Table IV Summary Table for Site Activities in the coming Three
Months
Contract
No. |
Site Activities (August to October 2023) |
ND/2019/01 |
(a)
Site
Clearance, tree felling, removal of existing structures, slope work and
drainage works in Portion 1a (b)
Excavation,
backfilling, construction of hoarding/fencing and road works in Portion 1b (c)
Site
formation and socket H piling in Portion 1c (d)
Temporary
storage of material in Portion 1e (e)
Tree
felling, site formation work, construction of subway and road works in
Portion 2 (f)
Excavation,
backfilling and drainage works in Portion 3 (g)
Watermain,
excavation, backfilling, road works, sheet piling and pipe jacking in Portion
5 (h)
Drainage
works, backfilling, road works, watermains work in Portion 6a (i)
Operation
of HAC treatment facility in Portion 6b (j)
Site
formation, sheet piling, excavation and drainage works in Portion 7 (k)
Construction
of retaining wall, RC construction of fresh water reservoir, excavation at WSD¡¦s
maintenance access, backfilling works and drainage works in Portion 8a (l)
Trenchless
work, excavation and watermain works in Portion 8b (m)
Sheet
piling, excavation, drainage works and watermain works in Portion 9b (n)
Stockpile
of soil in Portion 9c (o)
Site clearance, tree felling and remove of
existing structure in Portion 13 |
ND/2019/02 |
(a)
Pipe
Jacking (b)
Backfilling (c)
Concreting (d)
Bedding
& Pipe Laying (e)
ELS (f)
Sheet
Pile Installation (g)
Cut and
Fill of Slope |
ND/2019/03 |
(a)
Portion 1 & Portion 1A -
Road &
Drainage works and watermains works at Yin Kong Road -
Construction of Pavilion at Yin Kong Road (b)
Portion 2
to Portion 20C -
Wetland creation & restoration, Dry
agricultural land creation -
Construction of compacted earth path -
Construction of Water Treatment Wetland -
Tree felling and tree pruning work -
Construction of Lodging Facility -
Construction of Dry Weather Flow Interception
(DWFI) -
Construction of Car Park and Farmer¡¦s Forum |
ND/2019/04 |
(a)
Tree Felling (b)
Pile Cap (c)
Back Filling (d)
Excavation (e)
Grouting (f)
Sheet Piling (g)
Road works (h)
Formwork Erection (i)
Rebar Fixing (j)
Pre-drill (k)
Bore pile (l)
ELS |
ND/2019/05 |
(a)
North Team Works -
ELS works and Pile cap construction at B2-01 -
Backfilling and drainage work at C4-02 &
C4-01. -
Backfilling at C3-04b. -
Slope works at On Lok Garden FS 28 & 29. -
Construction of B1-abutment wall and backfill. -
Slope drainage works of Jockey Club Rd ¡V F63. -
Road works of northbound of Jockey Club Rd. -
Laying ducting for traffic signal, traffic light
& street light & construction of permanent footpath for subsequent
pedestrian diversion at J/O of JCR and Tong Hang Tsuen -
Construction of new box culvert & retaining
wall at Tong Hang Tsuen -
Drainage works ¡V DN 900 at On Kui Street near B1. -
Pier construction at D2-01 & B2-03 -
Pier head construction at D2-01 -
Cross head construction at C2-01 (b)
Viaduct Works -
Segment fabrication for bridge C2, D1, D2& E1 -
Segments erection by LG at bridges C3, C2 -
Segments erection by crane at bridge D1 and E1 -
SOP construction at E2-01, E2-03, D2-01 -
Construction of pile cap and installation of
bridge rotation components at pier D2-01 -
Design and fabrication of falsework for Bridge B1 -
Erection of tower crane at E2-01 (c)
South Team Works -
TWSRW ¡V Road construction work and UUs laying
(Section P800 CH 235 to 450). -
TWSRW ¡V Hydroseeding of FS04. -
TWSRW - CLP 11 kv cable
diversion work (1ST) -
TWSRE ¡V Form D300 new road, BBI footing,
relocation of existing BBI and road diversion -
TWSRE ¡V Drainage Diversion, Road Drain, UUs
laying (HKT, CLP, TCSS, Irrigation) -
HKY FB (East) ¡V Construction of extension roof,
install subframe, cladding, E&M -
HKY FB (West) ¡V Construction of LT2 (Foundation) -
E3-04a, E3-05M, E4-01 and E4-02 ¡V cap
construction. -
NB109 ¡V Bay 9~12 base slab construction. Bay 5 to
12 wall construction. -
NB69 ¡V Bay 6~8 ELS excavation and base slab
construction. -
NB110 ¡V Bay 3~5 Base slab and wall construction. (d)
Form Traveler -
E3-03 ¡V Relocate to E3-01 -
E2-02 ¡V construction 7th to 10th pair -
D2-02 ¡V construction 1st to 2nd pair -
D2-03 ¡V erection of form traveller
no. 4 -
E2-01 - Design and fabrication of 5th set of form
traveler. |
ND/2019/06 |
The construction phase has been completed
and handed over to AFCD since 4 April 2022. |
ND/2019/07 |
(a)
Road works at Portion 1, 4 and 5 (b)
C&D waste disposal at Portion 1,
2, 4 and 5 (c)
Construction of box culvert at Portion
2 (d)
Filling works at Portion 2 and 4 (e)
Construction of site haul road at
Portion 4 (f)
Drainage works, Sewerage works at
Portion 1, 3, 4 and 5 (g)
Mini piling works at Portion 4 (h)
Construction of noise barrier at
Portion 4 and 5 (i)
Waterworks at Portion 1 and 4 |