Table.
2.4
The
site boundary of the Project and all Works Contracts are shown in Drawing No. 1.
2.5
The
required submissions and submission status under Environmental Permits are
shown in Appendix U.
2.6
The
site
layout
plans
under concerned Environmental Permits are shown in Figures
12 - 22.
2.7
Different
parties with different levels of involvement in the Project organisation include:
Project Proponent ¡V Civil
Engineering and Development Department (CEDD)
Supervisor
/ Supervisor's Representative ¡V AECOM Asia Co. Ltd.
Environmental Team (ET) ¡V Wellab Limited
Independent Environmental Checker
(IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The
names and contact numbers of key personnel are summarised in Table
2.2.
Table 2.2 Key Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax
No. |
Civil Engineering and
Development Department, HKSAR (CEDD) |
Project Proponent |
Mr. Ryan Chau |
3797 5387 |
3547
1658 |
Supervisor / Supervisor's Representative (AECOM Asia Co. Ltd.) |
Chief Resident Engineer |
Mr. Alan Lee |
6398
5982 |
2680
9515 |
Senior Resident
Engineer |
Mr. King-man
Chan |
9651
2635 |
2680
9515 |
|
Environmental Team (Wellab
Limited) |
Environmental Team Leader |
Dr. Priscilla Choy |
2898
7388 |
2898 7076 |
Independent
Environmental Checker (MottMac) |
Independent Environmental Checker |
Mr. Thomas Chan |
2828 5967 |
2827 1823 |
Contract No. ND/2019/01 Contractor
(Build King ¡V Richwell Engineering Joint Venture) |
Site Agent |
Mr. Ivan Leung |
9640 8340 |
-- |
Environmental Officer |
Mr. Edward Tam |
9287 8270 |
||
Contract No. ND/2019/02 Contractor
(Chun Wo ¡V Kwan Lee Joint Venture.) |
Site Agent |
Mr. Andy Chan |
3485 9780 |
-- |
Environmental Officer |
Mr. Wesley So |
9144 1643 |
||
Contract No. ND/2019/03 Contractor
(Sang Hing Kuly Joint Venture) |
Site Agent |
Mr. Tang Wing Kai |
9300 7037 |
-- |
Environmental Officer |
Mr. Ken Cheung |
9803 5297 |
||
Contract No. ND/2019/04 Contractor
(Daewoo ¡V Chun Wo ¡V Kwan Lee Joint Venture) |
Site Agent |
Mr. Eric Wu |
9786 8630 |
-- |
Environmental Officer |
Mr. Sam Lam |
6178 3179 |
||
Contract No. ND/2019/05 Contractor
(CRCC ¡V Paul Y. Joint Venture) |
Site Agent |
Mr. Darvin Lo |
9467 5891 |
-- |
Environmental Manager |
Mr. Pan Fong |
9436 9435 |
||
Environmental Officer |
Ms. Iris Ho |
5611 8325 |
||
Contract No. ND/2019/06 Contractor
(New Concepts Engineering Development Ltd.) |
Project Manager |
Mr. Joe
Cheng |
9861 0060 |
-- |
Environmental Officer |
Mr. Alex Choy |
6360 3236 |
||
Contract No. ND/2019/07 Contractor
(China Road and Bridge Corporation) |
Site Agent |
Mr. Mac Chow |
9169 9567 |
-- |
Environmental Officer |
Mr. K. M. Lui |
5113 8223 |
||
Environmental Supervisor |
Mr. Attlee Chau |
6386 9018 |
2.9
The
major site activities undertaken in the reporting month are shown in Table 2.3.
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (October 2023) |
ND/2019/01 |
(a)
Drainage works at Portion 1a (b)
Site formation, socket-H piling and erection of hoarding at
Portion 1c (c)
Temporary storage of material at Portion 1e (d)
Site clearance, site formation, construction of subway, drainage
works and road works at Portion 2 (e)
Sheet piling, drainage works and watermain works at Portion 3 (f)
Watermains works at Portion 5 (g)
Drainage works and backfilling at Portion 6a (h)
Operation of HAC soil treatment facility at Portion 6b (i)
Excavation and drainage works at Portion
7 (j)
Construction of retaining wall, RC construction of fresh water
service reservoir, construction of WSD¡¦s maintenance access, drainage
works, backfilling works and soil nail at Portion 8a (k)
Pipe jacking at LWSC¡¦s car park, trenchless work and watermain construction at Portion
8b (l)
Sheet piling, excavation, drainage and watermain works at Portion
9b (m)
Site clearance and removal of existing
structures at Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road
& Drainage works and watermains works at Yin Kong Road -
Construction of Pavilion at Yin Kong Road (b) Portion 2 to Portion 20C -
Wetland creation & restoration, Dry
agricultural land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) -
Construction of Car Park and Farmer¡¦s Forum |
ND/2019/04 |
(a) Tree Felling (b) Pile Cap (c) Back Filling (d) Excavation (e) Grouting (f) Sheet Piling (g) Road works (h) Formwork Erection (i) Rebar Fixing (j) Pre-drill (k) Bore pile (l)
ELS |
ND/2019/05 |
(a)
South Team -
E3-05M ¡VPile cap completed. Pier construction in
progress. -
E3-04a ¡V ELS in progress. Abandoned pile cap was removed
6 Sep 2023. -
D2-04M ¡V Bored Piling is in progress. P1 was
completed on 26 Sep 2023. P2 is in progress. -
FS04 ¡V Raking drain and middle berm and
construction work completed. -
Works in TWSRE A. BBI
cover walkway (Steelwork) ¡V 1st stage was completed. B. Road
Drains (i.e. gullies and manholes) along Road L201
are completed. C. HKY
Footbridge/Staircase ¡V Installation of subframe and roof in progress. D. HKY
Footbridge/Staircase ¡V Installation of Roof Fabricated Movement Joints
completed. E. Road
D400 leading to L201 Pavement work is completed. F. Diversion
of Traffic to New BBI is completed on 7 Oct 2023. -
Works in TWSRW ¡V A. 11kv
cable laying (FS04) in progress. B. Telecoms
ducts laying (FS06) in progress. C. Sewerage
diversion (DN600 Between TWS1.02 and TWS1.08) is completed. D. Drainage
work ¡V Manhole (FL9110) construction work is completed. E. Gas
Pipe laying (IPA400/HP600 ¡V near HKY entrance) in completed. F. Fresh
and flushing water pipe laying (DN450/DN150 near HKY entrance) is completed. G. Road
construction work (Concrete and bitumen paving ¡V P800 CH350 to CH385) in progress. -
NB109 A. Bay 9
1st pour Wall is completed. B. Bay 10
1st pour Wall is in progress. C. Bay 11
Footing in progress. D. Bay 12
is setting up for Plate Load Test. E. Bay 5
to Bay 8 2nd Wall is in progress. -
NB69 ¡V Bay 5 and Bay 6 Footing are completed. 1st
Wall is in progress. -
NB110 ¡V Bay 3 to 5 Wall completed. Bay 8
Excavation is completed and Footing is in progress. (b)
North Team -
Construction
of pile cap of B2-01 completed. -
Slope
works of FS 30 was in progress. -
Installation
of falsework at C2-01 crosshead completed. -
Dismantling
of formwork for B1-02 Portal Beam construction completed. -
C1-02
portal beam construction in progress. -
C1-01 MJ
portal construction in progress. -
B2-01
pier construction completed -
Construction
of B1- Abutment wall in progress. -
Backfilling
& extraction of sheet pile at C2-02 were in progress. -
Backfilling
at C4-02 were in progress -
Removal
of temporary concrete block platform at D2-01 and debris due to black
rainstorm were in progress. -
JCR:
Traffic diversion of slow lane of northbound of Jockey Club Rd was completed. -
JCR:
Abandoned of gully, removal of existing kerb and
construction of bitumen joint were in progress. -
JCR:
Construction of pipe support for DN 150 exposed pipe was in progress. -
JCR Tong
Hang Village: Construction of cable duct / pits for detection loop/traffic
signal / street light was completed. (c)
Bridges and Structures -
Total 647 segments were casted in Huizhou
casting yard. -
Total 417 segments were delivered to site, and
total 365 segments erected. -
C3-02 T-span segment erection by LG in
progress. -
C2-03 diaphragm construction in completed. -
SOP E2-01 formwork dismantle completed. -
SOP E2-03 construction completed. -
Construction of D2-01 bridge rotation system
and upper turntable in progress. -
LG launch to C3-02 T-span -
Fabricate of steel support at Zheng Zhou for
Bridge B1 in progress (d)
Form Traveler -
Form traveler rebar fixing for 11th pair segment
at E2-02 in progress. -
Form traveler rebar fixing for 03rd pair segment
at D2-02 in progress. -
Dismantling of Form traveler at E3-03 completed. -
FT02 erection at E3-01 in progress. -
FT04 erection at D2-03 in progress. -
FT05 erection at E2-01 in progress. -
Completed concreting E2-E2-02-E2-03-S010,
E2-E2-02-E2-01-S10. -
Completed concreting D2-D2-02-D2-03-S01,
D2-D2-02-D2-01-S01, D2-D2-02-D2-03-S02, D2-D2-02-D2-01-S02. |
ND/2019/06 |
The construction phase was completed and handed over to AFCD
since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at
Portion 2, 3, 4 and 5 (d)
Construction of box culvert at Portion
2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at
Portion 4 (g)
Waterworks at Portion 1, 2 and 4 |
2.10
Copies of Contractors¡¦ construction programmes are
provided in Appendix A.
2.11
A
summary of the relevant permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.4.
Table 2.4 Status
of Environmental Licences, Notifications and Permits
Contract No. |
Permit / Licence No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental
Permit (EP) |
||||
ND/2019/01 |
EP-466/2013/A |
21/11/2013 |
N/A |
Valid |
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-470/2013/A |
21/11/2013 |
N/A |
Valid |
|
ND/2019/02 |
EP-469/2013 |
21/11/2013 |
N/A |
Valid |
ND/2019/03 |
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
|
ND/2019/04 |
EP/473/2013/A |
27/01/2017 |
N/A |
Valid |
EP/546/2017 |
16/11/2017 |
N/A |
Valid |
|
ND/2019/05 |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
ND/2019/06 |
EP-475/2013/A |
13/01/2017 |
N/A |
Valid |
Construction Noise
Permit (CNP) |
||||
ND/2019/01 |
GW-RN0966-23 |
25/09/2023 |
24/12/2023 |
Valid |
GW-RN0426-23 |
19/05/2023 |
18/11/2023 |
Valid |
|
GW-RN0840-23 |
01/09/2023 |
29/02/2024 |
Valid |
|
GW-RN0876-23 |
01/09/2023 |
31/01/2024 |
Valid |
|
GW-RN0802-23 |
16/08/2023 |
14/02/2024 |
Cancelled
and Superseded by GW-RN1057-23 in
reporting month |
|
GW-RN0877-23 |
01/09/2023 |
29/02/2024 |
Valid |
|
GW-RN0997-23 |
01/10/2023 |
31/03/2024 |
Valid |
|
GW-RN1057-23 |
13/10/2023 |
12/01/2024 |
Valid |
|
ND/2019/02 |
GW-RN0747-23 |
01/08/2023 |
31/10/2023 |
Expired
in reporting month |
GW-RN0534-23 |
08/06/2023 |
07/11/2023 |
Valid |
|
GW-RN0873-23 |
01/09/2023 |
31/12/2023 |
Valid |
|
GW-RN0938-23 |
08/09/2023 |
31/12/2023 |
Valid |
|
ND/2019/03 |
GW-RN0733-23 |
01/09/2023 |
29/02/2024 |
Valid |
ND/2019/04 |
GW-RN0709-23 |
13/07/2023 |
12/10/2023 |
Expired
in reporting month |
GW-RN0761-23 |
01/08/2023 |
31/10/2023 |
Expired
in reporting month |
|
GW-RN0799-23 |
06/08/2023 |
31/10/2023 |
Expired
in reporting month |
|
GW-RN0800-23 |
06/08/2023 |
31/10/2023 |
Expired
in reporting month |
|
GW-RN0878-23 |
17/08/2023 |
07/12/2023 |
Valid |
|
GW-RN0920-23 |
27/08/2023 |
26/11/2023 |
Valid |
|
GW-RN0984-23 |
23/09/2023 |
22/12/2023 |
Valid |
|
GW-RN1039-23 |
08/10/2023 |
07/01/2024 |
Valid |
|
GW-RN1101-23 |
13/10/2023 |
12/02/2024 |
Valid |
|
GW-RN1110-23 |
19/10/2023 |
31/12/2023 |
Valid |
|
ND/2019/05 |
GW-RN0765-23 |
18/07/2023 |
17/10/2023 |
Expired
in reporting month |
GW-RN0846-23 |
13/08/2023 |
30/11/2023 |
Valid |
|
GW-RN0847-23 |
13/08/2023 |
30/11/2023 |
Valid |
|
GW-RN0859-23 |
09/08/2023 |
08/11/2023 |
Valid |
|
GW-RN0870-23 |
01/09/2023 |
30/11/2023 |
Valid |
|
GW-RN0897-23 |
01/09/2023 |
29/02/2024 |
Valid |
|
GW-RN0899-23 |
01/09/2023 |
30/11/2023 |
Valid |
|
GW-RN0977-23 |
01/10/2023 |
31/12/2023 |
Valid |
|
GW-RN1062-23 |
09/10/2023 |
30/11/2023 |
Valid |
|
Notification pursuant
to Air Pollution Control (Construction Dust)
Regulation |
||||
ND/2019/01 |
451792 |
11/12/2019 |
N/A |
Valid |
477388 |
02/03/2022 |
N/A |
Valid |
|
ND/2019/02 |
454012 |
05/03/2020 |
N/A |
Valid |
ND/2019/03 |
452216 |
24/12/2019 |
N/A |
Valid |
452332 |
31/12/2019 |
N/A |
Valid |
|
452333 |
31/12/2019 |
N/A |
Valid |
|
ND/2019/04 |
461184 |
23/10/2020 |
N/A |
Valid |
ND/2019/05 |
454323 |
13/03/2020 |
N/A |
Valid |
ND/2019/06 |
449369 |
24/09/2019 |
N/A |
Valid |
ND/2019/07 |
459393 |
28/08/2020 |
N/A |
Valid |
Billing Account for
Disposal of Construction Waste |
||||
ND/2019/01 |
7036265 |
17/01/2020 |
N/A |
Valid |
ND/2019/02 |
7036898 |
01/04/2020 |
N/A |
Valid |
ND/2019/03 |
7036378 |
22/01/2020 |
N/A |
Valid |
ND/2019/04 |
7038391 |
22/09/2020 |
N/A |
Valid |
ND/2019/05 |
7036901 |
01/04/2020 |
N/A |
Valid |
ND/2019/06 |
7035473 |
17/10/2019 |
N/A |
Valid |
ND/2019/07 |
7038309 |
14/09/2020 |
N/A |
Valid |
Registration
of Chemical Waste Producer |
||||
ND/2019/01 |
5213-545-B2578-01 |
10/01/2020 |
N/A |
Valid |
ND/2019/02 |
5213-548-C4439-01 |
06/05/2020 |
N/A |
Valid |
ND/2019/03 |
5213-623-S4231-01 |
14/04/2020 |
N/A |
Valid |
ND/2019/04 |
5211-624-D2709-01 |
26/11/2020 |
N/A |
Valid |
ND/2019/05 |
5213-625-C4464-01 |
20/05/2020 |
N/A |
Valid |
ND/2019/06 |
5213-625-N2716-01 |
02/10/2019 |
N/A |
Valid |
ND/2019/07 |
5213-625-C4498-01 |
21/09/2020 |
N/A |
Valid |
Effluent
Discharge License under Water Pollution Control Ordinance |
||||
ND/2019/01 |
WT00036071-2020 |
22/06/2020 |
30/06/2025 |
Valid |
WT00036073-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036067-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036075-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036076-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00037191-2020 |
21/04/2022 |
28/02/2026 |
Valid |
|
WT00037204-2020 |
16/11/2022 |
28/02/2026 |
Valid |
|
WT00037412-2021 |
16/11/2022 |
30/04/2026 |
Valid |
|
WT00037564-2021 |
19/04/2021 |
30/04/2026 |
Valid |
|
WT00037886-2021 |
28/06/2021 |
30/06/2026 |
Valid |
|
WT00041311-2022 |
21/06/2022 |
30/06/2027 |
Valid |
|
ND/2019/02 |
WT00036584-2020 |
21/10/2020 |
31/10/2025 |
Valid |
WT00036952-2020 |
17/12/2020 |
31/12/2025 |
Valid |
|
ND/2019/03 |
WT00035847-2020 |
12/08/2020 |
31/08/2025 |
Valid |
WT00036414-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
WT00037771-2021 |
08/07/2021 |
31/07/2026 |
Valid |
|
WT00035984-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
ND/2019/04 |
WT00037539-2021 |
02/06/2022 |
30/04/2026 |
Valid |
ND/2019/05 |
WT00036996-2020 |
22/12/2020 |
31/12/2025 |
Valid |
ND/2019/06 |
WT00035415-2019 |
20/03/2020 |
31/03/2025 |
Valid |
ND/2019/07 |
WT00037526-2021 |
21/04/2022 |
31/05/2026 |
Valid |