The
Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs) are one of the important sources of land
and housing supply in the medium and long term. The development of the KTN and
FLN NDAs will be implemented in phase for full completion by 2031. The Phase 1
of the NDAs development, comprising the Advance Works and First Stage Works, is
targeted to be implemented from the second half of 2019 progressively. The
Advance and First Stage Works would include site formation, engineering
infrastructure works (including roads, drainage, sewerage, waterworks,
landscaping works, pumping stations, and fresh water and flushing water service
reservoirs), soil remediation, reprovisioning of North District Temporary
Wholesale Market, development of a nature park at Long Valley and
implementation of environmental mitigation measures.
2.2
The
scope of works under the Advance and First Stage Works comprises the following:
a)
The
Advance Works (PWP item No. 7747CL-2) consist of:
i)
site
formation of land (including soil remediation) in KTN and FLN NDAs for housing,
community facilities and engineering infrastructure;
ii)
construction
of roads including the eastern section of Fanling
Bypass (FLBP(E)) connecting the FLN NDA to Fanling
Highway and other roads with footpaths and cycle tracks, and associated
junction/ road improvements;
iii)
engineering
infrastructure works including drainage. Sewerage (including two sewage pumping stations), waterworks (including a fresh
water service reservoir and a flushing water service reservoir in the KTN NDA),
landscape works and slopeworks;
iv)
part
expansion and upgrading of Shek Wu Hui Sewage Treatment Works (SWHSTW);
v)
reprovisioning
works; and
vi)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (v) above.
b)
The
First Stage Works (PWP item No. 7759CL) consist of:
i)
development
of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung Yue River
for connection between these two facilities;
ii)
reprovisioning
of two egretry sites in the FLN NDA and enhancement
works to an existing egretry site in the KTN NDA;
iii)
site
formation of land for a village resite
area and a district police station in the KTN NDA;
iv)
engineering
infrastructure works including roads, drainage, sewerage, waterbirds, and
landscape works; and
v)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (iv) above.
2.3
The
Project which covers KTN and FLN NDAs is a designated project (DP) under
Schedule 3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499).
In October 2013, the EIA Report (AEIAR-175/2013) for the Project was approved
by the Director of Environmental Protection pursuant to the EIA Ordinance. The
relevant EPs under the Project and the respective Work Contracts are summarised in Tables
2.1a and 2.1.b.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP No. |
Designated Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
¡@ |
|||||||
Kwu Tung North New
Development Area Road P1 and P2 and Associated New Kwu
Tung Interchange and Pak Shek Au Interchange Improvement |
ü |
¡@ |
|||||||
Kwu Tung North New
Development Area Road D1 to D5 |
ü |
ü |
¡@ |
||||||
Sewage Pumping Stations in Kwu
Tung North New Development Area |
ü |
¡@ |
|||||||
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
|||||||
Fanling Bypass Eastern
Section |
ü |
ü |
ü |
¡@ |
|||||
Reprovision of temporary Wholesale Market in Fanling North New Development Area |
ü |
¡@ |
|||||||
EP-546/2017 |
Fanling North Temporary
Sewage Pumping Station |
ü |
¡@ |
Notes:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope of Works under concerned EP
Environmental
Permit (EP) No. |
Work
Contract(s) |
Scope
of Works under concerned EP(s) |
Site
Layout Plan under concerned EP(s) |
EP-466/2013/A(Part) |
C1 |
Realign Castle Peak Road and join with the Pak Shek
Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction of new primary distributor road (P1)
within Kwu Tung North New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction of new primary distributor roads (D1,
D3, D4 and part of D5) within Kwu Tung North New
Development Area |
Figure 14 |
C3 |
Development of a nature park at Long Valley and ecological
mitigation and enhancement works for the nature park (Condition 2.9) |
Figure 15 |
|
EP-469/2013(Part) |
C2 |
Construction of one sewage pumping station in Kwu Tung North with installed capacity of more than 2,000
m3 per day |
Figure 16 |
EP-470/2013/A(Part) |
C1 |
Construction of service reservoir and watermain
for the reuse of treated sewage effluent for reuse in Kwu
Tung North Development Areas |
Figure 17 |
EP-473/2013/A(Part) |
C3 |
Establishment of alternative egretry sites and enhance
the existing egretry site at Ho Sheung Heung and/or
its vicinity (Condition 2.7) |
Figure 18 |
EP-473/2013/A(Part) |
C5A |
Construction of new district distributor inside
FLN NDA, which provides a linkage between the Man Kam To
Road and the proposed Fanling Bypass Eastern
Section |
Figure 19 |
EP-473/2013/A(Part) |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The re-provisioned wholesale market will have
approximately 1,000 market stalls within a site area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a temporary sewage pumping
station in Fanling North with installed capacity
(average dry weather flow) of about 3,600m3/day |
Figure 22 |
Remark: The EP(s) not related to the Project of the First Phase of the Kwu
Tung North (KTN) and Fanling North (FLN) New Development
Area (NDA) Development Areas are not included in the Table.
2.4
The
site boundary of the Project and all Works Contracts are shown in Drawing No. 1.
2.5
The
required submissions and submission status under Environmental Permits are
shown in Appendix U.
2.6
The
site
layout
plans
under concerned Environmental Permits are shown in Figures
12 - 22.
2.7
Different
parties with different levels of involvement in the Project organisation include:
Project Proponent ¡V Civil
Engineering and Development Department (CEDD)
Supervisor
/ Supervisor's Representative ¡V AECOM Asia Co. Ltd.
Environmental Team (ET) ¡V Wellab Limited
Independent Environmental Checker
(IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The
names and contact numbers of key personnel are summarised in Table
2.2.
Table 2.2 Key Contacts of the
Project
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
Civil
Engineering and Development Department, HKSAR (CEDD) |
Project Proponent |
Mr. Ryan
Chau |
3797
5387 |
3547 1658 |
Supervisor /
Supervisor's Representative (AECOM
Asia Co. Ltd.) |
Chief
Resident Engineer |
Mr. Alan
Lee |
6398 5982 |
2680 9515 |
Senior
Resident Engineer |
Mr. King-man Chan |
9651 2635 |
2680 9515 |
|
Environmental
Team (Wellab Limited) |
Environmental Team Leader |
Dr.
Priscilla Choy |
2898 7388 |
2898 7076 |
Independent Environmental Checker (MottMac) |
Independent
Environmental Checker |
Mr. Thomas
Chan |
2828
5967 |
2827
1823 |
Contract No. ND/2019/01 Contractor (Build King ¡V Richwell
Engineering Joint Venture) |
Site Agent |
Mr. Ivan
Leung |
9640 8340 |
-- |
Environmental
Officer |
Mr. Edward
Tam |
9287 8270 |
||
Contract No. ND/2019/02 Contractor (Chun Wo ¡V Kwan Lee Joint Venture.) |
Site Agent |
Mr. Andy
Chan |
3485 9780 |
-- |
Environmental
Officer |
Mr. Wesley
So |
9144 1643 |
||
Contract No. ND/2019/03 Contractor (Sang Hing Kuly
Joint Venture) |
Site Agent |
Mr. Tang
Wing Kai |
9300 7037 |
-- |
Environmental
Officer |
Mr. Ken
Cheung |
9803
5297 |
||
Contract No. ND/2019/04 Contractor (Daewoo ¡V Chun Wo ¡V Kwan Lee Joint
Venture) |
Site Agent |
Mr. Eric
Wu |
9786
8630 |
-- |
Environmental
Officer |
Mr. Sam
Lam |
6178
3179 |
||
Contract No. ND/2019/05 Contractor (CRCC ¡V Paul Y. Joint Venture) |
Site Agent |
Mr. Darvin
Lo |
9467
5891 |
-- |
Environmental
Manager |
Mr. Pan
Fong |
9436
9435 |
||
Environmental
Officer |
Ms. Iris
Ho |
5611
8325 |
||
Contract No. ND/2019/06 Contractor (New Concepts Engineering Development
Ltd.) |
Project Manager |
Mr. Joe Cheng |
9861 0060 |
-- |
Environmental
Officer |
Mr. Alex
Choy |
6360
3236 |
||
Contract No. ND/2019/07 Contractor (China Road and Bridge Corporation) |
Site Agent |
Mr. Mac
Chow |
9169
9567 |
-- |
Environmental
Officer |
Mr. K. M.
Lui |
5113
8223 |
||
Environmental
Supervisor |
Mr. Attlee
Chau |
6386
9018 |
2.9
The
major site activities undertaken in the reporting month are shown in Table 2.3.
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (November 2023) |
ND/2019/01 |
(a)
Drainage works
and sheet piles in Portion 1a (b)
Site
formation, socket-H piling and erection of hoarding
in Portion 1c (c)
Temporary
storage of material in Portion 1e (d)
Site
clearance, site formation, construction of subway, drainage works and road
works in Portion 2 (e)
Sheet
piling, drainage works and watermain works in Portion 3 (f)
Watermain
works in Portion 5 (g)
Backfilling,
drainage and watermains works in Portion 6a (h)
Operation
of HAC treatment facility in Portion 6b (i)
Excavation
and drainage works in Portion 7 (j)
Construction
of retaining wall, RC construction of fresh water reservoir, construction of
WSD¡¦s maintenance access, drainage works, backfilling works and soil nail in
Portion 8a (k)
Pipe
jacking at LWSC¡¦s carpark, trenchless work and watermain construction in
Portion 8b (l)
Sheet
piling, excavation, drainage and watermain works in Portion 9b (m)
Site clearance, removal of existing structure in
Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road
& Drainage works and watermains works at Yin Kong Road -
Construction of Pavilion at Yin Kong Road (b) Portion 2 to Portion 20C -
Wetland creation & restoration, Dry agricultural
land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) -
Construction of Car Park and Farmer¡¦s Forum |
ND/2019/04 |
(a)
Tree Pruning (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork and Scaffolding Erection (i)
Rebar Fixing (j)
Bore pile (k)
ELS |
ND/2019/05 |
(a)
South Team -
E3-05M ¡VPile cap completed. Pier construction in
progress. -
E3-04a ¡VPilecap
completed. Column construction in progress. -
E3-04b ¡V ELS in progress -
E4-01 ¡V ELS in progress -
D2-04M ¡V Bored Piling is in progress. 3 out of 4
Piles were completed on 8 Nov 2023. P4 is in progress. -
FS04 ¡V Raking drain and middle berm construction
shall resume in 15 Nov 2023. -
Works in TWSRE A. BBI
cover walkway (Steelwork) ¡V 1st stage was completed. B. HKY
Footbridge/Staircase ¡V Installation of subframe and roof in progress. -
Works in TWSRW A. 11kv
cable laying (FS04) was completed. B. Telecoms
ducts laying (FS04 and FW06) was completed. C. Drainage
work ¡V Laying 2x1200Dia Pipes to Manhole (FL9110) is in progress. D. Gas
Pipe laying (IPA400/HP600 ¡V near HKY entrance) in completed. E. Fresh
and flushing water pipe laying (DN450/DN150 near HKY entrance) is completed. F. Road
construction work (Concrete and bitumen paving ¡V P800 CH350 to CH385) in
progress. -
NB109 A. Bay 9
1st pour Wall is completed. B. Bay 11
Footing was completed. 1st Wall is in progress. C. Bay 12
Plate Load Test is completed. Footing construction is in progress. D. Bay 5
to Bay 8 2nd Wall is in progress. -
NB69 A. Bay 5,
Bay 6 ¡V 1st Wall was completed. B. Bay 2,
Bay 7 ¡V ELS is in porgress. -
NB110 A. Bay 3
to 5 was completed. Backfilling to formation is in progress. B. Bay 8
was completed on 10 Nov 2023. (b)
North Team -
Slope
works of FS 28 completed. -
Slope
works of FS 30 was in progress. -
Installation
of formwork at C2-01 crosshead completed. -
Dismantling
of steel beam for B1-02 Portal Beam construction in progress. -
Truss
erection for C1-02 portal beam construction completed. -
Truss erection
for C1-01 MJ portal construction in progress. -
Falsework
erection for B2-02 & B2-03 cross head construction in progress -
D2-01
pier construction completed. -
Construction
of B1- Abutment wall- phase 1 completed. -
Backfilling
& extraction of sheet pile at C2-02 were in progress. -
Backfilling
at C4-02 & C4-01a were in progress -
Removal
of temporary concrete block platform at D2-01 and debris due to black
rainstorm were completed. -
JCR:
Permeant bitumen pavement works was in progress -
JCR:
Construction of pipe support for DN 150 exposed pipe was in progress. -
JCR Tong
Hang Village: Preparation works for upcoming works of box-culvert &
retaining wall completed. Construction of retaining walls were in progress. -
Construction
of manhole & associated DN 900 drain pipe were
in progress. -
Proposed
DSD River gauge was hand-over to DSD. (c)
Bridges and Structures -
Total 692 segments were casted in Huizhou
casting yard. -
Total 456 segments were delivered to site, and
total 365 segments erected. -
C3-01 T-span segment erection by LG completed -
Construction of D2-01 bridge rotation system
and upper turntable completed. -
LG launch to C2-04 in progress -
Fabricate of steel support at Zheng Zhou for
Bridge B1 in progress -
Bridge B1 construction in progress. (d)
Form Traveler -
Form traveler rebar fixing for 13th pair segment
at E2-02 in progress. -
Form traveler rebar fixing for 02nd pair segment
at E3-01 in progress. -
Form traveler rebar fixing for 05th pair segment
at D2-02 in progress. -
FT02 erection at E3-01 completed. -
FT04 erection at D2-03 completed. -
FT05 erection at E2-01 in progress. -
Completed concreting E2-E2-02-E2-03-S011,
E2-E2-02-E2-01-S11. E2-E2-02-E2-03-S012, E2-E2-02-E2-01-S12. -
Completed concreting D2-D2-02-D2-03-S03,
D2-D2-02-D2-01-S03, D2-D2-02-D2-03-S04, D2- D2-02-D2-01-S04. -
Completed concreting D2-D2-03-D2-04-S01,
D2-D2-03-D2-02-S01, E3-E3-01-E2-03-S02 |
ND/2019/06 |
The construction phase was completed and handed over to AFCD
since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at
Portion 2, 3, 4 and 5 (d)
Construction of box culvert at Portion
2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at
Portion 4 (g)
Waterworks at Portion 1, 2 and 4 |
2.10
Copies of Contractors¡¦ construction programmes are
provided in Appendix A.
2.11
A
summary of the relevant permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.4.
Table 2.4 Status
of Environmental Licences, Notifications and Permits
Contract
No. |
Permit / Licence No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental Permit
(EP) |
||||
ND/2019/01 |
EP-466/2013/A |
21/11/2013 |
N/A |
Valid |
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-470/2013/A |
21/11/2013 |
N/A |
Valid |
|
ND/2019/02 |
EP-469/2013 |
21/11/2013 |
N/A |
Valid |
ND/2019/03 |
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
|
ND/2019/04 |
EP/473/2013/A |
27/01/2017 |
N/A |
Valid |
EP/546/2017 |
16/11/2017 |
N/A |
Valid |
|
ND/2019/05 |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
ND/2019/06 |
EP-475/2013/A |
13/01/2017 |
N/A |
Valid |
Construction Noise Permit (CNP) |
||||
ND/2019/01 |
GW-RN0426-23 |
19/05/2023 |
18/11/2023 |
Expired in reporting month |
GW-RN0966-23 |
25/09/2023 |
24/12/2023 |
Valid |
|
GW-RN0840-23 |
01/09/2023 |
29/02/2024 |
Valid |
|
GW-RN0876-23 |
01/09/2023 |
31/01/2024 |
Valid |
|
GW-RN0877-23 |
01/09/2023 |
29/02/2024 |
Valid |
|
GW-RN0997-23 |
01/10/2023 |
31/03/2024 |
Valid |
|
GW-RN1057-23 |
13/10/2023 |
12/01/2024 |
Valid |
|
GW-RN1224-23 |
21/11/2023 |
20/02/2024 |
Valid |
|
GW-RN1146-23 |
19/11/2023 |
18/05/2024 |
Valid |
|
ND/2019/02 |
GW-RN0534-23 |
08/06/2023 |
07/11/2023 |
Expired in reporting month |
GW-RN0873-23 |
01/09/2023 |
31/12/2023 |
Valid |
|
GW-RN0938-23 |
08/09/2023 |
31/12/2023 |
Cancelled and superseded by GW-RN1178-23 In the reporting month |
|
GW-RN1163-23 |
08/11/2023 |
07/04/2024 |
Valid |
|
GW-RN1178-23 |
10/11/2023 |
09/02/2024 |
Valid |
|
ND/2019/03 |
GW-RN0733-23 |
01/09/2023 |
29/02/2024 |
Valid |
ND/2019/04 |
GW-RN0920-23 |
27/08/2023 |
26/11/2023 |
Expired in reporting month |
GW-RN1101-23 |
13/10/2023 |
12/02/2024 |
Cancelled by EPD in the reporting month |
|
GW-RN0878-23 |
17/08/2023 |
07/12/2023 |
Valid |
|
GW-RN0984-23 |
23/09/2023 |
22/12/2023 |
Valid |
|
GW-RN1110-23 |
19/10/2023 |
31/12/2023 |
Valid |
|
GW-RN1039-23 |
08/10/2023 |
07/01/2024 |
Valid |
|
ND/2019/05 |
GW-RN0846-23 |
13/08/2023 |
30/11/2023 |
Cancelled and superseded by GW-RN1197-23 In the reporting month |
GW-RN0847-23 |
13/08/2023 |
30/11/2023 |
Expired in reporting month |
|
GW-RN0859-23 |
09/08/2023 |
08/11/2023 |
Expired in reporting month |
|
GW-RN0870-23 |
01/09/2023 |
30/11/2023 |
Expired in reporting month |
|
GW-RN0899-23 |
01/09/2023 |
30/11/2023 |
Expired in reporting month |
|
GW-RN1062-23 |
09/10/2023 |
30/11/2023 |
Expired in reporting month |
|
GW-RN0897-23 |
01/09/2023 |
29/02/2024 |
Valid |
|
GW-RN0977-23 |
01/10/2023 |
31/12/2023 |
Valid |
|
GW-RN1138-23 |
09/11/2023 |
31/01/2024 |
Valid |
|
GW-RN1197-23 |
06/11/2023 |
30/11/2023 |
Expired in reporting month |
|
Notification pursuant to Air Pollution Control
(Construction Dust) Regulation |
||||
ND/2019/01 |
451792 |
11/12/2019 |
N/A |
Valid |
477388 |
02/03/2022 |
N/A |
Valid |
|
ND/2019/02 |
454012 |
05/03/2020 |
N/A |
Valid |
ND/2019/03 |
452216 |
24/12/2019 |
N/A |
Valid |
452332 |
31/12/2019 |
N/A |
Valid |
|
452333 |
31/12/2019 |
N/A |
Valid |
|
ND/2019/04 |
461184 |
23/10/2020 |
N/A |
Valid |
ND/2019/05 |
454323 |
13/03/2020 |
N/A |
Valid |
ND/2019/06 |
449369 |
24/09/2019 |
N/A |
Valid |
ND/2019/07 |
459393 |
28/08/2020 |
N/A |
Valid |
Billing Account for Disposal of Construction Waste |
||||
ND/2019/01 |
7036265 |
17/01/2020 |
N/A |
Valid |
ND/2019/02 |
7036898 |
01/04/2020 |
N/A |
Valid |
ND/2019/03 |
7036378 |
22/01/2020 |
N/A |
Valid |
ND/2019/04 |
7038391 |
22/09/2020 |
N/A |
Valid |
ND/2019/05 |
7036901 |
01/04/2020 |
N/A |
Valid |
ND/2019/06 |
7035473 |
17/10/2019 |
N/A |
Valid |
ND/2019/07 |
7038309 |
14/09/2020 |
N/A |
Valid |
Registration of Chemical Waste Producer |
||||
ND/2019/01 |
5213-545-B2578-01 |
10/01/2020 |
N/A |
Valid |
ND/2019/02 |
5213-548-C4439-01 |
06/05/2020 |
N/A |
Valid |
ND/2019/03 |
5213-623-S4231-01 |
14/04/2020 |
N/A |
Valid |
ND/2019/04 |
5211-624-D2709-01 |
26/11/2020 |
N/A |
Valid |
ND/2019/05 |
5213-625-C4464-01 |
20/05/2020 |
N/A |
Valid |
ND/2019/06 |
5213-625-N2716-01 |
02/10/2019 |
N/A |
Valid |
ND/2019/07 |
5213-625-C4498-01 |
21/09/2020 |
N/A |
Valid |
Effluent Discharge License under Water Pollution
Control Ordinance |
||||
ND/2019/01 |
WT00036071-2020 |
22/06/2020 |
30/06/2025 |
Valid |
WT00036073-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036067-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036075-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036076-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00037191-2020 |
21/04/2022 |
28/02/2026 |
Valid |
|
WT00037204-2020 |
16/11/2022 |
28/02/2026 |
Valid |
|
WT00037412-2021 |
16/11/2022 |
30/04/2026 |
Valid |
|
WT00037564-2021 |
19/04/2021 |
30/04/2026 |
Valid |
|
WT00037886-2021 |
28/06/2021 |
30/06/2026 |
Valid |
|
WT00041311-2022 |
21/06/2022 |
30/06/2027 |
Valid |
|
ND/2019/02 |
WT00036584-2020 |
21/10/2020 |
31/10/2025 |
Valid |
WT00036952-2020 |
17/12/2020 |
31/12/2025 |
Valid |
|
ND/2019/03 |
WT00035847-2020 |
12/08/2020 |
31/08/2025 |
Valid |
WT00036414-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
WT00037771-2021 |
08/07/2021 |
31/07/2026 |
Valid |
|
WT00035984-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
ND/2019/04 |
WT00037539-2021 |
02/06/2022 |
30/04/2026 |
Valid |
ND/2019/05 |
WT00036996-2020 |
22/12/2020 |
31/12/2025 |
Valid |
ND/2019/06 |
WT00035415-2019 |
20/03/2020 |
31/03/2025 |
Valid |
ND/2019/07 |
WT00037526-2021 |
21/04/2022 |
31/05/2026 |
Valid |