Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (April to June 2023)

ND/2019/01

 

(a)          Site Clearance, tree felling, removal of existing structures, slope work and drainage works in Portion 1a

(b)         Excavation, backfilling, drainage works, construction of hoarding/fencing and road works in Portion 1b

(c)          Site clearance, site formation and socket H piling in Portion 1c

(d)         Temporary storage of material and site formation in Portion 1e

(e)          Tree felling, site formation work and construction of subway in Portion 2

(f)          Excavation, backfilling and drainage works in Portion 3

(g)         Drainage works, watermain, excavation, backfilling, road works, sheet piling and pipe jacking in Portion 5

(h)         Drainage works, backfilling, road works, watermains work in Portion 6a

(i)           Operation of HAC treatment facility in Portion 6b

(j)           Site formation, sheet piling, excavation and drainage works in Portion 7

(k)         Construction of retaining wall, RC construction of flushing water service reservoir and fresh water reservoir, construction of WSD¡¦s maintenance access and backfilling works in Portion 8a

(l)           Construction of jacking pit at LWSC¡¦s car park and trenchless work, excavation, watermain construction and trial pit in Portion 8b

(m)       Sheet piling, excavation, drainage works and watermain construction in Portion 9b

(n)         Stockpile of soil in Portion 9c

(o)         Utilities works in Portion 10a

(p)         Sheet piling, excavation and drainage works in Portion 10b

(q)         Site clearance, tree felling, remove of existing structure in Portion 13

ND/2019/02

(a)           Pipe Jacking

(b)           Backfilling

(c)           Concreting

(d)           Bedding & Pipe Laying

(e)           ELS

(f)            Sheet Pile Installation

(g)           Cut and Fill of Slope

ND/2019/03

 

(a)        Portion 1 & Portion 1A

-            Road & Drainage works and watermains works at Yin Kong Road

-            Construction of Pai Lau

-            Installation of Street Lighting

-            Construction of Pavilion at Yin Kong Road

(b)     Portion 2 to Portion 20C

-          Wetland creation & restoration, Dry agricultural land creation

-          Construction of Tea House Pavilion

-          Construction of compacted earth path

-          Construction of Water Treatment Wetland

-          Tree felling and tree pruning work

-          Construction of Lodging Facility

-          Construction of Dry Weather Flow Interception (DWFI)

ND/2019/04

 

(a)           Tree Felling and transplant

(b)           Pile Cap

(c)           Excavation

(d)           Grouting

(e)           Sheet Piling

(f)            Road works

(g)           Pre-drill

(h)           Bore pile

(i)            ELS

ND/2019/05

(a)           North Team Works

-          ELS and Pile cap construction at B2-01, B2-02, B2-03, C1-01a, C2-03b, C2-04b & D2-01

-          Pier construction at C1-01a, C2-03b, C2-04b, D2-01 & E2-01.

-          Pier head construction at C3-01b, C1-01a & E2-01

-          Cross head construction at C2-01, C2-02, C3-02.

-          Slope works, road works and drainage work at Jockey Club Road (3SW-C/F63), Tong Hang Junction and Portion VI (FS28 & 29)

(b)          Viaduct Works

-          Segment fabrication for bridge C2 & D1 & E1.

-          Segments erection by LG at bridges C4,C3,

-          Segments erection by crane at bridge D1 and E1.

-          T-span construction by form traveler at Pier E2-02, E3-03, D2-02, E3-01

-          SOP construction at D2-02, E3-02, D2-03

-          Construction of pile cap and installation of bridge rotation components at pier E2-01, D2-01.

-          Design and fabrication of 3rd and 4th set of form traveler.

-          Design and fabrication of truss formwork for Bridge B1.

-          Erection of tower crane at E2-01.

(c)          South Team Works

-          TWSRW ¡V Road work (section ch 250 to 450). UU diversion.

-          TWSRW ¡V Slope work for FS06. Soil nail for FS04. Outage of CLP 132 kv.

-          TWSRE ¡V Form D300 new road, BBI footing, relocation of existing BBI and road diversion

-          HKY FB (East) ¡V Erection of stair case

-          HKY FB (West) ¡V Construction of LT2

-          E2-03 ¡V Pier and pier head construction.

-          E3-04a, E3-05M, E4-01 and E4-02 ¡V cap construction.

-          NB109 ¡V bay 5~8, base slab construction.

ND/2019/06

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 1, 4 and 5

(b)        C&D waste disposal at Portion 1, 2, 4 and 5

(c)        Construction of box culvert at Portion 2

(d)        Filling works at Portion 2 and 4

(e)        Construction of site haul road at Portion 4

(f)         Drainage works, Sewerage works at Portion 1, 3, 4 and 5

(g)        Mini piling works at Portion 4

(h)        Construction of noise barrier at Portion 4 and 5

(i)         Waterworks at Portion 1