Table 10.1 Summary
of Site Audits
Environmental Site Inspection |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
|
Weekly site audit with representative of the Supervisor’s Representative and the
Contractor |
7, 17, 21
and 29 Nov 23 |
1, 8, 15,
24 and 29 Nov 23 |
3, 10,
17, 21 and 28 Nov 23 |
2, 9, 16,
20 and 30 Nov 23 |
6, 14, 20 and 27 Nov 23 |
N/A |
3, 10, 17 and 24 Nov 23 |
Joint Site Audit with representative of the Supervisor’s Representative, the
Contractor and IEC |
7 Nov 23 |
24 Nov 23 |
21 Nov 23 |
20 Nov 23 |
14 Nov 23 |
N/A |
17 Nov 23 |
Remarks: The weekly site inspection for ND/2019/06 has been terminated
starting from 19/10/2023 since the termination proposal was approved by EPD on the
same day.