11.1 Four (4)
Limit Level for DO, Three (3) Limit Level for
turbidity, and Two (2) Limit Level for Suspended Solid of impact water quality
monitoring were recorded. After investigation, the exceedance was
considered due to the other external factors rather than the contract works.
11.2 No Action/Limit Level exceedance for air
quality, construction noise, ambient arsenic, built heraitage
and landfill gas monitoring was recorded in the reporting month. The summary of
exceedance record in the reporting month is shown in Appendix O.
11.3 Ecological monitoring was carried out in the reporting
month. One (1) Action Level exceedance and one (1) Limit Level exceedance for
odonatan monitoring were recorded. The exceedance was considered non-project
related as the habitat were heavily altered due to non-project related works..
11.4 Should the monitoring results of the environmental
monitoring parameters at any designated monitoring stations indicate that
Action / Limit Levels are exceeded, the actions in accordance with the Event/Action
Plan in Appendix N would be carried
out.
11.5 No environmental non-compliance was recorded in the
reporting month.
11.6 No environmental complaint was received in the
reporting month. The Cumulative Complaint Log since the commencement of the
Project is presented in Appendix S.
11.7
There was no
successful environmental prosecution or notification of summons received since
the Project commencement. The Cumulative Log for environmental summon and
successful prosecution since the commencement of the Project is presented in Appendix T.