Table IV       Summary Table for Site Activities in the coming Three Months

Contract No.

Site Activities (February to April 2023)

ND/2019/01

 

(a)          Site Clearance, tree felling, removal of existing structures, site formation and G.I works in Portion 1a

(b)         Excavation, backfilling, drainage works, construction of hoarding/fencing, road works and noise barrier in Portion 1b

(c)          Site clearance, site formation in Portion 1c

(d)         Temporary storage of material and site formation in Portion 1e

(e)          Site clearance, tree felling, site formation work and construction of subway in Portion 2

(f)          Excavation, backfilling and drainage works in Portion 3

(g)         Drainage works, watermain, excavation, backfilling, road works, sheet piling and pipe jacking in Portion 5

(h)         Drainage works, backfilling, road works and watermains work and socket H piling in Portion 6a

(i)           Operation of HAC treatment facility in Portion 6b

(j)           Site formation, sheet piling, excavation and drainage works in Portion 7

(k)         Construction of retaining wall, RC construction of flushing water service reservoir and fresh water reservoir, pipe pile wall of WSD¡¦s maintenance access and backfilling works in Portion 8a

(l)           ELS for jacking pit at LWSC¡¦s car park and trenchless work, excavation and watermain construction and trial pit in Portion 8b

(m)       Sheet piling, excavation, drainage works and constructure of retaining wall, soil nail and watermain construction in Portion 9b

(n)         Stockpile of soil in Portion 9c

(o)         Excavation, drainage works, road construction and utilities works in Portion 10a

(p)         Sheet piling, excavation and drainage works in Portion 10b

(q)         Site clearance, tree felling, remove of existing structure in Portion 13

ND/2019/02

(a)           Pipe Jacking

(b)           Backfilling

(c)           Concreting

(d)           Bedding & Pipe Laying

(e)           ELS

(f)            Sheet Pile Installation

(g)           Cut and Fill of Slope

ND/2019/03

 

(a)        Portion 1 & Portion 1A

-            Road work at Yin Kong Road

-            Construction of Pai Lau

(b)     Portion 2 to Portion 20C

-          Erection of Permanent Boundary Structure

-          Construction of Type 1 Storage House

-          Construction of Type 2 Storage House

-          Construction of Tea House

-          Construction of Composting Facility

-          Construction works of Bird Hide

-          Construction works of Outdoor Classroom

-          Wetland Creation & Restoration works

-          Construction of Compacted Earth Path/ Walkway

-          Construction of Wetland Boardwalk

ND/2019/04

 

(a)           Tree Felling

(b)           Pile Cap

(c)           Bored Piling

(d)           Excavation

(e)           Sheet Piling

(f)            Drainage Works

(g)           Grouting

(h)           Road works

(i)            ELS

ND/2019/05

(a)           North Team Works

-            ELS works and Pile cap construction at B1-01M, B2-02, B2-03, C1-01a, C2-03b, C2-04b, C3-01b, D2-01

-            Pier construction at C1-01a C3-01b, C2-03b, C2-04b, D2-01 & E2-01.

-            Pier head construction at C3-01b, C1-01a & E2-01

-            Cross head construction at C2-02, C3-02.

-            Slope works, road works and drainage works at Jockey Club Road (3SW-C/F63), Tong Hang Junction and Portion VI (FS28 & 29)

(b)          Viaduct Works

-          Segment fabrication for bridge C2 & D1 & E1.

-          Segments erection for bridges C3, D1 and E1.

-          3rd set FT design and fabrication. To be used in Feb-2023.

-          4th set FT design and fabrication. To be used in May-2023.

-          Complete construction of pile cap D2-01 and installation of cast-in rotation bridge components.

-          Complete erection of tower crane at D2-02, and E2-02.

-          Complete segment erection for C4-02 T-Span.

-          Complete segment casting for E2-02 and E3-03.

(b)       South Team Works

-          TWSRW ¡V Road work (section ch 250 to 450).

-          TWSR (West) ¡V Slope work for FS06. Soil nail for FS04. 132KV ducts laying at FS04. Outage of 132 kv.

-          TWSR (East) ¡V Form D300 new road, BBI footing

-          HKY FB (East) ¡V Erection of steel bridge

-          HKY FB (West) ¡V Construction of LT2

-          E2-03 ¡V Pier construction.

-          D2-03 ¡V Pier construction.

-          E3-05M and E4-01 ¡V cap construction.

-          NB109 ¡V base slab construction.

ND/2019/06

The construction phase has been completed and handed over to AFCD since 4 April 2022.

ND/2019/07

(a)        Road works at Portion 1, 4 and 5

(b)        C&D waste disposal at Portion 1, 2, 4 and 5

(c)        Construction of box culvert at Portion 2

(d)        Filling works at Portion 2 and 4

(e)        Construction of site haul road at Portion 4

(f)         Drainage works, Sewerage works at Portion 1, 3, 4 and 5

(g)        Mini piling works at Portion 4

(h)        Construction of noise barrier at Portion 4 and 5

(i)         Waterworks at Portion 1