8.2 Vibration Monitoring Plan
EP. No |
Contract No. |
Monitoring Stations |
Distance with Construction Works |
Monitoring Plan |
EP-473/2013/A |
ND/2019/05 |
FL02 |
Within 50m |
Daily assessment is required |
Within 75m |
Bi-daily assessment is required |
|||
Within 100m |
Weekly assessment is required |
Remark:
[1] Baseline condition survey was
conducted for built heritage features at HFL08, FL05, FL07, FL08, FL10, FL11,
FL17, FL19, FL31 and FL33 under ND/2019/04, also HFL05, FL02, FL04, FL24, FL27
and FL36 under ND/2019/05 for EP-473/2013/A. As HFL05, HFL08, FL04, FL05, FL07,
FL08, FL10, FL11, FL17, FL19, FL24, FL27, FL31, FL33 and FL36 were not within
the assessment area of the related construction work, no construction vibration
monitoring was conducted for the built heritage in the reporting month.