Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Contract
No. |
Site
Activities (June 2023) |
ND/2019/01 |
(a)
Site clearance, removal of existing structures and drainage works
at Portion 1a (b)
Excavation, backfilling and drainage
works at Portion 1b (c)
Site clearance and site formation at Portion 1c (d)
Temporary storage of material at Portion 1e (e)
Site clearance, site formation and construction of subway,
drainage works and road works at Portion 2 (f)
Site clearance, excavation, sheet piling and drainage works at
Portion 3 (g)
Drainage works, excavation, backfilling and sheet piling at
Portion 5 (h)
Drainage works and backfilling at Portion 6a (i)
Operation of HAC soil treatment facility at Portion 6b (j)
Drainage works, excavation and backfilling at Portion 7 (k)
Construction of retaining wall, RC construction of fresh water
service reservoir, construction of WSD¡¦s maintenance access, drainage
works and backfilling works at Portion 8a (l)
Set up for pipe jacking at jacking pit at LWSC¡¦s car park, trenchless work, and
watermain construction at Portion 8b (m)
Sheet piling, excavation, drainage works and watermain
construction at Portion 9b (n)
Stockpile of soil at Portion 9c (o)
Portion 10a was handed over. Road
opened. (p)
Road works and site clearance at
Portion 10b (q)
Site clearance and removal of existing
structures at Portion 13 |
ND/2019/02 |
(a)
Pipe Jacking (b)
Backfilling (c)
Concreting (d)
Bedding and pipe laying (e)
ELS (f)
Sheet Pile Installation (g)
Cut and Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road
& Drainage works and watermains works at Yin Kong Road -
Installation of Street Lighting -
Construction of Pavilion at Yin Kong Road (b)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry
agricultural land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) |
ND/2019/04 |
(a)
Tree Felling and transplant (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork Erection (i)
Rebar Fixing (j)
Pre-drill (k)
Bore pile (l)
ELS |
ND/2019/05 |
(a)
The segment erection using launching gantry is
critical to completion of section 4. (b)
The pier D2-01 with bridge rotation system is
critical to completion of section 5. (c)
The erection of 3rd form traveler at D2-02 is in
progress. (d)
5th set of form traveler is under fabrication
off-site to be used at E2-01. |
ND/2019/06 |
The construction phase was completed and handed over to AFCD
since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1, 2, 4 and 5 (c)
Drainage works, Sewerage works at
Portion 1, 3 and 4 (d)
Construction of box culvert at Portion
2 (e)
Filling works at Portion 2 and 4 (f)
Construction of site haul road at
Portion 4 (g)
Waterworks at Portion 1 |