Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (October 2023) |
ND/2019/01 |
(a)
Drainage works at Portion 1a (b)
Site formation, socket-H piling and erection of hoarding at
Portion 1c (c)
Temporary storage of material at Portion 1e (d)
Site clearance, site formation, construction of subway, drainage
works and road works at Portion 2 (e)
Sheet piling, drainage works and watermain works at Portion 3 (f)
Watermains works at Portion 5 (g)
Drainage works and backfilling at Portion 6a (h)
Operation of HAC soil treatment facility at Portion 6b (i)
Excavation and drainage works at Portion
7 (j)
Construction of retaining wall, RC construction of fresh water
service reservoir, construction of WSD¡¦s maintenance access, drainage
works, backfilling works and soil nail at Portion 8a (k)
Pipe jacking at LWSC¡¦s car park, trenchless work and watermain construction at Portion
8b (l)
Sheet piling, excavation, drainage and watermain works at Portion
9b (m)
Site clearance and removal of existing
structures at Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road
& Drainage works and watermains works at Yin Kong Road -
Construction of Pavilion at Yin Kong Road (b) Portion 2 to Portion 20C -
Wetland creation & restoration, Dry
agricultural land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) -
Construction of Car Park and Farmer¡¦s Forum |
ND/2019/04 |
(a) Tree Felling (b) Pile Cap (c) Back Filling (d) Excavation (e) Grouting (f) Sheet Piling (g) Road works (h) Formwork Erection (i) Rebar Fixing (j) Pre-drill (k) Bore pile (l)
ELS |
ND/2019/05 |
(a)
South Team -
E3-05M ¡VPile cap completed. Pier construction in
progress. -
E3-04a ¡V ELS in progress. Abandoned pile cap was removed
6 Sep 2023. -
D2-04M ¡V Bored Piling is in progress. P1 was
completed on 26 Sep 2023. P2 is in progress. -
FS04 ¡V Raking drain and middle berm and
construction work completed. -
Works in TWSRE A. BBI
cover walkway (Steelwork) ¡V 1st stage was completed. B. Road
Drains (i.e. gullies and manholes) along Road L201
are completed. C. HKY
Footbridge/Staircase ¡V Installation of subframe and roof in progress. D. HKY
Footbridge/Staircase ¡V Installation of Roof Fabricated Movement Joints
completed. E. Road
D400 leading to L201 Pavement work is completed. F. Diversion
of Traffic to New BBI is completed on 7 Oct 2023. -
Works in TWSRW ¡V A. 11kv
cable laying (FS04) in progress. B. Telecoms
ducts laying (FS06) in progress. C. Sewerage
diversion (DN600 Between TWS1.02 and TWS1.08) is completed. D. Drainage
work ¡V Manhole (FL9110) construction work is completed. E. Gas
Pipe laying (IPA400/HP600 ¡V near HKY entrance) in completed. F. Fresh
and flushing water pipe laying (DN450/DN150 near HKY entrance) is completed. G. Road
construction work (Concrete and bitumen paving ¡V P800 CH350 to CH385) in progress. -
NB109 A. Bay 9
1st pour Wall is completed. B. Bay 10
1st pour Wall is in progress. C. Bay 11
Footing in progress. D. Bay 12
is setting up for Plate Load Test. E. Bay 5
to Bay 8 2nd Wall is in progress. -
NB69 ¡V Bay 5 and Bay 6 Footing are completed. 1st
Wall is in progress. -
NB110 ¡V Bay 3 to 5 Wall completed. Bay 8
Excavation is completed and Footing is in progress. (b)
North Team -
Construction
of pile cap of B2-01 completed. -
Slope
works of FS 30 was in progress. -
Installation
of falsework at C2-01 crosshead completed. -
Dismantling
of formwork for B1-02 Portal Beam construction completed. -
C1-02
portal beam construction in progress. -
C1-01 MJ
portal construction in progress. -
B2-01
pier construction completed -
Construction
of B1- Abutment wall in progress. -
Backfilling
& extraction of sheet pile at C2-02 were in progress. -
Backfilling
at C4-02 were in progress -
Removal
of temporary concrete block platform at D2-01 and debris due to black
rainstorm were in progress. -
JCR:
Traffic diversion of slow lane of northbound of Jockey Club Rd was completed. -
JCR:
Abandoned of gully, removal of existing kerb and
construction of bitumen joint were in progress. -
JCR:
Construction of pipe support for DN 150 exposed pipe was in progress. -
JCR Tong
Hang Village: Construction of cable duct / pits for detection loop/traffic
signal / street light was completed. (c)
Bridges and Structures -
Total 647 segments were casted in Huizhou
casting yard. -
Total 417 segments were delivered to site, and
total 365 segments erected. -
C3-02 T-span segment erection by LG in
progress. -
C2-03 diaphragm construction in completed. -
SOP E2-01 formwork dismantle completed. -
SOP E2-03 construction completed. -
Construction of D2-01 bridge rotation system
and upper turntable in progress. -
LG launch to C3-02 T-span -
Fabricate of steel support at Zheng Zhou for
Bridge B1 in progress (d)
Form Traveler -
Form traveler rebar fixing for 11th pair segment
at E2-02 in progress. -
Form traveler rebar fixing for 03rd pair segment
at D2-02 in progress. -
Dismantling of Form traveler at E3-03 completed. -
FT02 erection at E3-01 in progress. -
FT04 erection at D2-03 in progress. -
FT05 erection at E2-01 in progress. -
Completed concreting E2-E2-02-E2-03-S010,
E2-E2-02-E2-01-S10. -
Completed concreting D2-D2-02-D2-03-S01,
D2-D2-02-D2-01-S01, D2-D2-02-D2-03-S02, D2-D2-02-D2-01-S02. |
ND/2019/06 |
The construction phase was completed and handed over to AFCD
since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at
Portion 2, 3, 4 and 5 (d)
Construction of box culvert at Portion
2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at
Portion 4 (g)
Waterworks at Portion 1, 2 and 4 |