2.1
The
Kwu Tung North (KTN) and Fanling
North (FLN) New Development Areas (NDAs) are one of the important sources of
land and housing supply in the medium and long term. The development of the KTN
and FLN NDAs will be implemented in phase for full completion by 2031. The
Phase 1 of the NDAs development, comprising the Advance Works and First Stage
Works, is targeted to be implemented from the second half of 2019
progressively. The Advance and First Stage Works would include site formation,
engineering infrastructure works (including roads, drainage, sewerage,
waterworks, landscaping works, pumping stations, and fresh water and flushing
water service reservoirs), soil remediation, reprovisioning of North District
Temporary Wholesale Market, development of a nature park at Long Valley and
implementation of environmental mitigation measures.
2.2
The
scope of works under the Advance and First Stage Works comprises the following:
a)
The
Advance Works (PWP item No. 7747CL-2) consist of:
i)
site
formation of land (including soil remediation) in KTN and FLN NDAs for housing,
community facilities and engineering infrastructure;
ii)
construction
of roads including the eastern section of Fanling
Bypass (FLBP(E)) connecting the FLN NDA to Fanling
Highway and other roads with footpaths and cycle tracks, and associated
junction/ road improvements;
iii)
engineering
infrastructure works including drainage. Sewerage (including two sewage pumping
stations), waterworks (including a fresh water service reservoir and a flushing
water service reservoir in the KTN NDA), landscape works and slopeworks;
iv)
part
expansion and upgrading of Shek Wu Hui Sewage Treatment Works (SWHSTW);
v)
reprovisioning
works; and
vi)
implementation
of environmental mitigation measures and environmental monitoring and audit (EM&A)
programme for the works mentioned in (i) to (v) above.
b)
The
First Stage Works (PWP item No. 7759CL) consist of:
i)
development
of a nature park at Long Valley including provision of a visitor centre and a footbridge spanning across Sheung Yue River for
connection between these two facilities;
ii)
reprovisioning
of two egretry sites in the FLN NDA and enhancement
works to an existing egretry site in the KTN NDA;
iii)
site
formation of land for a village resite
area and a district police station in the KTN NDA;
iv)
engineering
infrastructure works including roads, drainage, sewerage, waterbirds, and
landscape works; and
v)
implementation
of environmental mitigation measures and environmental monitoring and audit
(EM&A) programme for the works mentioned in (i) to (iv) above.
2.3
The
Project which covers KTN and FLN NDAs is a designated project (DP) under Schedule
3 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499). In October
2013, the EIA Report (AEIAR-175/2013) for the Project was approved by the Director
of Environmental Protection pursuant to the EIA Ordinance. The relevant EPs
under the Project and the respective Work Contracts are summarised in Tables
2.1a and 2.1.b.
Table 2.1a Summary
of EPs under the Project and the Respective Work Contracts
EP No. |
Designated Project |
C1 |
C2 |
C3 |
C5A |
C5B |
C6 |
C7 |
|
Castle Peak Road Diversion |
ü |
¡@ |
|||||||
Kwu Tung North New
Development Area Road P1 and P2 and Associated New Kwu
Tung Interchange and Pak Shek Au Interchange Improvement |
ü |
¡@ |
|||||||
Kwu Tung North New
Development Area Road D1 to D5 |
ü |
ü |
¡@ |
||||||
Sewage Pumping Stations in Kwu
Tung North New Development Area |
ü |
¡@ |
|||||||
Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works |
ü |
¡@ |
|||||||
Fanling Bypass Eastern
Section |
ü |
ü |
ü |
¡@ |
|||||
Reprovision of temporary Wholesale Market in Fanling North New Development Area |
ü |
¡@ |
|||||||
EP-546/2017 |
Fanling North Temporary
Sewage Pumping Station |
ü |
¡@ |
Notes:
C1: ND/2019/01 C2:
ND/2019/02 C3: ND/2019/03 C5A: ND/2019/04
C5B: ND/2019/05 C6:
ND/2019/06 C7: ND/2019/07
Table 2.1b Summary of Scope of Works under concerned EP
Environmental
Permit (EP) No. |
Work
Contract(s) |
Scope
of Works under concerned EP(s) |
Site
Layout Plan under concerned EP(s) |
EP-466/2013/A(Part) |
C1 |
Realign Castle Peak Road and join with the Pak
Shek Au Interchange at the western end |
Figure 12 |
EP-467/2013/A(Part) |
C1 |
Construction of new primary distributor road (P1)
within Kwu Tung North New Development Area |
Figure 13 |
EP-468/2013/A(Part) |
C1 |
Construction of new primary distributor roads (D1,
D3, D4 and part of D5) within Kwu Tung North New
Development Area |
Figure 14 |
C3 |
Development of a nature park at Long Valley and
ecological mitigation and enhancement works for the nature park (Condition
2.9) |
Figure 15 |
|
EP-469/2013(Part) |
C2 |
Construction of one sewage pumping station in Kwu Tung North with installed capacity of more than 2,000
m3 per day |
Figure 16 |
EP-470/2013/A(Part) |
C1 |
Construction of service reservoir and watermain
for the reuse of treated sewage effluent for reuse in Kwu
Tung North Development Areas |
Figure 17 |
EP-473/2013/A(Part) |
C3 |
Establishment of alternative egretry sites and enhance
the existing egretry site at Ho Sheung Heung and/or
its vicinity (Condition 2.7) |
Figure 18 |
EP-473/2013/A(Part) |
C5A |
Construction of new district distributor inside
FLN NDA, which provides a linkage between the Man Kam To
Road and the proposed Fanling Bypass Eastern
Section |
Figure 19 |
EP-473/2013/A(Part) |
C5B |
Figure 20 |
|
EP-475/2013/A |
C6 |
The re-provisioned wholesale market will have
approximately 1,000 market stalls within a site area of around 1.3 ha |
Figure21 |
EP-546/2017 |
C5A |
Construct and operate a temporary sewage pumping
station in Fanling North with installed capacity
(average dry weather flow) of about 3,600m3/day |
Figure 22 |
Remark: The EP(s) not related to the Project of the First Phase of the Kwu
Tung North (KTN) and Fanling North (FLN) New
Development Area (NDA) Development Areas are not included in the Table.
2.4
The
site boundary of the Project and all Works Contracts are shown in Drawing No. 1.
2.5
The
required submissions and submission status under Environmental Permits are
shown in Appendix U.
2.6
The
site
layout
plans
under concerned Environmental Permits are shown in Figures
12 - 22.
2.7
Different
parties with different levels of involvement in the Project organisation include:
Project Proponent ¡V Civil
Engineering and Development Department (CEDD)
Supervisor
/ Supervisor's Representative ¡V AECOM Asia Co. Ltd.
Environmental Team (ET) ¡V Wellab Limited
Independent Environmental Checker
(IEC) ¡V Mott MacDonald Hong Kong Ltd (MottMac)
2.8
The
names and contact numbers of key personnel are summarised in Table
2.2.
Table 2.2 Key Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax
No. |
Civil Engineering and
Development Department, HKSAR (CEDD) |
Project Proponent |
Mr. Raymond Cheng |
3619 3919 |
3547
1658 |
Supervisor / Supervisor's Representative (AECOM Asia Co. Ltd.) |
Chief Resident Engineer |
Mr. Alan Lee |
6398
5982 |
2680
9515 |
Senior Resident
Engineer |
Mr. King-man
Chan |
9651
2635 |
2680
9515 |
|
Environmental Team (Wellab
Limited) |
Environmental Team Leader |
Dr. Priscilla Choy |
2898
7388 |
2898 7076 |
Independent
Environmental Checker (MottMac) |
Independent Environmental Checker |
Mr. Thomas Chan |
2828 5967 |
2827 1823 |
Contract No. ND/2019/01 Contractor
(Build King ¡V Richwell Engineering Joint Venture) |
Site Agent |
Mr. Ivan Leung |
9640 8340 |
-- |
Environmental Officer |
Mr. Edward Tam |
9287 8270 |
||
Contract No. ND/2019/02 Contractor
(Chun Wo ¡V Kwan Lee Joint Venture.) |
Site Agent |
Mr. Andy Chan |
3485 9780 |
-- |
Environmental Officer |
Mr. Wesley So |
9144 1643 |
||
Contract No. ND/2019/03 Contractor
(Sang Hing Kuly Joint Venture) |
Site Agent |
Mr. Tang Wing Kai |
9300 7037 |
-- |
Environmental Officer |
Mr. Ken Cheung |
9803 5297 |
||
Contract No. ND/2019/04 Contractor
(Daewoo ¡V Chun Wo ¡V Kwan Lee Joint Venture) |
Site Agent |
Mr. Eric Wu |
9786 8630 |
-- |
Environmental Manager |
Mr. Jimmy Cheng |
9609 5916 |
||
Environmental Officer |
Mr. Sam Lam |
6178 3179 |
||
Contract No. ND/2019/05 Contractor
(CRCC ¡V Paul Y. Joint Venture) |
Site Agent |
Mr. Darvin Lo |
9467 5891 |
-- |
Environmental Manager |
Mr. Pan Fong |
9436 9435 |
||
Environmental Officer |
Ms. Louise Poon |
5272 5709 |
||
Contract No. ND/2019/06 Contractor
(New Concepts Engineering Development Ltd.) |
Project Manager |
Mr. Joe
Cheng |
9861 0060 |
-- |
Environmental Officer |
Mr. Alex Choy |
6360 3236 |
||
Contract No. ND/2019/07 Contractor
(China Road and Bridge Corporation) |
Site Agent |
Mr. Daniel Wong |
5335 9572 |
-- |
Environmental Officer |
Mr. K. M. Lui |
5113 8223 |
||
Environmental Supervisor |
Mr. Attlee Chau |
6386 9018 |
2.9
The
major site activities undertaken in the reporting month are shown in Table 2.3.
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (May 2023) |
ND/2019/01 |
(a)
Site clearance, removal of existing structures and drainage works
at Portion 1a (b)
Excavation, backfilling and drainage
works at Portion 1b (c)
Site clearance and site formation at Portion 1c (d)
Temporary storage of material at Portion 1e (e)
Site clearance, site formation and construction of subway at Portion
2 (f)
Site clearance, excavation, sheet piling and drainage works at
Portion 3 (g)
Drainage works, excavation, backfilling and sheet piling at
Portion 5 (h)
Drainage works and backfilling at Portion 6a (i)
Operation of HAC soil treatment facility at Portion 6b (j)
Drainage works, excavation and backfilling at Portion 7 (k)
Construction of retaining wall, RC construction of fresh water
service reservoir and backfilling works at Portion 8a (l)
Construction of jacking pit at LWSC¡¦s car park, trenchless work and watermain
construction at Portion 8b (m)
Sheet piling, excavation, drainage works and watermain
construction at Portion 9b (n)
Stockpile of soil at Portion 9c (o)
Road works and site clearance at
Portion 10a (p)
Road works and site clearance at
Portion 10b (q)
Site clearance and removal of existing
structures at Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road &
Drainage works and watermains works at Yin Kong Road -
Construction of Pai Lau -
Installation of Street Lighting -
Construction of Pavilion at Yin Kong Road (b) Portion 2 to Portion 20C -
Wetland creation & restoration, Dry
agricultural land creation -
Construction of Tea House Pavilion -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) |
ND/2019/04 |
(a)
Tree Felling (b)
Pile Cap (c)
Back Filling (d) Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork erection (i)
Rebar fixing (j)
Pre-drill (k)
Bore pile (l)
ELS |
ND/2019/05 |
(a)
The segment erection using launching gantry is
critical to completion of section 4. (b)
The pier D2-01 with bridge rotation system is critical
to completion of section 5. (c)
5th set of form traveler will be
procured to be used at E2-01, thus, delay of E2-01, E2-02 and E3-03 will be
mitigated. |
ND/2019/06 |
The construction phase was completed and handed over to AFCD
since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at
Portion 1, 3 and 4 (d)
Construction of box culvert at Portion
2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at Portion
4 (g)
Waterworks at Portion 1 |
2.10
Copies of Contractors¡¦ construction programmes are
provided in Appendix A.
2.11
A
summary of the relevant permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.4.
Table 2.4 Status of Environmental Licences,
Notifications and Permits
Contract No. |
Permit / Licence No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental
Permit (EP) |
||||
ND/2019/01 |
EP-466/2013/A |
21/11/2013 |
N/A |
Valid |
EP-467/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
|
EP-470/2013/A |
21/11/2013 |
N/A |
Valid |
|
ND/2019/02 |
EP-469/2013 |
21/11/2013 |
N/A |
Valid |
ND/2019/03 |
EP-468/2013/A |
27/01/2017 |
N/A |
Valid |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
|
ND/2019/04 |
EP/473/2013/A |
27/01/2017 |
N/A |
Valid |
EP/546/2017 |
16/11/2017 |
N/A |
Valid |
|
ND/2019/05 |
EP-473/2013/A |
27/01/2017 |
N/A |
Valid |
ND/2019/06 |
EP-475/2013/A |
13/01/2017 |
N/A |
Valid |
Construction Noise
Permit (CNP) |
||||
ND/2019/01 |
GW-RN0144-23 |
13/02/2023 |
12/05/2023 |
Expired
in reporting month |
GW-RN1196-22 |
19/12/2022 |
18/05/2023 |
Expired
in reporting month |
|
GW-RN0252-23 |
16/03/2023 |
15/08/2023 |
Valid |
|
GW-RN0304-23 |
26/03/2023 |
31/08/2023 |
Valid |
|
GW-RN0392-23 |
20/04/2023 |
19/08/2023 |
Valid |
|
GW-RN0394-23 |
26/04/2023 |
25/07/2023 |
Valid |
|
GW-RN0419-23 |
24/04/2023 |
31/08/2023 |
Valid |
|
GW-RN0414-23 |
13/05/2023 |
12/09/2023 |
Valid |
|
GW-RN0426-23 |
19/05/2023 |
18/11/2023 |
Valid |
|
GW-RN0439-23 |
17/05/2023 |
31/08/2023 |
Valid |
|
GW-RN0459-23 |
15/05/2023 |
14/07/2023 |
Valid |
|
ND/2019/02 |
GW-RN1130-22 |
22/11/2022 |
10/05/2023 |
Expired
in reporting month |
GW-RN0049-23 |
16/02/2023 |
15/05/2023 |
Expired
in reporting month |
|
GW-RN0234-23 |
15/03/2023 |
14/07/2023 |
Valid |
|
GW-RN0048-23 |
08/02/2023 |
07/06/2023 |
Valid |
|
GW-RN0518-23 |
21/05/2023 |
31/08/2023 |
Valid |
|
ND/2019/03 |
GW-RN0054-23 |
01/03/2023 |
31/08/2023 |
Valid |
ND/2019/04 |
GW-RN0183-23 |
27/02/2023 |
26/05/2023 |
Expired
in reporting month |
GW-RN0430-23 |
05/05/2023 |
31/05/2023 |
Expired
in reporting month |
|
GW-RN0300-23 |
23/03/2023 |
22/06/2023 |
Valid |
|
GW-RN0353-23 |
13/04/2023 |
12/07/2023 |
Valid |
|
GW-RN0480-23 |
13/05/2023 |
25/07/2023 |
Valid |
|
GW-RN0481-23 |
15/05/2023 |
31/07/2023 |
Valid |
|
GW-RN0498-23 |
24/05/2023 |
30/07/2023 |
Valid |
|
ND/2019/05 |
GW-RN0301-23 |
01/04/2023 |
31/05/2023 |
Expired
in reporting month |
GW-RN0239-23 |
08/03/2023 |
07/06/2023 |
Valid |
|
GW-RN0262-23 |
22/03/2023 |
21/06/2023 |
Valid |
|
GW-RN0288-23 |
30/03/2023 |
31/08/2023 |
Valid |
|
GW-RN0435-23 |
08/05/2023 |
07/08/2023 |
Valid |
|
Notification pursuant
to Air Pollution Control (Construction Dust)
Regulation |
||||
ND/2019/01 |
451792 |
11/12/2019 |
N/A |
Valid |
477388 |
02/03/2022 |
N/A |
Valid |
|
ND/2019/02 |
454012 |
05/03/2020 |
N/A |
Valid |
ND/2019/03 |
452216 |
24/12/2019 |
N/A |
Valid |
452332 |
31/12/2019 |
N/A |
Valid |
|
452333 |
31/12/2019 |
N/A |
Valid |
|
ND/2019/04 |
461184 |
23/10/2020 |
N/A |
Valid |
ND/2019/05 |
454323 |
13/03/2020 |
N/A |
Valid |
ND/2019/06 |
449369 |
24/09/2019 |
N/A |
Valid |
ND/2019/07 |
459393 |
28/08/2020 |
N/A |
Valid |
Billing Account for
Disposal of Construction Waste |
||||
ND/2019/01 |
7036265 |
17/01/2020 |
N/A |
Valid |
ND/2019/02 |
7036898 |
01/04/2020 |
N/A |
Valid |
ND/2019/03 |
7036378 |
22/01/2020 |
N/A |
Valid |
ND/2019/04 |
7038391 |
22/09/2020 |
N/A |
Valid |
ND/2019/05 |
7036901 |
01/04/2020 |
N/A |
Valid |
ND/2019/06 |
7035473 |
17/10/2019 |
N/A |
Valid |
ND/2019/07 |
7038309 |
14/09/2020 |
N/A |
Valid |
Registration
of Chemical Waste Producer |
||||
ND/2019/01 |
5213-545-B2578-01 |
10/01/2020 |
N/A |
Valid |
ND/2019/02 |
5213-548-C4439-01 |
06/05/2020 |
N/A |
Valid |
ND/2019/03 |
5213-623-S4231-01 |
14/04/2020 |
N/A |
Valid |
ND/2019/04 |
5211-624-D2709-01 |
26/11/2020 |
N/A |
Valid |
ND/2019/05 |
5213-625-C4464-01 |
20/05/2020 |
N/A |
Valid |
ND/2019/06 |
5213-625-N2716-01 |
02/10/2019 |
N/A |
Valid |
ND/2019/07 |
5213-625-C4498-01 |
21/09/2020 |
N/A |
Valid |
Effluent
Discharge License under Water Pollution Control Ordinance |
||||
ND/2019/01 |
WT00036071-2020 |
22/06/2020 |
30/06/2025 |
Valid |
WT00036073-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036067-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036075-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00036076-2020 |
22/06/2020 |
30/06/2025 |
Valid |
|
WT00037191-2020 |
21/04/2022 |
28/02/2026 |
Valid |
|
WT00037204-2020 |
02/02/2021 |
28/02/2025 |
Valid |
|
WT00037412-2021 |
15/04/2021 |
30/04/2026 |
Valid |
|
WT00037564-2021 |
19/04/2021 |
30/04/2026 |
Valid |
|
WT00037886-2021 |
28/06/2021 |
30/06/2026 |
Valid |
|
WT00041311-2022 |
21/06/2022 |
30/06/2027 |
Valid |
|
ND/2019/02 |
WT00036584-2020 |
21/10/2020 |
31/10/2025 |
Valid |
WT00036952-2020 |
17/12/2020 |
31/12/2025 |
Valid |
|
ND/2019/03 |
WT00035847-2020 |
12/08/2020 |
31/08/2025 |
Valid |
WT00036414-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
WT00037771-2021 |
08/07/2021 |
31/07/2026 |
Valid |
|
WT00035984-2020 |
25/02/2021 |
28/02/2026 |
Valid |
|
ND/2019/04 |
WT00037539-2021 |
02/06/2022 |
30/04/2026 |
Valid |
ND/2019/05 |
WT00036996-2020 |
22/12/2020 |
31/12/2025 |
Valid |
ND/2019/06 |
WT00035415-2019 |
20/03/2020 |
31/03/2025 |
Valid |
ND/2019/07 |
WT00037526-2021 |
21/04/2022 |
31/05/2026 |
Valid |