13           CONCLUSIONS AND RECOMMENDATIONS

Conclusions

 

13.1     This monthly EM&A Report presents the EM&A work undertaken in June 2023 in accordance with the Updated EM&A Manual.

13.2     No Action/Limit Level exceedance for air quality, water quality, construction noise, ambient arsenic, landfill gas monitoring and build heritage monitoring was recorded in the reporting month.

13.3     One (1) action level exceedance and one (1) limit level exceedance for odonata were recorded.

Contract No. ND/2019/01

13.4     Environmental site inspections were conducted on 6, 14, 20 and 27 Jun 23 by ET in the reporting month.

Contract No. ND/2019/02

13.5     Environmental site inspections were conducted on 9, 12, 21 and 28 Jun 23 by ET in the reporting month.

Contract No. ND/2019/03

13.6     Environmental site inspections were conducted on 2, 9, 16, 20 and 30 Jun 23 by ET in the reporting month.

Contract No. ND/2019/04

13.7     Environmental site inspections were conducted on 1, 8, 14, 21 and 29 Jun 23 by ET in the reporting month.

Contract No. ND/2019/05

13.8     Environmental site inspections were conducted on 5, 15, 19 and 26 Jun 23 by ET in the reporting month.

Contract No. ND/2019/06

13.9     Environmental site inspections were conducted on 1, 8, 14, 21 and 29 Jun 23 by ET in the reporting month.

Contract No. ND/2019/07

13.10 Environmental site inspections were conducted on 2, 9, 16, 19 and 30 Jun 23 by ET in the reporting month.

13.11 No environmental complaints was received in the reporting month. No notification of summons or successful prosecutions was received in the reporting month.

13.12 The ET would keep track on the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all necessary mitigation measures.


 

Recommendations                                                                              

 

13.13 According to the environmental audits performed in the reporting month, the following recommendations were made:

 

Air Quality Impact

¡P  To regular water haul roads;

¡P  To provide vehicle washing facilities with high pressure water jet at every discernible or designated vehicle exit point;

¡P  To maintain the impervious material to entirely cover the stockpile of dusty materials; and

¡P  To ensure all regulated machines displayed with valid Non-road Mobile Machinery (NRMM) labels.

 

Construction Noise Impact

¡P  To ensure compressor operated with doors closed.

¡P  To ensure the noise barriers were fully enclosed.

Water Impact

¡P  To review and implement temporary drainage system;

¡P  To prevent any surface runoff discharge into Sheung Yuen River, Ma Wat River or public road;

¡P  To provide sandbags or construct berm to prevent any outflow of muddy water from site area;

¡P  To ensure all vehicle clear of earth and mud before leaving the site areas;

¡P  To ensure the drainage facilities would not be clogged with waste or sediment to avoid overflow;

¡P  To regularly check the condition of desilting materials for proper function;

¡P  To regularly maintain and ensure water treatment facilities proper operation and function;

¡P  To divert all the water generated from the construction site to de-silting facilities with sufficient handling capacity before discharge; and

¡P  To avoid or regularly clear the stagnant water in drip trays;

Waste/Chemical Management

¡P  To dispose of general refuse properly;

¡P  To clear and avoid oil stains at site areas;

¡P  To provide proper storage areas for chemical; and

¡P  To maintain drip trays for chemical storage well.

Landfill Gas Hazard

¡P  ¡§No Smoking¡¨ and ¡§No Naked Flame¡¨ notices in Chinese and English should be posted prominently around the construction site.

Land Contamination

¡P  Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be properly covered by impermeable sheeting to reduce dust emission during dry season or contaminated run-off during rainy season. Watering should be avoided on stockpiles of soil to minimise runoff.

Ecology

¡P  Properly erect and maintain 2m high solid barriers for protecting Siu Hang San Tsuen Stream.

Permit/ Licences

¡P  To display valid Permit or Licences at the site entrances.