10.1
Site
audits were carried out by ET on a weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures on the Contract site. Summary
of the site
audits are presented in Table 10.1 and Appendix P.
Table 10.1 Summary
of Site Audits
Environmental Site Inspection |
Works Contracts |
||||||
ND/2019/01 |
ND/2019/02 |
ND/2019/03 |
ND/2019/04 |
ND/2019/05 |
ND/2019/06 |
ND/2019/07 |
|
Weekly site audit with representative
of the Supervisor¡¦s Representative
and the Contractor |
4, 12, 18 and 25 Jul
23 |
5, 12, 19 and 28 Jul
23 |
6, 14, 18 and 28 Jul
23 |
6, 13, 19 and 27 Jul
23 |
3, 10, 20, 24 and 31
Jul 23 |
6, 13, 19 and 27 Jul
23 |
7, 14, 21 and 28 Jul
23 |
Joint Site Audit with representative of the Supervisor¡¦s Representative, the
Contractor and IEC |
12 Jul 23 |
28 Jul 23 |
18 Jul 23 |
19 Jul 23 |
20 Jul 23 |
N/A |
21 Jul 23 |
10.2
During
site inspections in the reporting month, no non-conformance was identified. The
observations and recommendations made during the audit sessions are summarised in Table 10.2.
10.3
All
construction activities with significant environmental impact undertaken by
Contract No. ND/2019/06 was substantially completed in March 2022 and the majority
of outstanding works were also completed
in April 2022 with defect rectification works remained. The outstanding installation works
were
the short-duration works which would be completed within 2 months during
the 1-year defect correction period, originally estimated.
10.4
Due to problems
in material deliveries from Mainland China in 2022, the completion date of the
outstanding works would be extended to June 2023 tentatively. However, in June
2023, more defects were found during the handover inspection so the
rectification works will continue for another week or two. In the reporting
month (July 2023), all works have been completed and waiting for the
confirmation of the authority. The status will be updated in the next reporting
period.
10.5
The
weekly site inspection and EM&A Reporting for ND/2019/06 will be maintained
until the termination proposal for ND/2019/06 has been endorsed by the IEC, the
Engineer and the Project Proponent followed by approval from EPD in accordance.
The procedure for termination proposal for ND/2019/06 is in accordance with
section 15.4.2 of updated EM&A Manual.
Table 10.2
Observations and Recommendations during Site Audits
Parameters |
Date |
Observations
and Recommendations |
Follow-up |
Contract No.: ND/2019/01 |
|||
-- |
-- |
-- |
-- |
Contract No.: ND/2019/02 |
|||
Water Quality |
19/07/2023 |
The exposed slopes next to Sheung Yue River should be covered by
tarpaulin sheets and maintained regularly and properly to prevent muddy water
discharge during rainstorm. |
Item remarked as 230728-R02. Follow-up action is
needed to be review. |
28/07/2023 |
Follow-up action is needed to be reported in the
following month. |
||
Air Quality |
28/07/2023 |
Faded NRMM label should be replaced. |
Follow-up action is needed to be reported in the
following month. |
Landscape and Visual |
19/07/2023 |
The removed green hoarding along Sheung Yue River due to the
construction works should be replaced and maintained properly as soon as
possible. |
Item remarked as 230728-R01. Follow-up action is
needed to be review. |
28/07/2023 |
Follow-up action is needed to be reported in the
following month. |
||
Contract No.: ND/2019/03 |
|||
Air Quality |
30/06/2023 |
Dusty
stockpiles should be covered with tarpaulin sheets. |
Item
remarked as 230706-R01. Follow-up action is needed to be review. |
06/07/2023 |
Item
remarked as 230714-R01. Follow-up action is needed to be review. |
||
14/07/2023 |
Item
remarked as 230718-R01. Follow-up action is needed to be review. |
||
18/07/2023 |
Item
remarked as 230728-R01. Follow-up action is needed to be review. |
||
28/07/2023 |
Follow-up
action is needed to be reported in the following month. |
||
Water Quality |
30/06/2023 |
Provide
adequate wheel-washing facilities for each vehicle exits. |
Item
remarked as 230706-O01. Follow-up action is needed to be review. |
06/07/2023 |
Item
remarked as 230714-O01. Follow-up action is needed to be review. |
||
14/07/2023 |
Item
remarked as 230718-O01. Follow-up action is needed to be review. |
||
18/07/2023 |
Item
remarked as 230728-O01. Follow-up action is needed to be review. |
||
28/07/2023 |
Follow-up
action is needed to be reported in the following month. |
||
30/06/2023 |
Provide
sand bags to prevent muddy water discharge. |
Item
remarked as 230706-R02. Follow-up action is needed to be review. |
|
06/07/2023 |
Item
remarked as 230714-R02. Follow-up action is needed to be review. |
||
14/07/2023 |
Item
remarked as 230718-R02. Follow-up action is needed to be review. |
||
18/07/2023 |
Item
remarked as 230728-R02. Follow-up action is needed to be review. |
||
28/07/2023 |
Follow-up
action is needed to be reported in the following month. |
||
Contract No.: ND/2019/04 |
|||
Noise |
29/06/2023 |
The noise barrier at Bridge F should be fully
enclosed. |
Improvement/Rectification
was observed during follow-up audit session on 6 Jul 2023. |
Ecology |
29/06/2023 |
Provide maintenance for 2m high solid barrier at
the lower reaches of Siu Hang San Tsuen Stream. |
Item remarked as 230706-R01. Follow-up action is
needed to be review. |
06/07/2023 |
Item remarked as 230713-R01. Follow-up action is
needed to be review. |
||
13/07/2023 |
Item remarked as 230719-R01. Follow-up action is
needed to be review. |
||
19/07/2023 |
Improvement/Rectification
was observed during follow-up audit session on 27 Jul 2023. |
||
Contract No.: ND/2019/05 |
|||
Water Quality |
26/06/2023 |
Enhance
the water mitigation measure for E201. |
Improvement/Rectification
was observed during follow-up audit session on 3 Jul 2023. |
03/07/2023 |
Sandbag
barrier should be enhanced to prevent surface runoff at D2-01. |
Improvement/Rectification
was observed during follow-up audit session on 10 Jul 2023. |
|
Air Quality |
26/06/2023 |
Provide
impervious sheeting for dusty stockpile. (Man Young) |
Improvement/Rectification
was observed during follow-up audit session on 3 Jul 2023. |
Waste / Chemical Management |
31/07/2023 |
Provide
Drip tray for chemical/fuel containers. |
Follow-up action is needed to be reported in the following month. |
Contract No.: ND/2019/06 |
|||
-- |
-- |
-- |
-- |
Contract No.: ND/2019/07 |
|||
-- |
-- |
-- |
-- |
10.6
According
to the EIA Report, EPs and the Updated EM&A Manual, the mitigation measures
detailed in the documents are recommended to be implemented during the
construction phase. An updated summary of the Environmental Mitigation
Implementation Schedule is provided in Appendix
Q. The photographic records of measures as stipulated in EPs
to mitigate environmental impacts in the reporting month are presented in Table 10.3.
Table 10.3 Photographic Records and
Implementation Status of Measures
EP No. |
Condition |
Photographic Record |
Implementation Status |
EP-466/2013/A |
2.9 |
To
minimise adverse impacts on habitats of ecological
importance
in the vicinity of the Project, 2m high solid dull green site barrier fences
shall be erected around all active works areas. |
^[1] |
EP-467/2013/A |
2.9 |
To
minimise adverse impacts on habitats of ecological
importance
in the vicinity of the Project, 2m high solid dull green site barrier fences shall
be erected around all active works areas. |
^[1] |
EP-468/2013/A |
2.11 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-469/2013 |
2.7 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-473/2013/A |
2.13 |
To
minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
EP-475/2013/A |
2.7 |
To minimise adverse impacts on habitats of ecological
importance in the vicinity of the Project, 2m high solid dull green site
barrier fences shall be erected around all active works areas. |
^[1] |
Implementation status: |
^ Mitigation
measure was fully implemented * Observation/reminder
was made during site audit but improved/rectified by the contractor # Observation/reminder
was made during site audit but not yet improved/ rectified by the contractor X Non-compliance
of mitigation measure ¡P Non-compliance
but rectified by the contractor N/A Not
Applicable at this stage as no such site activities were conducted in the
reporting period |
Remark:
[1]: Barrier
fences might be subjected to change according to the phasing plan designed at
detailed design stage
10.7
The water quality mitigation measures
detailed in the EIA Report and the Updated EM&A Manual are recommended to
be implemented during the construction phase. Water quality mitigation measures
implemented by the contractors were closely monitored to prevent water
pollution, especially during rainy season. An updated summary of the
Environmental Mitigation Implementation Schedule is provided in Appendix Q.
Specific water quality mitigation measures for major construction works in the
reporting month are presented in Table 10.4.
Table 10.4 Specific Water Quality
Mitigation Measures for Major Construction Works in the Reporting Month
Works Contracts |
Photographic Records |
|
ND/2019/01 |
Hard paved exposed
slope surface |
Hydroseeding for
slope area |
ND/2019/02 |
Hard paved exposed
haul road |
Hard paved exposed slope surface |
ND/2019/03 |
Hard paved exposed
haul road |
Watering the main haul road regularly. |
ND/2019/04 |
Hard paved exposed slope surface |
Deployment of silt curtain around works area in Ng Tung River |
ND/2019/05 |
Covering dusty
stockpile |
Provision of sand bags around works area |
ND/2019/07 |
Covering exposed slope surface with tarpaulin |
De-silting waste water before discharge |
Water quality mitigation measures for site(s) in operation
phase, remaining defect works |
||
ND/2019/06 |
Hard paved exposed
haul road |
Hard paved exposed haul road |
10.8
Waste generated
from Contract Nos.
ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05 and ND/2019/07
included
inert construction and demolition (C&D) materials and non-inert C&D wastes
in the reporting
month.
The site of ND/2019/06 was handed over to AFCD for operation since 4 April
2022.
10.9
The amount of wastes generated by the construction works of the Contract
Nos.
ND/2019/01, ND/2019/02, ND/2019/03, ND/2019/04, ND/2019/05 and ND/2019/07 during the reporting month are shown in Appendix R. The site of
ND/2019/06 was handed over to AFCD for operation since 4 April 2022.
10.10 The Contractors are advised to minimise the wastes generated
through recycling or reusing. All mitigation measures stipulated in the Updated
EM&A Manual and waste management plans shall be fully implemented. The
status of implementation of waste management and reduction measures are
summited in Appendix Q.
10.11
Based on the findings of the EIA
Report, the area of Long Valley has been assessed as of high to very high
ecological value and is the largest contiguous area of freshwater wetland
habitats in Hong Kong. To safeguard the ecological value of Long Valley, about
37 hectares of land in Long Valley has been proposed to develop into Long
Valley Nature Park (LVNP) for conserving and enhancing the ecologically
important environment as well as for compensation of the wetland loss due to
the NDA development.
10.12
LVNP is developed according to the approved
Habitat Creation and Management Plan (HCMP) submitted under EP-468/2013/A. HCMP
provides a framework and specifications for development and management of LVNP
and guides the development to maintain and enhance the 37 hectares of low-lying
wetland habitats.
10.13
Regarding
the design, the zoning of land use in LVNP is intended to maintain the existing
mosaic pattern of wet and dry agriculture, while controlling the activities
that could potentially disturb target habitats and species. LVNP will be divided
into three broad zones of land use as below:
•
Biodiversity
Zone of about 21 hectares largely designated for biodiversity conservation
through cultivation of specified crops and habitat management.
•
Agricultural
Zone of about 11 hectares designated for commercially focuses crop production
and eco-friendly agricultural practice for farming.
•
Visitor
Zone of about 5 hectares designed to accommodate visitors as well as storage
and other facilities and for educational purposes.
10.14
The
construction of LVNP started in late 2019 and was expected to be completed in 2023.
During the construction
period, the progress of construction and wetland enhancement works has been
under observation by different stakeholders including AFCD and green groups.
Close communication between AFCD and CEDD were conducted to exchange views on
conservation, restoration and management of habitats
as well as on the planning and design of the park. In addition, advices
from green groups, Hong Kong Bird Watching Society (HKBWS) and The Conservancy
Association (CA), have been taken on habitat management of Long
Valley and potential effects on habitat and wildlife of each individual work
conducted in Long Valley. The last meeting was held on 18 November 2022 to share
the progress of LVNP with different stakeholders, including CEDD, AFCD, CA,
HKBWS, Contractor, ET, IEC and farmers.
10.15 Proposals on wetland creation and
restoration, dry agricultural land creation, pond creation, water treatment
wetland and design of irrigation channel were submitted by the Contractor to
achieve the objectives stated in HCMP and accepted by the Engineer with consent
from AFCD before implementation. The Contractor would consult the stakeholders for
recommendations and suggestions on mitigation measures to minimise
the environmental impacts arising from construction works. The progress of
works would
be arranged to minimise impacts to avifauna and
maintain the habitat for avifauna. The photographic records of site activities
in LVNP are presented in Table 10.5.
Table 10.5 Photographic
Records of Site Activities in LVNP
Continuing agricultural practice in existing
farmland to maintain habitats in Long Valley |
||
Open
water Habitat |
Open
water Habitat |
|
Creation of wetland with designated
habitat for biodiversity conservation |
||
Planting of paddy rice to provide
foraging ground for Yellow-breasted Bunting |
||
Enhancement of irrigation channel
to provide reliable water source for farmland in Long Valley |
||
Provision of bird island (hidden area) |
Restoring of water flea pond to provide
food source to water birds |
|
Construction of storage sheds for farmers |
A Himantopus
himantopus was recorded |
|
Wet agricultural land |
Provision of noise barrier for noisy
works in Long Valley |
|