Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (November 2023) |
ND/2019/01 |
(a)
Drainage works
and sheet piles in Portion 1a (b)
Site
formation, socket-H piling and erection of hoarding
in Portion 1c (c)
Temporary
storage of material in Portion 1e (d)
Site
clearance, site formation, construction of subway, drainage works and road
works in Portion 2 (e)
Sheet
piling, drainage works and watermain works in Portion 3 (f)
Watermain
works in Portion 5 (g)
Backfilling,
drainage and watermains works in Portion 6a (h)
Operation
of HAC treatment facility in Portion 6b (i)
Excavation
and drainage works in Portion 7 (j)
Construction
of retaining wall, RC construction of fresh water reservoir, construction of
WSD¡¦s maintenance access, drainage works, backfilling works and soil nail in
Portion 8a (k)
Pipe
jacking at LWSC¡¦s carpark, trenchless work and watermain construction in
Portion 8b (l)
Sheet
piling, excavation, drainage and watermain works in Portion 9b (m)
Site clearance, removal of existing structure in
Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road
& Drainage works and watermains works at Yin Kong Road -
Construction of Pavilion at Yin Kong Road (b) Portion 2 to Portion 20C -
Wetland creation & restoration, Dry agricultural
land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) -
Construction of Car Park and Farmer¡¦s Forum |
ND/2019/04 |
(a)
Tree Pruning (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork and Scaffolding Erection (i)
Rebar Fixing (j)
Bore pile (k)
ELS |
ND/2019/05 |
(a)
South Team -
E3-05M ¡VPile cap completed. Pier construction in
progress. -
E3-04a ¡VPilecap
completed. Column construction in progress. -
E3-04b ¡V ELS in progress -
E4-01 ¡V ELS in progress -
D2-04M ¡V Bored Piling is in progress. 3 out of 4
Piles were completed on 8 Nov 2023. P4 is in progress. -
FS04 ¡V Raking drain and middle berm construction
shall resume in 15 Nov 2023. -
Works in TWSRE A. BBI
cover walkway (Steelwork) ¡V 1st stage was completed. B. HKY
Footbridge/Staircase ¡V Installation of subframe and roof in progress. -
Works in TWSRW A. 11kv
cable laying (FS04) was completed. B. Telecoms
ducts laying (FS04 and FW06) was completed. C. Drainage
work ¡V Laying 2x1200Dia Pipes to Manhole (FL9110) is in progress. D. Gas
Pipe laying (IPA400/HP600 ¡V near HKY entrance) in completed. E. Fresh
and flushing water pipe laying (DN450/DN150 near HKY entrance) is completed. F. Road
construction work (Concrete and bitumen paving ¡V P800 CH350 to CH385) in
progress. -
NB109 A. Bay 9
1st pour Wall is completed. B. Bay 11
Footing was completed. 1st Wall is in progress. C. Bay 12
Plate Load Test is completed. Footing construction is in progress. D. Bay 5
to Bay 8 2nd Wall is in progress. -
NB69 A. Bay 5,
Bay 6 ¡V 1st Wall was completed. B. Bay 2,
Bay 7 ¡V ELS is in porgress. -
NB110 A. Bay 3
to 5 was completed. Backfilling to formation is in progress. B. Bay 8
was completed on 10 Nov 2023. (b)
North Team -
Slope
works of FS 28 completed. -
Slope
works of FS 30 was in progress. -
Installation
of formwork at C2-01 crosshead completed. -
Dismantling
of steel beam for B1-02 Portal Beam construction in progress. -
Truss
erection for C1-02 portal beam construction completed. -
Truss erection
for C1-01 MJ portal construction in progress. -
Falsework
erection for B2-02 & B2-03 cross head construction in progress -
D2-01
pier construction completed. -
Construction
of B1- Abutment wall- phase 1 completed. -
Backfilling
& extraction of sheet pile at C2-02 were in progress. -
Backfilling
at C4-02 & C4-01a were in progress -
Removal
of temporary concrete block platform at D2-01 and debris due to black
rainstorm were completed. -
JCR:
Permeant bitumen pavement works was in progress -
JCR:
Construction of pipe support for DN 150 exposed pipe was in progress. -
JCR Tong
Hang Village: Preparation works for upcoming works of box-culvert &
retaining wall completed. Construction of retaining walls were in progress. -
Construction
of manhole & associated DN 900 drain pipe were
in progress. -
Proposed
DSD River gauge was hand-over to DSD. (c)
Bridges and Structures -
Total 692 segments were casted in Huizhou
casting yard. -
Total 456 segments were delivered to site, and
total 365 segments erected. -
C3-01 T-span segment erection by LG completed -
Construction of D2-01 bridge rotation system
and upper turntable completed. -
LG launch to C2-04 in progress -
Fabricate of steel support at Zheng Zhou for
Bridge B1 in progress -
Bridge B1 construction in progress. (d)
Form Traveler -
Form traveler rebar fixing for 13th pair segment
at E2-02 in progress. -
Form traveler rebar fixing for 02nd pair segment
at E3-01 in progress. -
Form traveler rebar fixing for 05th pair segment
at D2-02 in progress. -
FT02 erection at E3-01 completed. -
FT04 erection at D2-03 completed. -
FT05 erection at E2-01 in progress. -
Completed concreting E2-E2-02-E2-03-S011,
E2-E2-02-E2-01-S11. E2-E2-02-E2-03-S012, E2-E2-02-E2-01-S12. -
Completed concreting D2-D2-02-D2-03-S03,
D2-D2-02-D2-01-S03, D2-D2-02-D2-03-S04, D2- D2-02-D2-01-S04. -
Completed concreting D2-D2-03-D2-04-S01,
D2-D2-03-D2-02-S01, E3-E3-01-E2-03-S02 |
ND/2019/06 |
The construction phase was completed and handed over to AFCD
since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at
Portion 2, 3, 4 and 5 (d)
Construction of box culvert at Portion
2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at
Portion 4 (g)
Waterworks at Portion 1, 2 and 4 |