Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site Activities (December 2023 to February 2024) |
ND/2019/01 |
(a)
Drainage
works and sheet piles in Portion 1a (b)
Site formation,
stockpile of soil, erection of hoarding and construction of noise barrier in
Portion 1c (c)
Temporary
storage of material in Portion 1e (d)
Site
formation work, construction of subway, road works and drainage works in Portion 2 (e)
Excavation,
backfilling, drainage and watermain works in Portion 3 (f)
Watermain
works, excavation, backfilling, road works, sheet piling and pipe jacking in
Portion 5 (g)
Drainage
works, backfilling, road works and watermains works in Portion 6a (h)
Operation
of HAC treatment facility in Portion 6b (i)
Sheet
piling, excavation, stockpile of soil, drainage works and watermain work in
Portion 7 (j)
Construction
of retaining wall, RC construction of fresh water reservoir, excavation at WSD¡¦s
maintenance access, backfilling works, drainage works, soil nail and pipe pile wall
installation in Portion 8a (k)
Trenchless
work, excavation, watermain works and ground treatment in Portion 8b (l)
Sheet
piling, excavation, road works, drainage works and watermain works in Portion
9b (m)
Removal of existing structure in Portion 11b (n)
Site clearance, tree felling, removal of existing
structure and stockpile of soil in Portion 13 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Construction of Pavilion at Yin Kong Road (b)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry
agricultural land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) -
Construction of Car Park and Farmer¡¦s Forum |
ND/2019/04 |
(a)
Tree Pruning (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork and Scaffolding Erection (i)
Rebar Fixing (j)
Bore pile (k)
ELS |
ND/2019/05 |
(a)
North Team Works -
Backfilling and drainage work at C4-02 &
C4-01. -
Backfilling at C2-02, C3-03 & portion II. -
Slope works at On Lok Garden FS 30. -
Extraction of sheet pile in abutment B1 and
construction of remaining abutment wall near portal B2-01. -
Construction of FW 53. -
Water works at Jockey Club Rd. -
Road works of northbound of Jockey Club Rd &
ducting works at central median. -
Sampling of existing pavement in southbound of
Jockey Club Rd. -
Construction of new box culvert & retaining
wall at Tong Hang Tsuen -
Drainage works ¡V DN 900 at On Kui Street near B1. -
pier head construction at D2-01. -
Cross head construction at B2-01, B2-02 &
B2-03. (b)
Viaduct Works -
Segment fabrication for bridge C2, C1, D1, D2,
E1, E4 -
Segments erection by LG at bridges C3, C2 -
SOP construction at D2-01 -
Construction of Bridge B1 -
Parapet skin fabrication and parapet
construction. (c)
South Team Works -
TWSRW ¡V
Road work and UUs laying (Section P800 CH 450 to 600). -
TWSRW ¡V
Construction of lower berm and Hydroseeding at FS04. -
TWSRW -
CLP 11 kv cable diversion work (1ST) -
TWSRW ¡V
Gas (IPA400 and HP600) diversion work -
TWSRW ¡V Foundation
work of D2-04M -
HKY FB
(East) ¡V Installation of cladding and E&M works. -
HKY FB
(West) ¡V Construction of LT2 (Mini-piles) -
E3-04a,
E304b, E4-01 and E4-02 ¡V cap construction -
E305M
Pier Head construction -
NB109 ¡V
Bay 11~12 base slab construction. Bay 5 to 12 wall construction. -
NB69 ¡V
Bay 2~8 ELS works -
NB110 ¡V
Bay 6~7 ELS works -
Demolish
Existing NB74 and BBI -
Removal
Sign Gantry DS64 (d)
Form Traveler -
E3-01 ¡V construction 3rd to 6th pair -
E2-02 ¡V construction 14th pair &
dismantling of FT1 -
D2-02 ¡V construction 06th to 8th pair -
D2-03 ¡V construction 2nd pair to 4th pair -
E2-01 - erection of 5th set of form traveler. |
ND/2019/06 |
The construction phase has been completed
and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1,
2, 4 and 5 (c)
Construction of box culvert at Portion
2 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at
Portion 4 (f)
Drainage works, Sewerage works at
Portion 2, 3, 4 and 5 (g)
Construction of noise barrier at
Portion 4 and 5 (h)
Waterworks at Portion 1, 2 and 4 |